Senate Bill No. 475–Committee on Government Affairs

CHAPTER........

AN ACT relating to public works; authorizing a public body to contract with a design-build

team or specialty contractor for the design and construction of a public work in

certain circumstances; authorizing a public body to contract with a nonprofit

organization for the design and construction of a project to restore, enhance or

develop wetlands; authorizing the department of transportation to contract with a

design-build team with respect to a project for the design and construction,

reconstruction or improvement of highways in certain circumstances; setting forth

the method in which proposals for a design-build contract must be solicited; setting

forth the method in which a design-build team must be selected; authorizing a

public body or the department of transportation to employ an architect or engineer to

oversee the construction of a public work or project; creating an interim advisory

committee to study the use of design-build contracting; and providing other matters

properly relating thereto.

 

 

THE PEOPLE OF THE STATE OF NEVADA, REPRESENTED IN

SENATE AND ASSEMBLY, DO ENACT AS FOLLOWS:

Section 1. Chapter 338 of NRS is hereby amended by adding thereto

the provisions set forth as sections 2 to 9, inclusive, of this act.

Sec. 2. 1. Except as otherwise provided in this section, a public

body shall contract with a prime contractor for the construction of a

public work for which the estimated cost exceeds $100,000.

2. A public body may contract with a design-build team for the

design and construction of a public work that is a discrete project if the

public body determines that:

(a) The public work is:

(1) A plant or facility for the treatment and pumping of water or the

treatment and disposal of wastewater or sewage, the estimated cost of

which exceeds $100,000,000; or

(2) Any other type of public work, except a stand-alone

underground utility project, the estimated cost of which exceeds

$30,000,000; and

(b) Contracting with a design-build team will enable the public body

to:

(1) Design and construct the public work at a cost that is

significantly lower than the cost that the public body would incur to

design and construct the public work using a different method;

(2) Design and construct the public work in a shorter time than

would be required to design and construct the public work using a

different method, if exigent circumstances require that the public work

be designed and constructed within a short time; or

(3) Ensure that the design and construction of the public work is

properly coordinated, if the public work is unique, highly technical and

complex in nature. 3. In a county whose population is 400,000 or more, a public body

that is responsible for financing public works may, for its own public

works and those financed by a different public body, including, without

limitation, an airport if the airport is owned and operated as a

department of the public body, contract with a design-build team once in

each fiscal year for the design and construction of a public work if the

public body determines that:

(a) The estimated cost of the public work is at least $5,000,000 but less

than $30,000,000; and

(b) Contracting with a design-build team will enable the public body

to:

(1) Design and construct the public work at a cost that is

significantly lower than the cost that the public body would incur to

design and construct the public work using a different method;

(2) Design and construct the public work in a shorter time than

would be required to design and construct the public work using a

different method, if exigent circumstances require that the public work

be designed and constructed within a short time; or

(3) Ensure that the design and construction of the public work is

properly coordinated, if the public work is unique, highly technical and

complex in nature.

4. Notwithstanding the provisions of subsections 1, 2 and 3, a public

body may contract with:

(a) A nonprofit organization for the design and construction of a

project to restore, enhance or develop wetlands.

(b) A prime contractor, specialty contractor or design-build team with

respect to a public work if the public body determines that the public

work is:

(1) Not part of a larger public work; and

(2) Limited in scope to:

(I) Removal of asbestos;

(II) Replacement of equipment or systems for heating, ventilation

and air-conditioning;

(III) Replacement of a roof;

(IV) Landscaping; or

(V) Restoration, enhancement or development of wetlands.

Sec. 3. 1. A public body shall not contract with a design-build team

with respect to a public work unless the governing body of the public

body makes the determinations, at a public hearing, that are required

pursuant to subsection 2, 3 or 4 of section 2 of this act, as applicable.

2. A public body that is required to hold a public hearing pursuant to

this section shall publish notice of the hearing at least once each week

for 3 consecutive weeks in:

(a) A newspaper of general circulation published in the county in

which the public work is proposed to be constructed or, if there is no suchnewspaper, in a newspaper of general circulation in the county published

in this state; and

(b) A newspaper of general circulation in this state.

Sec. 4. 1. A public body that is required to contract with a prime

contractor pursuant to subsection 1 of section 2 of this act or elects to

contract with a specialty contractor pursuant to subsection 4 of section 2

of this act shall select the prime contractor or specialty contractor, as

appropriate, in accordance with the procedures for bidding that are set

forth in:

(a) The provisions of sections 3 to 11, inclusive, of Assembly Bill No.

298 of this session; or

(b) NRS 338.140 to 338.147, inclusive, if the public body is a local

government that elects to award a contract for a public work in

accordance with paragraph (b) of subsection 1 of section 2 of Assembly

Bill No. 298 of this session.

2. A public body that contracts with a design-build team pursuant to

sections 2 and 3 of this act shall select the design-build team in

accordance with sections 5 to 8, inclusive, of this act.

Sec. 5. 1. A public body shall advertise for preliminary proposals

for the design and construction of a public work by a design-build team

at least twice each week for 3 consecutive weeks in:

(a) A newspaper of general circulation published in the county in

which the public work is proposed to be constructed or, if there is no such

newspaper, in a newspaper of general circulation in the county published

in this state; and

(b) A newspaper of general circulation in this state.

2. A request for preliminary proposals published pursuant to

subsection 1 must include, without limitation:

(a) A description of the public work to be designed and constructed;

(b) Separate estimates of the costs of designing and constructing the

public work;

(c) The dates on which it is anticipated that the separate phases of the

design and construction of the public work will begin and end;

(d) A statement setting forth the place and time in which a design

-build team desiring to submit a proposal for the public work may obtain

the information necessary to submit a proposal, including, without

limitation, the extent to which designs must be completed for both

preliminary and final proposals and any other requirements for the

design and construction of the public work that the public body

determines to be necessary;

(e) A list of the requirements set forth in section 6 of this act;

(f) A list of the factors that the public body will use to evaluate design

-build teams who submit a proposal for the public work, including,

without limitation:

(1) The relative weight to be assigned to each factor; an

d (2) A disclosure of whether the factors that are not related to cost

are, when considered as a group, more or less important in the process of

evaluation than the factor of cost;

(g) Notice that a design-build team desiring to submit a proposal for

the public work must include with its proposal the information used by

the public body to determine finalists among the design-build teams

submitting proposals pursuant to subsection 2 of section 7 of this act and

a description of that information;

(h) A statement that a design-build team whose prime contractor

holds a certificate of eligibility to receive a preference in bidding on

public works issued pursuant to NRS 338.147 should submit a copy of

the certificate of eligibility with its proposal;

(i) A statement as to whether a design-build team that is selected as a

finalist pursuant to section 7 of this act but is not awarded the design-

build contract pursuant to section 8 of this act will be partially

reimbursed for the cost of preparing a final proposal and, if so, an

estimate of the amount of the partial reimbursement; and

(j) The date by which preliminary proposals must be submitted to the

public body, which must not be less than 30 days or more than 60 days

after the date on which the request for preliminary proposals is first

published in a newspaper pursuant to subsection 1.

Sec. 6. To qualify to participate in a project for the design and

construction of a public work, a design-build team must:

1. Obtain a performance bond and payment bond as required

pursuant to NRS 339.025;

2. Obtain insurance covering general liability and liability for errors

and omissions;

3. Not have been found liable for breach of contract with respect to a

previous project, other than a breach for legitimate cause;

4. Not have been disqualified from being awarded a contract

pursuant to NRS 338.017, 338.145 or 408.333; and

5. Ensure that the members of the design-build team possess the

licenses and certificates required to carry out the functions of their

respective professions within this state.

Sec. 7. 1. At least 30 days after the date by which preliminary

proposals must be submitted to the public body, the public body shall

select at least three but not more than five finalists from among the

design-build teams that submitted preliminary proposals. If the public

body does not receive at least three preliminary proposals from design-

build teams that the public body determines to be qualified pursuant to

this section and section 6 of this act, the public body may not contract

with a design-build team for the design and construction of the public

work.

2. The public body shall select finalists pursuant to subsection 1 by

: (a) Verifying that each design-build team which submitted a

preliminary proposal satisfies the requirements of section 6 of this act;

and

(b) Conducting an evaluation of the qualifications of each design

-build team that submitted a preliminary proposal, including, without

limitation, an evaluation of:

(1) The professional qualifications and experience of the members

of the design-build team;

(2) The performance history of the members of the design-build

team concerning other recent, similar projects completed by those

members, if any;

(3) The safety programs established and the safety records

accumulated by the members of the design-build team; and

(4) The proposed plan of the design-build team to manage the

design and construction of the public work that sets forth in detail the

ability of the design-build team to design and construct the public work.

Sec. 8. 1. After selecting the finalists pursuant to section 7 of this

act, the public body shall provide to each finalist a request for final

proposals for the public work. The request for final proposals must:

(a) Set forth the factors that the public body will use to select a design

-build team to design and construct the public work, including the relative

weight to be assigned to each factor; and

(b) Set forth the date by which final proposals must be submitted to

the public body.

2. A final proposal submitted by a design-build team pursuant to this

section must be prepared thoroughly, be responsive to the criteria that the

public body will use to select a design-build team to design and construct

the public work described in subsection 1 and comply with the provisions

of NRS 338.144. If the cost of construction is a factor in the selection of

a design-build team, a design-build team whose prime contractor has

submitted with its proposal a certificate of eligibility to receive a

preference in bidding on public works issued pursuant to NRS 338.147 or

section 11 of Assembly Bill No. 298 of this session shall be deemed to

have submitted a better proposal than a competing design-build team

whose prime contractor has not submitted such a certificate of eligibility

if the amount proposed by the design-build team is not more than 5

percent higher than the amount proposed by the competing design-build

team.

3. At least 30 days after receiving the final proposals for the public

work, the public body shall:

(a) Select the most cost-effective and responsive final proposal, using

the criteria set forth pursuant to subsection 1; or

(b) Reject all the final proposals.

4. If a public body selects a final proposal pursuant to paragraph (a)

of subsection 3, the public body shall, at its next regularly scheduled

meeting: (a) Review and ratify the selection.

(b) Award the design-build contract to the design-build team whose

proposal is selected.

(c) Partially reimburse the unsuccessful finalists if partial

reimbursement was provided for in the request for preliminary proposals

pursuant to paragraph (i) of subsection 2 of section 5 of this act. The

amount of reimbursement must not exceed, for each unsuccessful

finalist, three percent of the total amount to be paid to the design-build

team as set forth in the design-build contract.

(d) Make available to the public a summary setting forth the factors

used by the public body to select the successful design-build team and the

ranking of the design-build teams who submitted final proposals. The

public body shall not release to a third party, or otherwise make public,

financial or proprietary information submitted by a design-build team.

