Senate Bill No. 475–Committee on Government Affairs

March 18, 1999

____________

Referred to Committee on Government Affairs

 

SUMMARY—Authorizes public body and department of transportation to use design-build method of contracting in certain circumstances. (BDR 28-517)

FISCAL NOTE: Effect on Local Government: No.

Effect on the State or on Industrial Insurance: No.

~

EXPLANATION – Matter in bolded italics is new; matter between brackets [omitted material] is material to be omitted. Green numbers along left margin indicate location on the printed bill (e.g., 5-15 indicates page 5, line 15).

 

AN ACT relating to public works; authorizing a public body to contract with a design-build team or specialty contractor for the design and construction of a public work in certain circumstances; authorizing a public body to contract with a nonprofit organization for the design and construction of a project to restore, enhance or develop wetlands; authorizing the department of transportation to contract with a design-build team with respect to a project for the design and construction, reconstruction or improvement of highways in certain circumstances; setting forth the method in which proposals for a design-build contract must be solicited; setting forth the method in which a design-build team must be selected; authorizing a public body or the department of transportation to employ an architect or engineer to oversee the construction of a public work or project; creating an interim advisory committee to study the use of design-build contracting; and providing other matters properly relating thereto.

 

THE PEOPLE OF THE STATE OF NEVADA, REPRESENTED IN SENATE AND ASSEMBLY, DO ENACT AS FOLLOWS:

1-1 Section 1. Chapter 338 of NRS is hereby amended by adding thereto

1-2 the provisions set forth as sections 2 to 9, inclusive, of this act.

1-3 Sec. 2. 1. Except as otherwise provided in this section, a public

1-4 body shall contract with a prime contractor for the construction of a

1-5 public work for which the estimated cost exceeds $100,000.

1-6 2. A public body may contract with a design-build team for the

1-7 design and construction of a public work that is a discrete project if the

1-8 public body determines that:

1-9 (a) The public work is:

2-1 (1) A plant or facility for the treatment and pumping of water or the

2-2 treatment and disposal of wastewater or sewage, the estimated cost of

2-3 which exceeds $100,000,000; or

2-4 (2) Any other type of public work, except a stand-alone

2-5 underground utility project, the estimated cost of which exceeds

2-6 $30,000,000; and

2-7 (b) Contracting with a design-build team will enable the public body

2-8 to:

2-9 (1) Design and construct the public work at a cost that is

2-10 significantly lower than the cost that the public body would incur to

2-11 design and construct the public work using a different method;

2-12 (2) Design and construct the public work in a shorter time than

2-13 would be required to design and construct the public work using a

2-14 different method, if exigent circumstances require that the public work

2-15 be designed and constructed within a short time; or

2-16 (3) Ensure that the design and construction of the public work is

2-17 properly coordinated, if the public work is unique, highly technical and

2-18 complex in nature.

2-19 3. In a county whose population is 400,000 or more, a public body

2-20 that is responsible for financing public works may, for its own public

2-21 works and those financed by a different public body, including, without

2-22 limitation, an airport if the airport is owned and operated as a

2-23 department of the public body, contract with a design-build team once in

2-24 each fiscal year for the design and construction of a public work if the

2-25 public body determines that:

2-26 (a) The estimated cost of the public work is at least $5,000,000 but less

2-27 than $30,000,000; and

2-28 (b) Contracting with a design-build team will enable the public body

2-29 to:

2-30 (1) Design and construct the public work at a cost that is

2-31 significantly lower than the cost that the public body would incur to

2-32 design and construct the public work using a different method;

2-33 (2) Design and construct the public work in a shorter time than

2-34 would be required to design and construct the public work using a

2-35 different method, if exigent circumstances require that the public work

2-36 be designed and constructed within a short time; or

2-37 (3) Ensure that the design and construction of the public work is

2-38 properly coordinated, if the public work is unique, highly technical and

2-39 complex in nature.

2-40 4. Notwithstanding the provisions of subsections 1, 2 and 3, a public

2-41 body may contract with:

2-42 (a) A nonprofit organization for the design and construction of a

2-43 project to restore, enhance or develop wetlands.

3-1 (b) A prime contractor, specialty contractor or design-build team with

3-2 respect to a public work if the public body determines that the public

3-3 work is:

3-4 (1) Not part of a larger public work; and

3-5 (2) Limited in scope to:

3-6 (I) Removal of asbestos;

3-7 (II) Replacement of equipment or systems for heating, ventilation

3-8 and air-conditioning;

3-9 (III) Replacement of a roof;

3-10 (IV) Landscaping; or

3-11 (V) Restoration, enhancement or development of wetlands.

