CHAPTER........
AN ACT relating to highways; providing for the prompt payment of subcontractors for the
construction and improvement of highways; and providing other matters properly
relating thereto.
THE PEOPLE OF THE STATE OF NEVADA, REPRESENTED IN
SENATE AND ASSEMBLY, DO ENACT AS FOLLOWS:
Section 1. NRS 408.383 is hereby amended to read as follows:
otherwise provided in9. A contractor shall disburse money paid to him pursuant to this
section, including any interest that the contractor receives, to his
subcontractors and suppliers within 15 days after he receives the money
in the proportion that the value of the work performed by each
subcontractor or the materials furnished by each supplier bears to the
total amount of the contract between the principal contractor and the
department.
10. Money payable to a subcontractor or supplier accrues interest at
a rate equal to the lowest daily prime rate at the three largest banks in the
United States on the date the subcontract or order for supplies was
executed plus 2 percent, from 15 days after the money was received by
the principal contractor until the date of payment.
11. If a contractor withholds more than 10 percent of a payment
required by subsection 9, the subcontractor or supplier may inform the
director in writing of the amount due. The director shall attempt to
resolve the dispute between the contractor and the subcontractor or
supplier within 20 working days after the date that the director receives
notice of the amount due. If the dispute is not resolved within 20 working
days after the date that the director receives notice of the amount due, the
contractor shall deposit the disputed amount in an escrow account that
bears interest. The contractor, subcontractor or supplier may pursue any
legal or equitable remedy to resolve the dispute over the amount due. The
director may not be made a party to any legal or equitable action brought
by the contractor, subcontractor or supplier.
~