5. A contract awarded pursuant to this section must specify:

(a) An amount that is the maximum amount that the public body will

pay for the performance of all the work required by the contract,

excluding any amount related to costs that may be incurred as a result of

unexpected conditions or occurrences as authorized by the contract;

(b) An amount that is the maximum amount that the public body will

pay for the performance of the professional services required by the

contract; and

(c) A date by which performance of the work required by the contract

must be completed.

6. A design-build team to whom a contract is awarded pursuant to

this section shall:

(a) Assume overall responsibility for ensuring that the design and

construction of the public work is completed in a satisfactory manner;

and

(b) Use the work force of the prime contractor on the design-build

team to construct at least 15 percent of the public work.

Sec. 9. A public body may employ a registered architect or licensed

professional engineer as a consultant to assist the public body in

overseeing the construction of a public work. An architect or engineer so

employed shall not:

1. Construct the public work; or

2. Assume overall responsibility for ensuring that the construction of

the public work is completed in a satisfactory manner.

Sec. 10. NRS 338.010 is hereby amended to read as follows:

338.010 As used in this chapter:

1. "Day labor" means all cases where public bodies, their officers,

agents or employees, hire, supervise and pay the wages thereof directly to a

workman or workmen employed by them on public works by the day and

not under a contract in writing. 2. "Design-build contract" means a contract between a public body

and a design-build team in which the design-build team agrees to design

and construct a public work.

3. "Design-build team" means an entity that consists of:

(a) At least one person who is licensed as a general engineering

contractor or a general building contractor pursuant to NRS 624.230 to

624.320, inclusive; and

(b) For a public work that consists of:

(1) A building and its site, at least one person who holds a

certificate of registration to practice architecture pursuant to chapter 623

of NRS.

(2) Anything other than a building and its site, at least one person

who holds a certificate of registration to practice architecture pursuant to

chapter 623 of NRS or is licensed as a professional engineer pursuant to

chapter 625 of NRS.

4. "Design professional" means a person with a professional license

or certificate issued pursuant to chapter 623, 623A or 625 of NRS.

5. "Eligible bidder" means a person who is:

(a) Found to be a responsible and responsive contractor by a local

government which requests bids for a public work in accordance with

paragraph (b) of subsection 1 of section 2 of [this act;] Assembly Bill No.

298 of this session; or

(b) Determined by a public body which awarded a contract for a public

work pursuant to sections 3 to 11, inclusive, of [this act,] Assembly Bill No.

298 of this session, to be qualified to bid on that contract pursuant to

section 5 of [this act] Assembly Bill No. 298 of this session or was exempt

from meeting such qualifications pursuant to section 6 of [this act.

3.] Assembly Bill No. 298 of this session.

6. "Local government" means every political subdivision or other

entity which has the right to levy or receive money from ad valorem or

other taxes or any mandatory assessments, and includes, without limitation,

counties, cities, towns, boards, school districts and other districts organized

pursuant to chapters 244A, 309, 318, 379, 474, 541, 543 and 555 of NRS,

NRS 450.550 to 450.750, inclusive, and any agency or department of a

county or city which prepares a budget separate from that of the parent

political subdivision.

[4.] 7. "Offense" means failing to:

(a) Pay the prevailing wage required pursuant to this chapter;

(b) Pay the contributions for unemployment compensation required

pursuant to chapter 612 of NRS; or

(c) Provide and secure compensation for employees required pursuant to

chapters 616A to 617, inclusive, of NRS.

[5.] 8. "Prime contractor" means a person who:

(a) Contracts to [complete] construct an entire project;

(b) Coordinates all work performed on the entire project

; (c) Uses his own work force to perform all or a part of the construction,

repair or reconstruction of the project; and

(d) Contracts for the services of any subcontractor or independent

contractor or is responsible for payment to any contracted subcontractors or

independent contractors.

[6.] 9. "Public body" means the state, county, city, town, school

district or any public agency of this state or its political subdivisions

sponsoring or financing a public work.

[7.] 10. "Public work" means any project for the new construction,

repair or reconstruction of:

(a) A project financed in whole or in part from public money for:

(1) Public buildings;

(2) Jails and prisons;

(3) Public roads;

(4) Public highways;

(5) Public streets and alleys;

(6) Public utilities which are financed in whole or in part by public

money;

(7) Publicly owned water mains and sewers;

(8) Public parks and playgrounds;

(9) Public convention facilities which are financed at least in part with

public funds; and

(10) Any other publicly owned works and property whose cost as a

whole exceeds $20,000.

Each separate unit that is a part of a project is included in the cost of the

project to determine whether a project meets that threshold.

(b) A building for the University and Community College System of

Nevada of which 25 percent or more of the costs of the building as a whole

are paid from money appropriated by this state or from federal money.

[8.] 11. "Specialty contractor" means a contractor whose operations

as such are the performance of construction work requiring special skill

and whose principal contracting business involves the use of specialized

building trades or crafts.

12. "Stand-alone underground utility project" means an

underground utility project that is not integrated into a larger project,

including, without limitation:

(a) An underground sewer line or an underground pipeline for the

conveyance of water, including facilities appurtenant thereto; and

(b) A project for the construction or installation of a storm drain,

including facilities appurtenant thereto,

that is not located at the site of a public work for the design and

construction of which a public body is authorized to contract with a

design-build team pursuant to subsection 2 of section 2 of this act.

13. "Wages" means:

(a) The basic hourly rate of pay; an

d (b) The amount of pension, health and welfare, vacation and holiday

pay, the cost of apprenticeship training or other similar programs or other

bona fide fringe benefits which are a benefit to the workman.

[9.] 14. "Workman" means a skilled mechanic, skilled workman,

semiskilled mechanic, semiskilled workman or unskilled workman. The

term does not include a design professional . [as that term is defined in

NRS 338.155.]

Sec. 11. NRS 338.143 is hereby amended to read as follows:

338.143 1. Except as otherwise provided in subsection 6 and NRS

338.1907, a local government that awards a contract for the construction,

alteration or repair of a public work in accordance with paragraph (b) of

subsection 1 of section 2 of [this act,] Assembly Bill No. 298 of this

session, or a public officer, public employee or other person responsible for

awarding a contract for the construction, alteration or repair of a public

work who represents that local government, shall not:

(a) Commence such a project for which the estimated cost exceeds

$100,000 unless it advertises in a newspaper of general circulation in this

state for bids for the project; or

(b) Divide such a project into separate portions to avoid the

requirements of paragraph (a).

2. Except as otherwise provided in subsection 6, a local government

that maintains a list of properly licensed contractors who are interested in

receiving offers to bid on public works projects for which the estimated

cost is more than $25,000 but less than $100,000 shall solicit bids from not

more than three of the contractors on the list for a contract of that value for

the construction, alteration or repair of a public work. The local

government shall select contractors from the list in such a manner as to

afford each contractor an equal opportunity to bid on a public works

project. A properly licensed contractor must submit a written request

annually to the local government to remain on the list. Offers for bids

which are made pursuant to this subsection must be sent by certified mail.

3. Approved plans and specifications for the bids must be on file at a

place and time stated in the advertisement for the inspection of all persons

desiring to bid thereon and for other interested persons. Contracts for the

project must be awarded on the basis of bids received.

4. Any bids received in response to an advertisement for bids may be

rejected if the person responsible for awarding the contract determines that:

(a) The bidder is not responsive or responsible;

(b) The quality of the services, materials, equipment or labor offered

does not conform to the approved plan or specifications; or

(c) The public interest would be served by such a rejection.

5. Before a local government may commence a project subject to the

provisions of this section, based upon a determination that the public

interest would be served by rejecting any bids received in response to an

advertisement for bids, it shall prepare and make available for public

inspection a written statement containing: (a) A list of all persons, including supervisors, whom the local

government intends to assign to the project, together with their

classifications and an estimate of the direct and indirect costs of their labor;

(b) A list of all equipment that the local government intends to use on

the project, together with an estimate of the number of hours each item of

equipment will be used and the hourly cost to use each item of equipment;

(c) An estimate of the cost of administrative support for the persons

assigned to the project;

(d) An estimate of the total cost of the project; and

(e) An estimate of the amount of money the local government expects to

save by rejecting the bids and performing the project itself.

6. This section does not apply to:

(a) Any utility subject to the provisions of chapter 318 or 710 of NRS;

(b) Any work of construction, reconstruction, improvement and

maintenance of highways subject to NRS 408.323 or 408.327;

(c) Normal maintenance of the property of a school district; [or]

(d) The Las Vegas Valley water district created pursuant to chapter 167,

Statutes of Nevada 1947, the Moapa Valley water district created pursuant

to chapter 477, Statutes of Nevada 1983 or the Virgin Valley water district

created pursuant to chapter 100, Statutes of Nevada 1993 [.] ; or

(e) The design and construction of a public work for which a public

body contracts with a design-build team pursuant to sections 2 to 9,

inclusive, of this act.

Sec. 12. NRS 338.143 is hereby amended to read as follows:

338.143 1. Except as otherwise provided in subsection 6, a local

government that awards a contract for the construction, alteration or repair

of a public work in accordance with paragraph (b) of subsection 1 of

section 2 of [this act,] Assembly Bill No. 298 of this session, or a public

officer, public employee or other person responsible for awarding a

contract for the construction, alteration or repair of a public work who

represents that local government, shall not:

(a) Commence such a project for which the estimated cost exceeds

$100,000 unless it advertises in a newspaper of general circulation in this

state for bids for the project; or

(b) Divide such a project into separate portions to avoid the

requirements of paragraph (a).

2. Except as otherwise provided in subsection 6, a local government

that maintains a list of properly licensed contractors who are interested in

receiving offers to bid on public works projects for which the estimated

cost is more than $25,000 but less than $100,000 shall solicit bids from not

more than three of the contractors on the list for a contract of that value for

the construction, alteration or repair of a public work. The local

government shall select contractors from the list in such a manner as to

afford each contractor an equal opportunity to bid on a public works

project. A properly licensed contractor must submit a written requestannually to the local government to remain on the list. Offers for bids

which are made pursuant to this subsection must be sent by certified mail.

3. Approved plans and specifications for the bids must be on file at a

place and time stated in the advertisement for the inspection of all persons

desiring to bid thereon and for other interested persons. Contracts for the

project must be awarded on the basis of bids received.

4. Any bids received in response to an advertisement for bids may be

rejected if the person responsible for awarding the contract determines that:

(a) The bidder is not responsive or responsible;

(b) The quality of the services, materials, equipment or labor offered

does not conform to the approved plan or specifications; or

(c) The public interest would be served by such a rejection.