3-12 Sec. 3. 1. A public body shall not contract with a design-build team

3-13 with respect to a public work unless the governing body of the public

3-14 body makes the determinations, at a public hearing, that are required

3-15 pursuant to subsection 2, 3 or 4 of section 2 of this act, as applicable.

3-16 2. A public body that is required to hold a public hearing pursuant to

3-17 this section shall publish notice of the hearing at least once each week

3-18 for 3 consecutive weeks in:

3-19 (a) A newspaper of general circulation published in the county in

3-20 which the public work is proposed to be constructed or, if there is no such

3-21 newspaper, in a newspaper of general circulation in the county published

3-22 in this state; and

3-23 (b) A newspaper of general circulation in this state.

3-24 Sec. 4. 1. A public body that is required to contract with a prime

3-25 contractor pursuant to subsection 1 of section 2 of this act or elects to

3-26 contract with a specialty contractor pursuant to subsection 4 of section 2

3-27 of this act shall select the prime contractor or specialty contractor, as

3-28 appropriate, in accordance with the procedures for bidding that are set

3-29 forth in NRS 338.140 to 338.147, inclusive.

3-30 2. A public body that contracts with a design-build team pursuant to

3-31 sections 2 and 3 of this act shall select the design-build team in

3-32 accordance with sections 5 to 8, inclusive, of this act.

3-33 Sec. 5. 1. A public body shall advertise for preliminary proposals

3-34 for the design and construction of a public work by a design-build team

3-35 at least twice each week for 3 consecutive weeks in:

3-36 (a) A newspaper of general circulation published in the county in

3-37 which the public work is proposed to be constructed or, if there is no such

3-38 newspaper, in a newspaper of general circulation in the county published

3-39 in this state; and

3-40 (b) A newspaper of general circulation in this state.

3-41 2. A request for preliminary proposals published pursuant to

3-42 subsection 1 must include, without limitation:

3-43 (a) A description of the public work to be designed and constructed;

4-1 (b) Separate estimates of the costs of designing and constructing the

4-2 public work;

4-3 (c) The dates on which it is anticipated that the separate phases of the

4-4 design and construction of the public work will begin and end;

4-5 (d) A statement setting forth the place and time in which a design-

4-6 build team desiring to submit a proposal for the public work may obtain

4-7 the information necessary to submit a proposal, including, without

4-8 limitation, the extent to which designs must be completed for both

4-9 preliminary and final proposals and any other requirements for the

4-10 design and construction of the public work that the public body

4-11 determines to be necessary;

4-12 (e) A list of the requirements set forth in section 6 of this act;

4-13 (f) A list of the factors that the public body will use to evaluate design-

4-14 build teams who submit a proposal for the public work, including,

4-15 without limitation:

4-16 (1) The relative weight to be assigned to each factor; and

4-17 (2) A disclosure of whether the factors that are not related to cost

4-18 are, when considered as a group, more or less important in the process of

4-19 evaluation than the factor of cost;

4-20 (g) Notice that a design-build team desiring to submit a proposal for

4-21 the public work must include with its proposal the information used by

4-22 the public body to determine finalists among the design-build teams

4-23 submitting proposals pursuant to subsection 2 of section 7 of this act and

4-24 a description of that information;

4-25 (h) A statement that a design-build team whose prime contractor

4-26 holds a certificate of eligibility to receive a preference in bidding on

4-27 public works issued pursuant to NRS 338.147 should submit a copy of

4-28 the certificate of eligibility with its proposal;

4-29 (i) A statement as to whether a design-build team that is selected as a

4-30 finalist pursuant to section 7 of this act but is not awarded the design-

4-31 build contract pursuant to section 8 of this act will be partially

4-32 reimbursed for the cost of preparing a final proposal and, if so, an

4-33 estimate of the amount of the partial reimbursement; and

4-34 (j) The date by which preliminary proposals must be submitted to the

4-35 public body, which must not be less than 30 days or more than 60 days

4-36 after the date on which the request for preliminary proposals is first

4-37 published in a newspaper pursuant to subsection 1.

4-38 Sec. 6. To qualify to participate in a project for the design and

4-39 construction of a public work, a design-build team must:

4-40 1. Obtain a performance bond and payment bond as required

4-41 pursuant to NRS 339.025;

4-42 2. Obtain insurance covering general liability and liability for errors

4-43 and omissions;

5-1 3. Not have been found liable for breach of contract with respect to a

5-2 previous project, other than a breach for legitimate cause;

5-3 4. Not have been disqualified from being awarded a contract

5-4 pursuant to NRS 338.017, 338.145 or 408.333; and

5-5 5. Ensure that the members of the design-build team possess the

5-6 licenses and certificates required to carry out the functions of their

5-7 respective professions within this state.