5. Before a local government may commence a project subject to the

provisions of this section, based upon a determination that the public

interest would be served by rejecting any bids received in response to an

advertisement for bids, it shall prepare and make available for public

inspection a written statement containing:

(a) A list of all persons, including supervisors, whom the local

government intends to assign to the project, together with their

classifications and an estimate of the direct and indirect costs of their labor;

(b) A list of all equipment that the local government intends to use on

the project, together with an estimate of the number of hours each item of

equipment will be used and the hourly cost to use each item of equipment;

(c) An estimate of the cost of administrative support for the persons

assigned to the project;

(d) An estimate of the total cost of the project; and

(e) An estimate of the amount of money the local government expects to

save by rejecting the bids and performing the project itself.

6. This section does not apply to:

(a) Any utility subject to the provisions of chapter 318 or 710 of NRS;

(b) Any work of construction, reconstruction, improvement and

maintenance of highways subject to NRS 408.323 or 408.327;

(c) Normal maintenance of the property of a school district; [or]

(d) The Las Vegas Valley water district created pursuant to chapter 167,

Statutes of Nevada 1947, the Moapa Valley water district created pursuant

to chapter 477, Statutes of Nevada 1983 or the Virgin Valley water district

created pursuant to chapter 100, Statutes of Nevada 1993.

Sec. 13. NRS 338.147 is hereby amended to read as follows:

338.147 1. Except as otherwise provided in NRS 338.143 [,] and

sections 2 to 9, inclusive, of this act, a local government shall award a

contract for a public work to the contractor who submits the best bid.

2. Except as otherwise provided in subsection 8 or limited by

subsection 9, for the purposes of this section, a contractor who:

(a) Has been found to be a responsible and responsive contractor by the

local government; and (b) At the time he submits his bid, provides to the local government a

copy of a certificate of eligibility to receive a preference in bidding on

public works issued to him by the state contractors' board pursuant to

subsection 3,

shall be deemed to have submitted a better bid than a competing contractor

who has not provided a copy of such a valid certificate of eligibility if the

amount of his bid is not more than 5 percent higher than the amount bid by

the competing contractor.

3. The state contractors' board shall issue a certificate of eligibility to

receive a preference in bidding on public works to a general contractor who

is licensed pursuant to the provisions of chapter 624 of NRS and submits to

the board an affidavit from a certified public accountant setting forth that

the general contractor has:

(a) Paid:

(1) The sales and use taxes imposed pursuant to chapters 372, 374

and 377 of NRS on materials used for construction in this state, including,

without limitation, construction that is undertaken or carried out on land

within the boundaries of this state that is managed by the Federal

Government or is on an Indian reservation or Indian colony, of not less than

$5,000 for each consecutive 12-month period for 60 months immediately

preceding the submission of the affidavit from the certified public

accountant;

(2) The motor vehicle privilege tax imposed pursuant to chapter 371

of NRS on the vehicles used in the operation of his business in this state of

not less than $5,000 for each consecutive 12-month period for 60 months

immediately preceding the submission of the affidavit from the certified

public accountant; or

(3) Any combination of such sales and use taxes and motor vehicle

privilege tax; or

(b) Acquired, by inheritance, gift or transfer through a stock option plan

for employees, all the assets and liabilities of a viable, operating

construction firm that possesses a:

(1) License as a general contractor pursuant to the provisions of

chapter 624 of NRS; and

(2) Certificate of eligibility to receive a preference in bidding on

public works.

4. For the purposes of complying with the requirements set forth in

paragraph (a) of subsection 3, a general contractor shall be deemed to have

paid:

(a) Sales and use taxes and motor vehicle privilege taxes paid in this

state by an affiliate or parent company of the contractor, if the affiliate or

parent company is also a general contractor; and

(b) Sales and use taxes paid in this state by a joint venture in which the

contractor is a participant, in proportion to the amount of interest the

contractor has in the joint venture. 5. A contractor who has received a certificate of eligibility to receive a

preference in bidding on public works from the state contractors' board

pursuant to subsection 3 shall, at the time for the annual renewal of his

contractors' license pursuant to NRS 624.283, submit to the board an

affidavit from a certified public accountant setting forth that the contractor

has, during the immediately preceding 12 months, paid the taxes required

pursuant to paragraph (a) of subsection 3 to maintain his eligibility to hold

such a certificate.

6. A contractor who fails to submit an affidavit to the board pursuant to

subsection 5 ceases to be eligible to receive a preference in bidding on

public works unless he reapplies for and receives a certificate of eligibility

pursuant to subsection 3.

7. If a contractor who applies to the state contractors' board for a

certificate of eligibility to receive a preference in bidding on public works

submits false information to the board regarding the required payment of

taxes, the contractor is not eligible to receive a preference in bidding on

public works for a period of 5 years after the date on which the board

becomes aware of the submission of the false information.

8. If any federal statute or regulation precludes the granting of federal

assistance or reduces the amount of that assistance for a particular public

work because of the provisions of subsection 2, those provisions do not

apply insofar as their application would preclude or reduce federal

assistance for that work. The provisions of subsection 2 do not apply to any

contract for a public work which is expected to cost less than $250,000.

9. [If] Except as otherwise provided in subsection 2 of section 8 of

this act and subsection 2 of section 27 of this act, if a bid is submitted by

two or more contractors as a joint venture or by one of them as a joint

venturer, the provisions of subsection 2 apply only if both or all of the joint

venturers separately meet the requirements of that subsection.

10. The state contractors' board shall adopt regulations and may assess

reasonable fees relating to the certification of contractors for a preference

in bidding on public works.

11. A person or entity who believes that a contractor wrongfully holds

a certificate of eligibility to receive a preference in bidding on public works

may challenge the validity of the certificate by filing a written objection

with the public body to which the contractor has submitted a bid or

proposal on a contract for the completion of a public work. A written

objection authorized pursuant to this subsection must:

(a) Set forth proof or substantiating evidence to support the belief of the

person or entity that the contractor wrongfully holds a certificate of

eligibility to receive a preference in bidding on public works; and

(b) Be filed with the public body at or after the time at which the

contractor submitted the bid or proposal to the public body and before the

time at which the public body awards the contract for which the bid or

proposal was submitted. 12. If a public body receives a written objection pursuant to subsection

11, the public body shall determine whether the objection is accompanied

by the proof or substantiating evidence required pursuant to paragraph (a)

of that subsection. If the public body determines that the objection is not

accompanied by the required proof or substantiating evidence, the public

body shall dismiss the objection and may proceed immediately to award the

contract. If the public body determines that the objection is accompanied

by the required proof or substantiating evidence, the public body shall

determine whether the contractor qualifies for the certificate pursuant to the

provisions of this section and may proceed to award the contract

accordingly.

Sec. 13.5. NRS 338.147 is hereby amended to read as follows:

338.147 1. Except as otherwise provided in NRS 338.143 , [and

sections 2 to 9, inclusive, of this act,] a local government shall award a

contract for a public work to the contractor who submits the best bid.

2. Except as otherwise provided in subsection 8 or limited by

subsection 9, for the purposes of this section, a contractor who:

(a) Has been found to be a responsible and responsive contractor by the

local government; and

(b) At the time he submits his bid, provides to the local government a

copy of a certificate of eligibility to receive a preference in bidding on

public works issued to him by the state contractors' board pursuant to

subsection 3,

shall be deemed to have submitted a better bid than a competing contractor

who has not provided a copy of such a valid certificate of eligibility if the

amount of his bid is not more than 5 percent higher than the amount bid by

the competing contractor.

3. The state contractors' board shall issue a certificate of eligibility to

receive a preference in bidding on public works to a general contractor who

is licensed pursuant to the provisions of chapter 624 of NRS and submits to

the board an affidavit from a certified public accountant setting forth that

the general contractor has:

(a) Paid:

(1) The sales and use taxes imposed pursuant to chapters 372, 374

and 377 of NRS on materials used for construction in this state, including,

without limitation, construction that is undertaken or carried out on land

within the boundaries of this state that is managed by the Federal

Government or is on an Indian reservation or Indian colony, of not less than

$5,000 for each consecutive 12-month period for 60 months immediately

preceding the submission of the affidavit from the certified public

accountant;

(2) The motor vehicle privilege tax imposed pursuant to chapter 371

of NRS on the vehicles used in the operation of his business in this state of

not less than $5,000 for each consecutive 12-month period for 60 months

immediately preceding the submission of the affidavit from the certified

public accountant; or (3) Any combination of such sales and use taxes and motor vehicle

privilege tax; or

(b) Acquired, by inheritance, gift or transfer through a stock option plan

for employees, all the assets and liabilities of a viable, operating

construction firm that possesses a:

(1) License as a general contractor pursuant to the provisions of

chapter 624 of NRS; and

(2) Certificate of eligibility to receive a preference in bidding on

public works.

4. For the purposes of complying with the requirements set forth in

paragraph (a) of subsection 3, a general contractor shall be deemed to have

paid:

(a) Sales and use taxes and motor vehicle privilege taxes paid in this

state by an affiliate or parent company of the contractor, if the affiliate or

parent company is also a general contractor; and

(b) Sales and use taxes paid in this state by a joint venture in which the

contractor is a participant, in proportion to the amount of interest the

contractor has in the joint venture.

5. A contractor who has received a certificate of eligibility to receive a

preference in bidding on public works from the state contractors' board

pursuant to subsection 3 shall, at the time for the annual renewal of his

contractors' license pursuant to NRS 624.283, submit to the board an

affidavit from a certified public accountant setting forth that the contractor

has, during the immediately preceding 12 months, paid the taxes required

pursuant to paragraph (a) of subsection 3 to maintain his eligibility to hold

such a certificate.

6. A contractor who fails to submit an affidavit to the board pursuant to

subsection 5 ceases to be eligible to receive a preference in bidding on

public works unless he reapplies for and receives a certificate of eligibility

pursuant to subsection 3.

7. If a contractor who applies to the state contractors' board for a

certificate of eligibility to receive a preference in bidding on public works

submits false information to the board regarding the required payment of

taxes, the contractor is not eligible to receive a preference in bidding on

public works for a period of 5 years after the date on which the board

becomes aware of the submission of the false information.

8. If any federal statute or regulation precludes the granting of federal

assistance or reduces the amount of that assistance for a particular public

work because of the provisions of subsection 2, those provisions do not

apply insofar as their application would preclude or reduce federal

assistance for that work. The provisions of subsection 2 do not apply to any

contract for a public work which is expected to cost less than $250,000.

9. [Except as otherwise provided in subsection 2 of section 8 of this act

and subsection 2 of section 27 of this act, if] If a bid is submitted by two or

more contractors as a joint venture or by one of them as a joint venturer,the provisions of subsection 2 apply only if both or all of the joint venturers

separately meet the requirements of that subsection.

10. The state contractors' board shall adopt regulations and may assess

reasonable fees relating to the certification of contractors for a preference

in bidding on public works.

11. A person or entity who believes that a contractor wrongfully holds

a certificate of eligibility to receive a preference in bidding on public works

may challenge the validity of the certificate by filing a written objection

with the public body to which the contractor has submitted a bid or

proposal on a contract for the completion of a public work. A written

objection authorized pursuant to this subsection must:

(a) Set forth proof or substantiating evidence to support the belief of the

person or entity that the contractor wrongfully holds a certificate of

eligibility to receive a preference in bidding on public works; and

(b) Be filed with the public body at or after the time at which the

contractor submitted the bid or proposal to the public body and before the

time at which the public body awards the contract for which the bid or

proposal was submitted.

12. If a public body receives a written objection pursuant to subsection

11, the public body shall determine whether the objection is accompanied

by the proof or substantiating evidence required pursuant to paragraph (a)

of that subsection. If the public body determines that the objection is not

accompanied by the required proof or substantiating evidence, the public

body shall dismiss the objection and may proceed immediately to award the

contract. If the public body determines that the objection is accompanied

by the required proof or substantiating evidence, the public body shall

determine whether the contractor qualifies for the certificate pursuant to the

provisions of this section and may proceed to award the contract

accordingly.

Sec. 14. NRS 338.155 is hereby amended to read as follows:

338.155 [1.] If a public body enters into a contract with a design

professional who is not a member of a design-build team for the provision

of services in connection with a public work, the contract:

[(a)] 1. Must set forth:

[(1)] (a) The specific period within which the public body must pay

the design professional.

[(2)] (b) The specific period and manner in which the public body

may dispute a payment or portion thereof that the design professional

alleges is due.

[(3)] (c) The terms of any penalty that will be imposed upon the

public body if the public body fails to pay the design professional within

the specific period set forth in the contract pursuant to [subparagraph (1).

(4)] paragraph (a).

(d) That the prevailing party in an action to enforce the contract is

entitled to reasonable attorney's fees and costs. [(b)] 2. May set forth the terms of any discount that the public body

will receive if the public body pays the design professional within the

specific period set forth in the contract pursuant to [subparagraph (1) of]

paragraph (a) [.

2. As used in this section, "design professional" means a person with a

professional license or certificate issued pursuant to chapter 623, 623A or

625 of NRS.] of subsection 1.

Sec. 14.5. NRS 341.161 is hereby amended to read as follows:

341.161 1. The board may, with the approval of the interim finance

committee when the legislature is not in regular or special session, or with

the approval of the legislature by concurrent resolution when the legislature

is in regular or special session, let to a contractor licensed under chapter

624 of NRS a contract for services which assist the architect in the design

of a project of capital improvement. The board shall for that purpose

participate in the development of plans, outlines of specifications and

estimates of costs.

2. The board shall adopt regulations establishing procedures for:

(a) The determination of the qualifications of contractors to bid for

contracts for services described in subsection 1.

(b) The bidding and awarding of such contracts, subject to the

provisions of subsection 3.

(c) The awarding of construction contracts [, subject to the provisions of

subsection 4,] based on a final cost of the project which the contractor

guarantees will not be exceeded.

(d) The scheduling and controlling of projects.

3. Bids on contracts for services which assist the architect in the design

of a project of capital improvement must state separately the contractor's

cost for:

(a) Assisting the architect in the design of the project.

(b) Obtaining all bids for subcontracts.

(c) Administering the construction contract.

4. [A contractor who is:

(a) Qualified under the regulations of the board to bid for a contract for

services described in subsection 1; and

(b) Awarded that contract,

is entitled to be awarded the construction contract for the project if his

work under the contract for services is satisfactory to the board and he

guarantees a final cost for the project which the board is willing to accept.

5.] A person who furnishes services under a contract awarded pursuant

to subsection 1 is a contractor subject to all provisions pertaining to a

contractor in Title 28 of NRS.

Sec. 15. Chapter 408 of NRS is hereby amended by adding thereto the

provisions set forth as sections 16 to 28, inclusive, of this act. Sec. 16. As used in sections 16 to 28, inclusive, of this act, unless the

context otherwise requires, the words and terms defined in sections 17 to

20, inclusive, of this act have the meanings ascribed to them in those

sections.

Sec. 17. "Design-build contract" means a contract between the

department and a design-build team in which the design-build team

agrees to design and construct a project.

Sec. 18. "Design-build team" means an entity that consists of:

1. At least one person who is licensed as a general engineering

contractor or a general building contractor pursuant to NRS 624.230 to

624.320, inclusive; and

2. At least one person who holds a certificate of registration to

practice architecture pursuant to chapter 623 of NRS or is licensed as a

professional engineer pursuant to chapter 625 of NRS.

Sec. 19. "Prime contractor" means a person who:

1. Contracts to construct an entire project;

2. Coordinates all work performed on the entire project;

3. Uses his own workforce to perform all or a part of the

construction of the project; and

4. Contracts for the services of any subcontractor or independent

contractor or is responsible for payment to any contracted subcontractors

or independent contractors.

Sec. 20. "Project" means a project for the construction,

reconstruction or improvement of a highway.

Sec. 21. 1. The department may contract with a design-build team

for the design and construction of a project if the department determines

that:

(a) Except as otherwise provided in subsection 2, the estimated cost of

the project exceeds $30,000,000; and

(b) Contracting with a design-build team will enable the department

to:

(1) Design and construct the project at a cost that is significantly

lower than the cost that the department would incur to design and

construct the project using a different method;

(2) Design and construct the project in a shorter time than would be

required to complete the project using a different method, if exigent

circumstances require that the project be designed and constructed

within a short time; or

(3) Ensure that the design and construction of the project is

properly coordinated, if the project is unique, highly technical and

complex in nature.

2. Notwithstanding the provisions of subsection 1, the department

may, once in each fiscal year, contract with a design-build team for the

design and construction of a project the estimated cost of which is at least

$5,000,000 but less than $30,000,000 if the department makes thedeterminations otherwise required pursuant to paragraph (b) of

subsection 1.

Sec. 22. 1. The department shall not contract with a design-build

team with respect to a project unless the board makes the determinations,

at a public meeting, that are required pursuant to section 21 of this act.

2. If the department is required to hold a public meeting pursuant to

this section, the department shall publish notice of the meeting at least

once each week for 3 consecutive weeks in:

(a) A newspaper of general circulation published in each county in

which the project is proposed to be constructed or, if there is no such

newspaper, in a newspaper of general circulation in each county

published in this state; and

(b) A newspaper of general circulation in this state.

Sec. 23. If the department desires to contract with a design-build

team pursuant to sections 21 and 22 of this act, the department must

select the design-build team in accordance with sections 24 to 27,

inclusive, of this act.

Sec. 24. 1. The department shall advertise for preliminary

proposals for the design and construction of a project by a design-build

team at least twice each week for 3 consecutive weeks in:

(a) A newspaper of general circulation published in each county in

which the project is proposed to be constructed or, if there is no such

newspaper, in a newspaper of general circulation in each county

published in this state; and

(b) A newspaper of general circulation in this state.

2. A request for preliminary proposals published pursuant to

subsection 1 must include, without limitation:

(a) A description of the proposed project;

(b) Separate estimates of the costs of designing and constructing the

project;

(c) The dates on which it is anticipated that the separate phases of the

design and construction of the project will begin and end;

(d) A statement setting forth the place and time in which a design

-build team desiring to submit a proposal for the project may obtain the

information necessary to submit a proposal, including, without

limitation, the extent to which designs must be completed for both

preliminary and final proposals and any other requirements for the

design and construction of the project that the department determines to

be necessary;

(e) A list of the requirements set forth in section 25 of this act;

(f) A list of the factors that the department will use to evaluate design

-build teams who submit a proposal for the project, including, without

limitation:

(1) The relative weight to be assigned to each factor; an

d (2) A disclosure of whether the factors that are not related to cost

are, when considered as a group, more or less important in the process of

evaluation than the factor of cost;

(g) Notice that a design-build team desiring to submit a proposal for

the project must include with its proposal the information used by the

department to determine finalists among the design-build teams

submitting proposals pursuant to subsection 2 of section 26 of this act

and a description of that information;

(h) A statement that a design-build team whose prime contractor

holds a certificate of eligibility to receive a preference in bidding on

public works issued pursuant to NRS 338.147 should submit a copy of

the certificate of eligibility with its proposal;

(i) A statement as to whether a bidding design-build team that is

selected as a finalist pursuant to section 26 of this act but is not awarded

the design-build contract pursuant to section 27 of this act will be

partially reimbursed for the cost of preparing a final proposal and, if so,

an estimate of the amount of the partial reimbursement; and

(j) The date by which preliminary proposals must be submitted to the

department, which must not be less than 30 days or more than 60 days

after the date on which the request for preliminary proposals is first

published in a newspaper pursuant to subsection 1.

Sec. 25. To qualify to participate in the design and construction of a

project for the department, a design-build team must:

1. Obtain a performance bond and payment bond as the department

may require;

2. Obtain insurance covering general liability and liability for errors

and omissions;

3. Not have been found liable for breach of contract with respect to a

previous project, other than a breach for legitimate cause;

4. Not have been disqualified from being awarded a contract

pursuant to NRS 338.017, 338.145 or 408.333; and

5. Ensure that the members of the design-build team possess the

licenses and certificates required to carry out the functions of their

respective professions within this state.

Sec. 26. 1. At least 30 days after the date by which preliminary

proposals must be submitted to the department, the department shall

select at least three but not more than five finalists from among the

design-build teams that submitted preliminary proposals. If the

department does not receive at least three preliminary proposals from

design-build teams that the department determines to be qualified

pursuant to this section and section 25 of this act, the department may

not contract with a design-build team for the design and construction of

the project.

2. The department shall select finalists pursuant to subsection 1 by

: (a) Verifying that each design-build team which submitted a

preliminary proposal satisfies the requirements of section 25 of this act;

and

(b) Conducting an evaluation of the qualifications of each design

-build team that submitted a preliminary proposal, including, without

limitation, an evaluation of:

(1) The professional qualifications and experience of the members

of the design-build team;

(2) The performance history of the members of the design-build

team concerning other recent, similar projects completed by those

members, if any;

(3) The safety programs established and the safety records

accumulated by the members of the design-build team; and

(4) The proposed plan of the design-build team to manage the

design and construction of the project that sets forth in detail the ability

of the design-build team to design and construct the project.