5-8 Sec. 7. 1. At least 30 days after the date by which preliminary

5-9 proposals must be submitted to the public body, the public body shall

5-10 select at least three but not more than five finalists from among the

5-11 design-build teams that submitted preliminary proposals. If the public

5-12 body does not receive at least three preliminary proposals from design-

5-13 build teams that the public body determines to be qualified pursuant to

5-14 this section and section 6 of this act, the public body may not contract

5-15 with a design-build team for the design and construction of the public

5-16 work.

5-17 2. The public body shall select finalists pursuant to subsection 1 by:

5-18 (a) Verifying that each design-build team which submitted a

5-19 preliminary proposal satisfies the requirements of section 6 of this act;

5-20 and

5-21 (b) Conducting an evaluation of the qualifications of each design-

5-22 build team that submitted a preliminary proposal, including, without

5-23 limitation, an evaluation of:

5-24 (1) The professional qualifications and experience of the members

5-25 of the design-build team;

5-26 (2) The performance history of the members of the design-build

5-27 team concerning other recent, similar projects completed by those

5-28 members, if any;

5-29 (3) The safety programs established and the safety records

5-30 accumulated by the members of the design-build team; and

5-31 (4) The proposed plan of the design-build team to manage the

5-32 design and construction of the public work that sets forth in detail the

5-33 ability of the design-build team to design and construct the public work.

5-34 Sec. 8. 1. After selecting the finalists pursuant to section 7 of this

5-35 act, the public body shall provide to each finalist a request for final

5-36 proposals for the public work. The request for final proposals must:

5-37 (a) Set forth the factors that the public body will use to select a design-

5-38 build team to design and construct the public work, including the relative

5-39 weight to be assigned to each factor; and

5-40 (b) Set forth the date by which final proposals must be submitted to

5-41 the public body.

5-42 2. A final proposal submitted by a design-build team pursuant to this

5-43 section must be prepared thoroughly, be responsive to the criteria that the

6-1 public body will use to select a design-build team to design and construct

6-2 the public work described in subsection 1 and comply with the provisions

6-3 of NRS 338.144. If the cost of construction is a factor in the selection of

6-4 a design-build team, a design-build team whose prime contractor has

6-5 submitted with its proposal a certificate of eligibility to receive a

6-6 preference in bidding on public works issued pursuant to NRS 338.147

6-7 shall be deemed to have submitted a better proposal than a competing

6-8 design-build team whose prime contractor has not submitted such a

6-9 certificate of eligibility if the amount proposed by the design-build team

6-10 is not more than 5 percent higher than the amount proposed by the

6-11 competing design-build team.

6-12 3. At least 30 days after receiving the final proposals for the public

6-13 work, the public body shall:

6-14 (a) Select the most cost-effective and responsive final proposal, using

6-15 the criteria set forth pursuant to subsection 1; or

6-16 (b) Reject all the final proposals.

6-17 4. If a public body selects a final proposal pursuant to paragraph (a)

6-18 of subsection 3, the public body shall, at its next regularly scheduled

6-19 meeting:

6-20 (a) Review and ratify the selection.

6-21 (b) Award the design-build contract to the design-build team whose

6-22 proposal is selected.

6-23 (c) Partially reimburse the unsuccessful finalists if partial

6-24 reimbursement was provided for in the request for preliminary proposals

6-25 pursuant to paragraph (i) of subsection 2 of section 5 of this act. The

6-26 amount of reimbursement must not exceed, for each unsuccessful

6-27 finalist, three percent of the total amount to be paid to the design-build

6-28 team as set forth in the design-build contract.

6-29 (d) Make available to the public a summary setting forth the factors

6-30 used by the public body to select the successful design-build team and the

6-31 ranking of the design-build teams who submitted final proposals. The

6-32 public body shall not release to a third party, or otherwise make public,

6-33 financial or proprietary information submitted by a design-build team.

6-34 5. A design-build team to whom a contract is awarded pursuant to

6-35 this section shall:

6-36 (a) Assume overall responsibility for ensuring that the design and

6-37 construction of the public work is completed in a satisfactory manner;

6-38 and

6-39 (b) Use the work force of the prime contractor on the design-build

6-40 team to construct at least 15 percent of the public work.

6-41 Sec. 9. A public body may employ a registered architect or licensed

6-42 professional engineer as a consultant to assist the public body in

7-1 overseeing the construction of a public work. An architect or engineer so

7-2 employed shall not:

7-3 1. Design or construct the public work; or

7-4 2. Assume overall responsibility for ensuring that the design or

7-5 construction of the public work is completed in a satisfactory manner.

7-6 Sec. 10. NRS 338.010 is hereby amended to read as follows:

7-7 338.010 As used in this chapter:

7-8 1. "Day labor" means all cases where public bodies, their officers,

7-9 agents or employees, hire, supervise and pay the wages thereof directly to a

7-10 workman or workmen employed by them on public works by the day and

7-11 not under a contract in writing.