Sec. 27. 1. After selecting the finalists pursuant to section 26 of

this act, the department shall provide to each finalist a request for final

proposals for the project. The request for final proposals must:

(a) Set forth the factors that the department will use to select a design

-build team to design and construct the project, including the relative

weight to be assigned to each factor; and

(b) Set forth the date by which final proposals must be submitted to

the department.

2. A final proposal submitted by a design-build team pursuant to this

section must be prepared thoroughly, be responsive to the criteria that the

department will use to select a design-build team to design and construct

the project described in subsection 1 and comply with the provisions of

NRS 338.144. If the cost of construction is a factor in the selection of a

design-build team, a design-build team whose prime contractor has

submitted with its proposal a certificate of eligibility to receive a

preference in bidding on public works issued pursuant to NRS 338.147

shall be deemed to have submitted a better proposal than a competing

design-build team whose prime contractor has not submitted such a

certificate of eligibility if the amount proposed by the design-build team

is not more than 5 percent higher than the amount proposed by the

competing design-build team.

3. At least 30 days after receiving the final proposals for the project,

the department shall:

(a) Select the most cost-effective and responsive final proposal, using

the criteria set forth pursuant to subsection 1; or

(b) Reject all the final proposals.

4. If the department selects a final proposal pursuant to paragraph

(a) of subsection 3, the department shall hold a public meeting to:

(a) Review and ratify the selection

. (b) Award the design-build contract to the design-build team whose

proposal is selected.

(c) Partially reimburse the unsuccessful finalists if partial

reimbursement was provided for in the request for preliminary proposals

pursuant to paragraph (i) of subsection 2 of section 24 of this act. The

amount of reimbursement must not exceed, for each unsuccessful

finalist, three percent of the total amount to be paid to the design-build

team as set forth in the design-build contract.

(d) Make available to the public a summary setting forth the factors

used by the department to select the successful design-build team and the

ranking of the design-build teams who submitted final proposals. The

department shall not release to a third party, or otherwise make public,

financial or proprietary information submitted by a design-build team.

5. A contract awarded pursuant to this section must specify:

(a) An amount that is the maximum amount that the department will

pay for the performance of all the work required by the contract,

excluding any amount related to costs that may be incurred as a result of

unexpected conditions or occurrences as authorized by the contract;

(b) An amount that is the maximum amount that the department will

pay for the performance of the professional services required by the

contract; and

(c) A date by which performance of the work required by the contract

must be completed.

6. A design-build team to whom a contract is awarded pursuant to

this section shall:

(a) Assume overall responsibility for ensuring that the design and

construction of the project is completed in a satisfactory manner; and

(b) Use the work force of the prime contractor on the design-build

team to construct at least 15 percent of the project.

Sec. 28. The department may employ a registered architect or

licensed professional engineer as a consultant to assist the department in

overseeing the construction of a project. An architect or engineer so

employed shall not:

1. Construct, reconstruct or improve the highway; or

2. Assume overall responsibility for ensuring that the construction of

the project is completed in a satisfactory manner.

Sec. 29. NRS 408.215 is hereby amended to read as follows:

408.215 1. The director has charge of all the records of the

department, keeping records of all proceedings pertaining to the department

and keeping on file information, plans, specifications, estimates, statistics

and records prepared by the department, except those financial statements

described in NRS 408.333 [,] and the financial or proprietary information

described in paragraph (d) of subsection 4 of section 27 of this act, which

must not become matters of public record. 2. The director may photograph, microphotograph or film or dispose of

the records of the department referred to in subsection 1 as provided in

NRS 239.051, 239.080 and 239.085.

3. The director shall maintain an index or record of deeds or other

references of title or interests in and to all lands or interests in land owned

or acquired by the department.

4. The director shall adopt such regulations as may be necessary to

carry out and enforce the provisions of this chapter.

Sec. 30. NRS 408.317 is hereby amended to read as follows:

408.317 1. [All] Except as otherwise provided in sections 16 to 28,

inclusive, of this act, all work of construction, reconstruction,

improvement and maintenance of highways as provided under the

provisions of this chapter is under the supervision and direction of the

director and must be performed in accordance with the plans, specifications

and contracts prepared by him.

2. All maintenance and repair of highways when performed by the

department must be paid out of the state highway fund.

Sec. 31. NRS 408.327 is hereby amended to read as follows:

408.327 Except as otherwise provided in sections 16 to 28, inclusive,

of this act:

1. Whenever the provisions of NRS 408.323 do not apply, the director

shall advertise for bids for such work according to the plans and

specifications prepared by him.

2. The advertisement must state the place where the bidders may obtain

or inspect the plans and specifications and the time and place for opening

the plans and specifications.

3. Publication of the advertisement must be made at least once a week

for 2 consecutive weeks for a total of at least two publications in a

newspaper of general circulation in the county in which the major portion

of the proposed improvement or construction is to be made, and the

advertisement must also be published at least once a week for 2 consecutive

weeks for a total of at least two publications in one or more daily papers of

general circulation throughout the state. The first publication of the

advertisement in the daily newspapers having general circulation

throughout the state must be made not less than 15 days before the time set

for opening bids.

Sec. 32. NRS 408.333 is hereby amended to read as follows:

408.333 Except as otherwise provided in sections 16 to 28, inclusive,

of this act:

1. Before furnishing any person proposing to bid on any advertised

work with the plans and specifications for such work, the director shall

require from the person a statement, verified under oath, in the form of

answers to questions contained in a standard form of questionnaire and

financial statement, which must include a complete statement of the

person's financial ability and experience in performing public work of a

similar nature. 2. Such statements must be filed with the director in ample time to

permit the department to verify the information contained therein in

advance of furnishing proposal forms, plans and specifications to any

person proposing to bid on the advertised public work, in accordance with

the regulations of the department.

3. Whenever the director is not satisfied with the sufficiency of the

answers contained in the questionnaire and financial statement, he may

refuse to furnish the person with plans and specifications and the official

proposal forms on the advertised project. Any bid of any person to whom

plans and specifications and the official proposal forms have not been

issued in accordance with this section must be disregarded, and the certified

check, cash or undertaking of such a bidder returned forthwith.

4. Any person who is disqualified by the director, in accordance with

the provisions of this section, may request, in writing, a hearing before the

director and present again his check, cash or undertaking and such further

evidence with respect to his financial responsibility, organization, plant and

equipment, or experience, as might tend to justify, in his opinion, issuance

to him of the plans and specifications for the work.

5. Such a person may appeal the decision of the director to the board

no later than 5 days before the opening of the bids on the project. If the

appeal is sustained by the board, the person must be granted the rights and

privileges of all other bidders.

Sec. 33. NRS 408.337 is hereby amended to read as follows:

408.337 Except as otherwise provided in sections 16 to 28, inclusive,

of this act:

1. All bids must be accompanied by an undertaking executed by a

corporate surety authorized to do business in the state, or by cash or a

certified check in an amount equal to at least 5 percent of the amount bid.

2. If the successful bidder fails to execute the contract in accordance

with his bid and give any bond required by law and the contract and bond

are not postmarked or delivered to the department within 20 days after

award of the contract, the undertaking, cash or certified check is forfeited

and the proceeds must be paid into the state highway fund.

3. The failure of the successful bidder to furnish any bond required of

him by law within the time fixed for his execution of the contract

constitutes a failure to execute the contract.

4. If the director deems it is for the best interests of the state, he may,

on refusal or failure of the successful bidder to execute the contract, award

it to the second lowest responsible bidder. If the second lowest responsible

bidder fails or refuses to execute the contract, the director may likewise

award it to the third lowest responsible bidder. On the failure or refusal to

execute the contract of the second or third lowest bidder to whom a

contract is so awarded, their bidder's security is likewise forfeited to the

state.

5. The bidder's security of the second and third lowest responsible

bidders may be withheld by the department until the contract has beenfinally executed and the bond given as required under the provisions of the

contract, at which time the security must be returned. The bidder's security

submitted by all other unsuccessful bidders must be returned to them within

10 days after the contract is awarded.

Sec. 34. NRS 408.343 is hereby amended to read as follows:

408.343 Except as otherwise provided in sections 16 to 28, inclusive,

of this act:

1. All bids must be submitted under sealed cover and received at the

address in Nevada stated in the advertisement for bids and must be opened

publicly and read at the time stated in the advertisement.

2. No bids may be received after the time stated in the advertisement

even though bids are not opened exactly at the time stated in the

advertisement. No bid may be opened before that time.

3. Any bid may be withdrawn at any time before the time stated in the

advertisement only by written request or telegram filed with the director

and executed by the bidder or his duly authorized representative. The

withdrawal of a bid does not prejudice the right of the bidder to file a new

bid before the time stated in the advertisement.

4. The department may reject any bid or all bids if, in the opinion of

the department, the bids are unbalanced, incomplete, contain irregularities

of any kind or for any good cause.

5. Until the final award of the contract, the department may reject or

accept any bids and may waive technical errors contained in the bids, as

may be deemed best for the interests of the state.

6. In awarding a contract, the department shall make the award to the

lowest responsible bidder who has qualified and submitted his bid in

accordance with the provisions of this chapter.

Sec. 35. NRS 625.530 is hereby amended to read as follows:

625.530 Except as otherwise provided in sections 2 to 9, inclusive,

and 16 to 28, inclusive, of this act:

1. The State of Nevada or any of its political subdivisions, including a

county, city or town, shall not engage in any public work requiring the

practice of professional engineering or land surveying, unless the maps,

plans, specifications, reports and estimates have been prepared by, and the

work executed under the supervision of, a professional engineer,

professional land surveyor or registered architect.

2. The provisions of this section do not:

(a) Apply to any public work wherein the expenditure for the complete

project of which the work is a part does not exceed $35,000.

(b) Include any maintenance work undertaken by the State of Nevada or

its political subdivisions.

(c) Authorize a professional engineer, registered architect or

professional land surveyor to practice in violation of any of the provisions

of chapter 623 of NRS or this chapter.

(d) Require the services of an architect registered pursuant to the

provisions of chapter 623 of NRS for the erection of buildings or structuresmanufactured in an industrial plant, if those buildings or structures meet the

requirements of local building codes of the jurisdiction in which they are

being erected.

3. The selection of a professional engineer, professional land surveyor

or registered architect to perform services pursuant to subsection 1 must be

made on the basis of the competence and qualifications of the engineer,

land surveyor or architect for the type of services to be performed and not

on the basis of competitive fees. If, after selection of the engineer, land

surveyor or architect, an agreement upon a fair and reasonable fee cannot

be reached with him, the public agency may terminate negotiations and

select another engineer, land surveyor or architect.

Sec. 35.2. Section 11 of this act is hereby amended to read as follows:

Sec. 11. NRS 338.143 is hereby amended to read as follows:

338.143 1. Except as otherwise provided in subsection 6 and

NRS 338.1907, a local government that awards a contract for the

construction, alteration or repair of a public work in accordance

with paragraph (b) of subsection 1 of section 2 of this act, or a

public officer, public employee or other person responsible for

awarding a contract for the construction, alteration or repair of a

public work who represents that local government, shall not:

(a) Commence such a project for which the estimated cost

exceeds $100,000 unless it advertises in a newspaper of general

circulation in this state for bids for the project; or

(b) Divide such a project into separate portions to avoid the

requirements of paragraph (a).

2. Except as otherwise provided in subsection 6, a local

government that maintains a list of properly licensed contractors

who are interested in receiving offers to bid on public works

projects for which the estimated cost is more than $25,000 but less

than $100,000 shall solicit bids from not more than three of the

contractors on the list for a contract of that value for the

construction, alteration or repair of a public work. The local

government shall select contractors from the list in such a manner as

to afford each contractor an equal opportunity to bid on a public

works project. A properly licensed contractor must submit a written

request annually to the local government to remain on the list.

Offers for bids which are made pursuant to this subsection must be

sent by certified mail.

3. Approved plans and specifications for the bids must be on

file at a place and time stated in the advertisement for the inspection

of all persons desiring to bid thereon and for other interested

persons. Contracts for the project must be awarded on the basis of

bids received.

4. Any bids received in response to an advertisement for bids

may be rejected if the person responsible for awarding the contract

determines that: (a) The bidder is not responsive or responsible;

(b) The quality of the services, materials, equipment or labor

offered does not conform to the approved plan or specifications; or

(c) The public interest would be served by such a rejection.

5. Before a local government may commence a project subject

to the provisions of this section, based upon a determination that the

public interest would be served by rejecting any bids received in

response to an advertisement for bids, it shall prepare and make

available for public inspection a written statement containing:

(a) A list of all persons, including supervisors, whom the local

government intends to assign to the project, together with their

classifications and an estimate of the direct and indirect costs of

their labor;

(b) A list of all equipment that the local government intends to

use on the project, together with an estimate of the number of hours

each item of equipment will be used and the hourly cost to use each

item of equipment;

(c) An estimate of the cost of administrative support for the

persons assigned to the project;

(d) An estimate of the total cost of the project; and

(e) An estimate of the amount of money the local government

expects to save by rejecting the bids and performing the project

itself.

6. This section does not apply to:

(a) Any utility subject to the provisions of chapter 318 or 710 of

NRS;

(b) Any work of construction, reconstruction, improvement and

maintenance of highways subject to NRS 408.323 or 408.327;

(c) Normal maintenance of the property of a school district; or

(d) The Las Vegas Valley water district created pursuant to

chapter 167, Statutes of Nevada 1947, the Moapa Valley water

district created pursuant to chapter 477, Statutes of Nevada 1983 or

the Virgin Valley water district created pursuant to chapter 100,

Statutes of Nevada 1993 . [; or

(e) The design and construction of a public work for which a

public body contracts with a design-build team pursuant to sections

2 to 9, inclusive, of this act.]

Sec. 35.4. Assembly Bill No. 298 of this session is hereby amended by

adding thereto new sections designated sections 19.2 through 19.6,

following sec. 19, to read as follows:

Sec. 19.2. Section 8 of this act is hereby amended to read as

follows:

Sec. 8. 1. Except as otherwise provided in subsection 7

and NRS 338.1906 and 338.1907, this state, or a local

government that awards a contract for the construction, alteration

or repair of a public work in accordance with paragraph (a) ofsubsection 1 of section 2 of this act, or a public officer, public

employee or other person responsible for awarding a contract for

the construction, alteration or repair of a public work who

represents the state or the local government, shall not:

(a) Commence such a project for which the estimated cost

exceeds $100,000 unless it advertises in a newspaper of general

circulation in this state for bids for the project; or

(b) Divide such a project into separate portions to avoid the

requirements of paragraph (a).

2. Except as otherwise provided in subsection 7, a public

body that maintains a list of properly licensed contractors who

are interested in receiving offers to bid on public works projects

for which the estimated cost is more than $25,000 but less than

$100,000 shall solicit bids from not more than three of the

contractors on the list for a contract of that value for the

construction, alteration or repair of a public work. The public

body shall select contractors from the list in such a manner as to

afford each contractor an equal opportunity to bid on a public

works project. A properly licensed contractor must submit a

written request annually to the public body to remain on the list.

Offers for bids which are made pursuant to this subsection must

be sent by certified mail.

3. Each advertisement for bids must include a provision that

sets forth:

(a) The requirement that a contractor must be qualified

pursuant to section 5 of this act to bid on the contract or must be

exempt from meeting such qualifications pursuant to section 6 of

this act; and

(b) The period during which an application to qualify as a

bidder on the contract must be submitted.

4. Approved plans and specifications for the bids must be on

file at a place and time stated in the advertisement for the

inspection of all persons desiring to bid thereon and for other

interested persons. Contracts for the project must be awarded on

the basis of bids received.

5. Any bids received in response to an advertisement for bids

may be rejected if the person responsible for awarding the

contract determines that:

(a) The bidder is not a qualified bidder pursuant to section 5

of this act, unless the bidder is exempt from meeting such

qualifications pursuant to section 6 of this act;

(b) The bidder is not responsive;

(c) The quality of the services, materials, equipment or labor

offered does not conform to the approved plan or specifications;

or

(d) The public interest would be served by such a rejection

. 6. Before the state or a local government may commence a

project subject to the provisions of this section, based upon a

determination that the public interest would be served by

rejecting any bids received in response to an advertisement for

bids, it shall prepare and make available for public inspection a

written statement containing:

(a) A list of all persons, including supervisors, whom the state

or the local government intends to assign to the project, together

with their classifications and an estimate of the direct and indirect

costs of their labor;

(b) A list of all equipment that the state or the local

government intends to use on the project, together with an

estimate of the number of hours each item of equipment will be

used and the hourly cost to use each item of equipment;

(c) An estimate of the cost of administrative support for the

persons assigned to the project;

(d) An estimate of the total cost of the project; and

(e) An estimate of the amount of money the state or the local

government expects to save by rejecting the bids and performing

the project itself.

7. This section does not apply to:

(a) Any utility subject to the provisions of chapter 318 or 710

of NRS;

(b) Any work of construction, reconstruction, improvement

and maintenance of highways subject to NRS 408.323 or

408.327;

(c) Normal maintenance of the property of a school district; or

(d) The Las Vegas Valley water district created pursuant to

chapter 167, Statutes of Nevada 1947, the Moapa Valley water

district created pursuant to chapter 477, Statutes of Nevada 1983

or the Virgin Valley water district created pursuant to chapter

100, Statutes of Nevada 1993 . [; or

(e) The design and construction of a public work for which a

public body contracts with a design-build team pursuant to

sections 2 to 9, inclusive, of Senate Bill No. 475 of this session.]

Sec. 19.4. Section 8 of this act is hereby amended to read as

follows:

Sec. 8. 1. Except as otherwise provided in subsection 7 ,

[and NRS 338.1906 and 338.1907,] this state, or a local

government that awards a contract for the construction, alteration

or repair of a public work in accordance with paragraph (a) of

subsection 1 of section 2 of this act, or a public officer, public

employee or other person responsible for awarding a contract for

the construction, alteration or repair of a public work who

represents the state or the local government, shall not: (a) Commence such a project for which the estimated cost

exceeds $100,000 unless it advertises in a newspaper of general

circulation in this state for bids for the project; or

(b) Divide such a project into separate portions to avoid the

requirements of paragraph (a).

2. Except as otherwise provided in subsection 7, a public

body that maintains a list of properly licensed contractors who

are interested in receiving offers to bid on public works projects

for which the estimated cost is more than $25,000 but less than

$100,000 shall solicit bids from not more than three of the

contractors on the list for a contract of that value for the

construction, alteration or repair of a public work. The public

body shall select contractors from the list in such a manner as to

afford each contractor an equal opportunity to bid on a public

works project. A properly licensed contractor must submit a

written request annually to the public body to remain on the list.

Offers for bids which are made pursuant to this subsection must

be sent by certified mail.

3. Each advertisement for bids must include a provision that

sets forth:

(a) The requirement that a contractor must be qualified

pursuant to section 5 of this act to bid on the contract or must be

exempt from meeting such qualifications pursuant to section 6 of

this act; and

(b) The period during which an application to qualify as a

bidder on the contract must be submitted.

4. Approved plans and specifications for the bids must be on

file at a place and time stated in the advertisement for the

inspection of all persons desiring to bid thereon and for other

interested persons. Contracts for the project must be awarded on

the basis of bids received.

5. Any bids received in response to an advertisement for bids

may be rejected if the person responsible for awarding the

contract determines that:

(a) The bidder is not a qualified bidder pursuant to section 5

of this act, unless the bidder is exempt from meeting such

qualifications pursuant to section 6 of this act;

(b) The bidder is not responsive;

(c) The quality of the services, materials, equipment or labor

offered does not conform to the approved plan or specifications;

or

(d) The public interest would be served by such a rejection.

6. Before the state or a local government may commence a

project subject to the provisions of this section, based upon a

determination that the public interest would be served by

rejecting any bids received in response to an advertisement forbids, it shall prepare and make available for public inspection a

written statement containing:

(a) A list of all persons, including supervisors, whom the state

or the local government intends to assign to the project, together

with their classifications and an estimate of the direct and indirect

costs of their labor;

(b) A list of all equipment that the state or the local

government intends to use on the project, together with an

estimate of the number of hours each item of equipment will be

used and the hourly cost to use each item of equipment;

(c) An estimate of the cost of administrative support for the

persons assigned to the project;

(d) An estimate of the total cost of the project; and

(e) An estimate of the amount of money the state or the local

government expects to save by rejecting the bids and performing

the project itself.

7. This section does not apply to:

(a) Any utility subject to the provisions of chapter 318 or 710

of NRS;

(b) Any work of construction, reconstruction, improvement

and maintenance of highways subject to NRS 408.323 or

408.327;

(c) Normal maintenance of the property of a school district; or

(d) The Las Vegas Valley water district created pursuant to

chapter 167, Statutes of Nevada 1947, the Moapa Valley water

district created pursuant to chapter 477, Statutes of Nevada 1983

or the Virgin Valley water district created pursuant to chapter

100, Statutes of Nevada 1993.

Sec. 19.6. Section 11 of this act is hereby amended to read as

follows:

Sec. 11. 1. Except as otherwise provided in section 8 of

this act , [and sections 2 to 9, inclusive, of Senate Bill No. 475 of

this session,] a public body shall award a contract for a public

work to the contractor who submits the best bid.

2. Except as otherwise provided in subsection 8 or limited by

subsection 9, for the purposes of this section, a contractor who:

(a) Has been determined by the public body to be a qualified

bidder pursuant to section 5 of this act or is exempt from meeting

such requirements pursuant to section 6 of this act; and

(b) At the time he submits his bid, provides to the public body

a copy of a certificate of eligibility to receive a preference in

bidding on public works issued to him by the state contractors'

board pursuant to subsection 3,

shall be deemed to have submitted a better bid than a competing

contractor who has not provided a copy of such a valid certificateof eligibility if the amount of his bid is not more than 5 percent

higher than the amount bid by the competing contractor.

3. The state contractors' board shall issue a certificate of

eligibility to receive a preference in bidding on public works to a

general contractor who is licensed pursuant to the provisions of

chapter 624 of NRS and submits to the board an affidavit from a

certified public accountant setting forth that the general

contractor has:

(a) Paid:

(1) The sales and use taxes imposed pursuant to chapters

372, 374 and 377 of NRS on materials used for construction in

this state, including, without limitation, construction that is

undertaken or carried out on land within the boundaries of this

state that is managed by the Federal Government or is on an

Indian reservation or Indian colony, of not less than $5,000 for

each consecutive 12-month period for 60 months immediately

preceding the submission of the affidavit from the certified public

accountant;

(2) The motor vehicle privilege tax imposed pursuant to

chapter 371 of NRS on the vehicles used in the operation of his

business in this state of not less than $5,000 for each consecutive

12-month period for 60 months immediately preceding the

submission of the affidavit from the certified public accountant;

or

(3) Any combination of such sales and use taxes and motor

vehicle privilege tax; or

(b) Acquired, by inheritance, gift or transfer through a stock

option plan for employees, all the assets and liabilities of a

viable, operating construction firm that possesses a:

(1) License as a general contractor pursuant to the

provisions of chapter 624 of NRS; and

(2) Certificate of eligibility to receive a preference in

bidding on public works.

4. For the purposes of complying with the requirements set

forth in paragraph (a) of subsection 3, a general contractor shall

be deemed to have paid:

(a) Sales and use taxes and motor vehicle privilege taxes paid

in this state by an affiliate or parent company of the contractor, if

the affiliate or parent company is also a general contractor; and

(b) Sales and use taxes paid in this state by a joint venture in

which the contractor is a participant, in proportion to the amount

of interest the contractor has in the joint venture.

5. A contractor who has received a certificate of eligibility to

receive a preference in bidding on public works from the state

contractors' board pursuant to subsection 3 shall, at the time

for the annual renewal of his contractors' license pursuant toNRS 624.283, submit to the board an affidavit from a certified

public accountant setting forth that the contractor has, during the

immediately preceding 12 months, paid the taxes required

pursuant to paragraph (a) of subsection 3 to maintain his

eligibility to hold such a certificate.

6. A contractor who fails to submit an affidavit to the board

pursuant to subsection 5 ceases to be eligible to receive a

preference in bidding on public works unless he reapplies for and

receives a certificate of eligibility pursuant to subsection 3.

7. If a contractor who applies to the state contractors' board

for a certificate of eligibility to receive a preference in bidding on

public works submits false information to the board regarding the

required payment of taxes, the contractor is not eligible to receive

a preference in bidding on public works for a period of 5 years

after the date on which the board becomes aware of the

submission of the false information.

8. If any federal statute or regulation precludes the granting

of federal assistance or reduces the amount of that assistance for

a particular public work because of the provisions of subsection

2, those provisions do not apply insofar as their application

would preclude or reduce federal assistance for that work. The

provisions of subsection 2 do not apply to any contract for a

public work which is expected to cost less than $250,000.

9. [Except as otherwise provided in subsection 2 of section 8

of Senate Bill No. 475 of this session, if] If a bid is submitted by

two or more contractors as a joint venture or by one of them as a

joint venturer, the provisions of subsection 2 apply only if both or

all of the joint venturers separately meet the requirements of that

subsection.

10. The state contractors' board shall adopt regulations and

may assess reasonable fees relating to the certification of

contractors for a preference in bidding on public works.

11. A person or entity who believes that a contractor

wrongfully holds a certificate of eligibility to receive a preference

in bidding on public works may challenge the validity of the

certificate by filing a written objection with the public body to

which the contractor has submitted a bid or proposal on a

contract for the construction of a public work. A written

objection authorized pursuant to this subsection must:

(a) Set forth proof or substantiating evidence to support the

belief of the person or entity that the contractor wrongfully holds

a certificate of eligibility to receive a preference in bidding on

public works; and

(b) Be filed with the public body at or after the time at which

the contractor submitted the bid or proposal to the public bodyand before the time at which the public body awards the contract

for which the bid or proposal was submitted.

12. If a public body receives a written objection pursuant to

subsection 11, the public body shall determine whether the

objection is accompanied by the proof or substantiating evidence

required pursuant to paragraph (a) of that subsection. If the

public body determines that the objection is not accompanied by

the required proof or substantiating evidence, the public body

shall dismiss the objection and may proceed immediately to

award the contract. If the public body determines that the

objection is accompanied by the required proof or substantiating

evidence, the public body shall determine whether the contractor

qualifies for the certificate pursuant to the provisions of this

section and may proceed to award the contract accordingly.

Sec. 35.6. Sections 8, 11, 12 and 21 of Assembly Bill No. 298 of this

session are hereby amended to read as follows:

Sec. 8. 1. Except as otherwise provided in subsection 7 and

NRS 338.1906 and 338.1907, this state, or a local government

that awards a contract for the construction, alteration or repair of

a public work in accordance with paragraph (a) of subsection 1 of

section 2 of this act, or a public officer, public employee or other

person responsible for awarding a contract for the construction,

alteration or repair of a public work who represents the state or

the local government, shall not:

(a) Commence such a project for which the estimated cost

exceeds $100,000 unless it advertises in a newspaper of general

circulation in this state for bids for the project; or

(b) Divide such a project into separate portions to avoid the

requirements of paragraph (a).

2. Except as otherwise provided in subsection 7, a public body

that maintains a list of properly licensed contractors who are

interested in receiving offers to bid on public works projects for

which the estimated cost is more than $25,000 but less than

$100,000 shall solicit bids from not more than three of the

contractors on the list for a contract of that value for the

construction, alteration or repair of a public work. The public

body shall select contractors from the list in such a manner as to

afford each contractor an equal opportunity to bid on a public

works project. A properly licensed contractor must submit a

written request annually to the public body to remain on the list.

Offers for bids which are made pursuant to this subsection must

be sent by certified mail.

3. Each advertisement for bids must include a provision that

sets forth:

(a) The requirement that a contractor must be qualified

pursuant to section 5 of this act to bid on the contract or must beexempt from meeting such qualifications pursuant to section 6 of

this act; and

(b) The period during which an application to qualify as a

bidder on the contract must be submitted.

4. Approved plans and specifications for the bids must be on

file at a place and time stated in the advertisement for the

inspection of all persons desiring to bid thereon and for other

interested persons. Contracts for the project must be awarded on

the basis of bids received.

5. Any bids received in response to an advertisement for bids

may be rejected if the person responsible for awarding the

contract determines that:

(a) The bidder is not a qualified bidder pursuant to section 5 of

this act, unless the bidder is exempt from meeting such

qualifications pursuant to section 6 of this act;

(b) The bidder is not responsive;

(c) The quality of the services, materials, equipment or labor

offered does not conform to the approved plan or specifications;

or

(d) The public interest would be served by such a rejection.

6. Before the state or a local government may commence a

project subject to the provisions of this section, based upon a

determination that the public interest would be served by rejecting

any bids received in response to an advertisement for bids, it shall

prepare and make available for public inspection a written

statement containing:

(a) A list of all persons, including supervisors, whom the state

or the local government intends to assign to the project, together

with their classifications and an estimate of the direct and indirect

costs of their labor;

(b) A list of all equipment that the state or the local

government intends to use on the project, together with an

estimate of the number of hours each item of equipment will be

used and the hourly cost to use each item of equipment;

(c) An estimate of the cost of administrative support for the

persons assigned to the project;

(d) An estimate of the total cost of the project; and

(e) An estimate of the amount of money the state or the local

government expects to save by rejecting the bids and performing

the project itself.

7. This section does not apply to:

(a) Any utility subject to the provisions of chapter 318 or 710

of NRS;

(b) Any work of construction, reconstruction, improvement

and maintenance of highways subject to NRS 408.323 or 408.327;

(c) Normal maintenance of the property of a school district;

(d) The Las Vegas Valley water district created pursuant to

chapter 167, Statutes of Nevada 1947, the Moapa Valley water

district created pursuant to chapter 477, Statutes of Nevada 1983

or the Virgin Valley water district created pursuant to chapter

100, Statutes of Nevada 1993; or

(e) The design and construction of a public work for which a

public body contracts with a design-build team pursuant to

sections 2 to 9, inclusive, of Senate Bill No. 475 of this session.

Sec. 11. 1. Except as otherwise provided in section 8 of this

act and sections 2 to 9, inclusive, of Senate Bill No. 475 of this

session, a public body shall award a contract for a public work to

the contractor who submits the best bid.

2. Except as otherwise provided in subsection 8 or limited by

subsection 9, for the purposes of this section, a contractor who:

(a) Has been determined by the public body to be a qualified

bidder pursuant to section 5 of this act or is exempt from meeting

such requirements pursuant to section 6 of this act; and

(b) At the time he submits his bid, provides to the public body a

copy of a certificate of eligibility to receive a preference in

bidding on public works issued to him by the state contractors'

board pursuant to subsection 3,

shall be deemed to have submitted a better bid than a competing

contractor who has not provided a copy of such a valid certificate

of eligibility if the amount of his bid is not more than 5 percent

higher than the amount bid by the competing contractor.

3. The state contractors' board shall issue a certificate of

eligibility to receive a preference in bidding on public works to a

general contractor who is licensed pursuant to the provisions of

chapter 624 of NRS and submits to the board an affidavit from a

certified public accountant setting forth that the general

contractor has:

(a) Paid:

(1) The sales and use taxes imposed pursuant to chapters

372, 374 and 377 of NRS on materials used for construction in

this state, including, without limitation, construction that is

undertaken or carried out on land within the boundaries of this

state that is managed by the Federal Government or is on an

Indian reservation or Indian colony, of not less than $5,000 for

each consecutive 12-month period for 60 months immediately

preceding the submission of the affidavit from the certified public

accountant;

(2) The motor vehicle privilege tax imposed pursuant to

chapter 371 of NRS on the vehicles used in the operation of his

business in this state of not less than $5,000 for each consecutive

12-month period for 60 months immediately preceding thesubmission of the affidavit from the certified public accountant;

or

(3) Any combination of such sales and use taxes and motor

vehicle privilege tax; or

(b) Acquired, by inheritance, gift or transfer through a stock

option plan for employees, all the assets and liabilities of a viable,

operating construction firm that possesses a:

(1) License as a general contractor pursuant to the

provisions of chapter 624 of NRS; and

(2) Certificate of eligibility to receive a preference in bidding

on public works.

4. For the purposes of complying with the requirements set

forth in paragraph (a) of subsection 3, a general contractor shall

be deemed to have paid:

(a) Sales and use taxes and motor vehicle privilege taxes paid

in this state by an affiliate or parent company of the contractor, if

the affiliate or parent company is also a general contractor; and

(b) Sales and use taxes paid in this state by a joint venture in

which the contractor is a participant, in proportion to the amount

of interest the contractor has in the joint venture.

5. A contractor who has received a certificate of eligibility to

receive a preference in bidding on public works from the state

contractors' board pursuant to subsection 3 shall, at the time for

the annual renewal of his contractors' license pursuant to NRS

624.283, submit to the board an affidavit from a certified public

accountant setting forth that the contractor has, during the

immediately preceding 12 months, paid the taxes required

pursuant to paragraph (a) of subsection 3 to maintain his

eligibility to hold such a certificate.

6. A contractor who fails to submit an affidavit to the board

pursuant to subsection 5 ceases to be eligible to receive a

preference in bidding on public works unless he reapplies for and

receives a certificate of eligibility pursuant to subsection 3. 7. If a contractor who applies to the state contractors' board

for a certificate of eligibility to receive a preference in bidding on

public works submits false information to the board regarding the

required payment of taxes, the contractor is not eligible to receive

a preference in bidding on public works for a period of 5 years

after the date on which the board becomes aware of the

submission of the false information.

8. If any federal statute or regulation precludes the granting

of federal assistance or reduces the amount of that assistance for

a particular public work because of the provisions of subsection 2,

those provisions do not apply insofar as their application would

preclude or reduce federal assistance for that work. Theprovisions of subsection 2 do not apply to any contract for a

public work which is expected to cost less than $250,000.

9. Except as otherwise provided in subsection 2 of section 8 of

Senate Bill No. 475 of this session, if a bid is submitted by two or

more contractors as a joint venture or by one of them as a joint

venturer, the provisions of subsection 2 apply only if both or all of

the joint venturers separately meet the requirements of that

subsection.

10. The state contractors' board shall adopt regulations and

may assess reasonable fees relating to the certification of

contractors for a preference in bidding on public works.

11. A person or entity who believes that a contractor

wrongfully holds a certificate of eligibility to receive a preference

in bidding on public works may challenge the validity of the

certificate by filing a written objection with the public body to

which the contractor has submitted a bid or proposal on a

contract for the construction of a public work. A written objection

authorized pursuant to this subsection must:

(a) Set forth proof or substantiating evidence to support the

belief of the person or entity that the contractor wrongfully holds

a certificate of eligibility to receive a preference in bidding on

public works; and

(b) Be filed with the public body at or after the time at which

the contractor submitted the bid or proposal to the public body

and before the time at which the public body awards the contract

for which the bid or proposal was submitted.

12. If a public body receives a written objection pursuant to

subsection 11, the public body shall determine whether the

objection is accompanied by the proof or substantiating evidence

required pursuant to paragraph (a) of that subsection. If the

public body determines that the objection is not accompanied by

the required proof or substantiating evidence, the public body

shall dismiss the objection and may proceed immediately to award

the contract. If the public body determines that the objection is

accompanied by the required proof or substantiating evidence, the

public body shall determine whether the contractor qualifies for

the certificate pursuant to the provisions of this section and may

proceed to award the contract accordingly.

Sec. 12. NRS 338.010 is hereby amended to read as follows:

338.010 As used in this chapter:

1. "Day labor" means all cases where public bodies, their

officers, agents or employees, hire, supervise and pay the wages

thereof directly to a workman or workmen employed by them on

public works by the day and not under a contract in writing.

2. "Eligible bidder" means a person who was [found] :

(a) Found to be a responsible contractor by a [public body]

local government which awarded a contract for a public work [.] in

accordance with paragraph (b) of subsection 1 of section 2 of this

act; or

(b) Determined by a public body which awarded a contract for

a public work pursuant to sections 3 to 11, inclusive, of this act, to

be qualified to bid on that contract pursuant to section 5 of this

act or was exempt from meeting such qualifications pursuant to

section 6 of this act.

3. "Local government" means every political subdivision or

other entity which has the right to levy or receive money from ad

valorem or other taxes or any mandatory assessments, and

includes, without limitation, counties, cities, towns, boards, school

districts and other districts organized pursuant to chapters 244A,

309, 318, 379, 474, 541, 543 and 555 of NRS, NRS 450.550 to

450.750, inclusive, and any agency or department of a county or

city which prepares a budget separate from that of the parent

political subdivision.

4. "Offense" means failing to:

(a) Pay the prevailing wage required pursuant to this chapter;

(b) Pay the contributions for unemployment compensation

required pursuant to chapter 612 of NRS; or

(c) Provide and secure compensation for employees required

pursuant to chapters 616A to 617, inclusive, of NRS.

[4.] 5. "Public body" means the state, county, city, town,

school district or any public agency of this state or its political

subdivisions sponsoring or financing a public work.

[5.] 6. "Public work" means any project for the new

construction, repair or reconstruction of:

(a) A project financed in whole or in part from public money for:

(1) Public buildings;

(2) Jails and prisons;

(3) Public roads;

(4) Public highways;

(5) Public streets and alleys;

(6) Public utilities which are financed in whole or in part by

public money;

(7) Publicly owned water mains and sewers;

(8) Public parks and playgrounds;

(9) Public convention facilities which are financed at least in

part with public funds; and

(10) [All] Any other publicly owned works and property

whose cost as a whole exceeds $20,000. Each separate unit which is

a part of a project is included in the cost of the project for the

purpose of determining whether a project meets this threshold. (b) A building for the University and Community College

System of Nevada of which 25 percent or more of the costs of the

building as a whole are paid from money appropriated by [the] this

state or from federal money.

[6.] 7. "Wages" means:

(a) The basic hourly rate of pay; and

(b) The amount of pension, health and welfare, vacation and

holiday pay, the cost of apprenticeship training or other similar

programs or other bona fide fringe benefits which are a benefit to

the workman.

[7.] 8. "Workman" means a skilled mechanic, skilled

workman, semiskilled mechanic, semiskilled workman or unskilled

workman.

Sec. 21. 1. This section and sections 2 to 7, inclusive, 10 to

14, inclusive, 16 to 19, inclusive, and 20 of this act become

effective on October 1, 1999.

2. Section 8 of this act becomes effective on October 1, 1999,

and expires by limitation on October 1, 2003.

3. Sections 19.2 and 19.6 of this act become effective on

October 1, 2003.

4. Sections 15 and 19.4 of this act become effective at 12:01

a.m. on May 1, 2013.

5. Sections 14, 18, 19 and 19.2 of this act expire by limitation

on May 1, 2013.

Sec. 35.8. Section 4 of Senate Bill No. 144 of this session is hereby

amended to read as follows:

Sec. 4. "Contractor" means : [a]

1. A person who:

[1.] (a) Is licensed pursuant to the provisions of chapter 624 of

NRS or performs such work that he is not required to be licensed

pursuant to chapter 624 of NRS; and

[2.] (b) Contracts with a public body to provide labor, materials

or services for a public work.

2. A design-build team that contracts with a public body to

design and construct a public work pursuant to sections 2 to 9,

inclusive, of Senate Bill No. 475 of this session.

Sec. 36. NRS 341.171 and section 9 of Assembly Bill No. 298 of this

session are hereby repealed.

Sec. 37. 1. The interim advisory committee to study the use of

design-build contracting within this state is hereby created. The interim

advisory committee consists of 16 members who are appointed as follows:

(a) One member appointed by the Northern Nevada Chapter of the

Associated General Contractors.

(b) One member appointed by the Southern Nevada Chapter of the

Associated General Contractors. (c) One member appointed by the Northern Nevada Chapter of the

Associated Builders and Contractors.

(d) One member appointed by the Southern Nevada Chapter of the

Associated Builders and Contractors.

(e) One member appointed by the Nevada chapter of the American

Institute of Architecture.

(f) One member appointed by the American Consulting Engineers

Council of Nevada.

(g) One member appointed by the Department of Transportation of the

State of Nevada.

(h) One member appointed by the Southern Nevada Water Authority.

(i) One member appointed by the Board of County Commissioners of

Clark County.

(j) One member appointed by the governing body of the City of

Las Vegas.

(k) One member appointed by the governing body of the City of

Henderson.

(l) One member appointed by the governing body of the City of North

Las Vegas.

(m) One member appointed by the Nevada Contractors Association.

(n) One member appointed by the Board of County Commissioners of

Washoe County.

(o) One member appointed by the governing body of the City of Reno.

(p) One member appointed by the governing body of the City of Sparks.

2. Members of the interim advisory committee shall serve without

compensation, travel expenses or subsistence allowances, except as they

may be provided by the members' respective agencies and organizations.

3. The interim advisory committee created pursuant to subsection 1

shall:

(a) Examine the methods of design-build contracting that are authorized

to be used pursuant to the provisions of this act; and

(b) Submit a report regarding its findings to the 72nd session of the

Nevada Legislature, accompanied by any suggestions for legislation that

the interim advisory committee determines to be advisable.

Sec. 38. 1. This section and sections 35.4 and 35.6 of this act

become effective on October 1, 1999.

2. Sections 1 to 9, inclusive, 14 to 35, inclusive, 36 and 37 of this

act become effective on October 1, 1999, and expire by limitation on

October 1, 2003.

3. Sections 10, 13 and 35.8 of this act become effective at 12:01 a.m.

on October 1, 1999, and expire by limitation on October 1, 2003.

4. Section 11 of this act becomes effective at 12:01 a.m. on October 1,

1999, and expires by limitation on May 1, 2013.

5. Section 13.5 of this act becomes effective at 12:01 a.m. on

October 1, 2003.

6. Section 35.2 of this act becomes effective at 12:01 a.m. on

October 1, 2003 and expires by limitation on May 1, 2013.

7. Section 12 of this act becomes effective at 12:02 a.m. on May 1,

2013.

~