7-12 2. "Design-build contract" means a contract between a public body

7-13 and a design-build team in which the design-build team agrees to design

7-14 and construct a public work.

7-15 3. "Design-build team" means an entity that consists of:

7-16 (a) At least one person who is licensed as a general engineering

7-17 contractor or a general building contractor pursuant to NRS 624.230 to

7-18 624.320, inclusive; and

7-19 (b) For a public work that consists of:

7-20 (1) A building and its site, at least one person who holds a

7-21 certificate of registration to practice architecture pursuant to chapter 623

7-22 of NRS.

7-23 (2) Anything other than a building and its site, at least one person

7-24 who holds a certificate of registration to practice architecture pursuant to

7-25 chapter 623 of NRS or is licensed as a professional engineer pursuant to

7-26 chapter 625 of NRS.

7-27 4. "Design professional" means a person with a professional license

7-28 or certificate issued pursuant to chapter 623, 623A or 625 of NRS.

7-29 5. "Eligible bidder" means a person who [was] is found to be a

7-30 responsible and responsive contractor or design-build team by a public

7-31 body which [awarded a contract] requests bids for a public work.

7-32 [3.] 6. "Offense" means failing to:

7-33 (a) Pay the prevailing wage required pursuant to this chapter;

7-34 (b) Pay the contributions for unemployment compensation required

7-35 pursuant to chapter 612 of NRS; or

7-36 (c) Provide and secure compensation for employees required pursuant to

7-37 chapters 616A to 617, inclusive, of NRS.

7-38 [4.] 7. "Prime contractor" means a person who:

7-39 (a) Contracts to construct an entire project;

7-40 (b) Coordinates all work performed on the entire project;

7-41 (c) Uses his own workforce to perform all or a part of the

7-42 construction, repair or reconstruction of the project; and

8-1 (d) Contracts for the services of any subcontractor or independent

8-2 contractor or is responsible for payment to any contracted subcontractors

8-3 or independent contractors.

8-4 8. "Public body" means the state, county, city, town, school district or

8-5 any public agency of this state or its political subdivisions sponsoring or

8-6 financing a public work.

8-7 [5.] 9. "Public work" means any project for the new construction,

8-8 repair or reconstruction of:

8-9 (a) A project financed in whole or in part from public money for:

8-10 (1) Public buildings;

8-11 (2) Jails and prisons;

8-12 (3) Public roads;

8-13 (4) Public highways;

8-14 (5) Public streets and alleys;

8-15 (6) Public utilities which are financed in whole or in part by public

8-16 money;

8-17 (7) Publicly owned water mains and sewers;

8-18 (8) Public parks and playgrounds;

8-19 (9) Public convention facilities which are financed at least in part with

8-20 public funds; and

8-21 (10) All other publicly owned works and property whose cost as a

8-22 whole exceeds $20,000. Each separate unit which is a part of a project is

8-23 included in the cost of the project for the purpose of determining whether a

8-24 project meets this threshold.

8-25 (b) A building for the University and Community College System of

8-26 Nevada of which 25 percent or more of the costs of the building as a whole

8-27 are paid from money appropriated by the state or federal money.

8-28 [6.] 10. "Specialty contractor" means a contractor whose operations

8-29 as such are the performance of construction work requiring special skill

8-30 and whose principal contracting business involves the use of specialized

8-31 building trades or crafts.

8-32 11. "Stand-alone underground utility project" means an

8-33 underground utility project that is not integrated into a larger project,

8-34 including, without limitation:

8-35 (a) An underground sewer line or an underground pipeline for the

8-36 conveyance of water, including facilities appurtenant thereto; and

8-37 (b) A project for the construction or installation of a storm drain,

8-38 including facilities appurtenant thereto,

8-39 that is not located at the site of a public work for the design and

8-40 construction of which a public body is authorized to contract with a

8-41 design-build team pursuant to subsection 2 of section 2 of this act.

8-42 12. "Wages" means:

8-43 (a) The basic hourly rate of pay; and

9-1 (b) The amount of pension, health and welfare, vacation and holiday

9-2 pay, the cost of apprenticeship training or other similar programs or other

9-3 bona fide fringe benefits which are a benefit to the workman.

9-4 [7.] 13. "Workman" means a skilled mechanic, skilled workman,

9-5 semiskilled mechanic, semiskilled workman or unskilled workman. The

9-6 term does not include a design professional.

9-7 Sec. 11. NRS 338.143 is hereby amended to read as follows:

9-8 338.143 1. Except as otherwise provided in subsection 6 and NRS

9-9 338.1906 and 338.1907, an agency or political subdivision of the state, or a

9-10 public officer, public employee or other person responsible for awarding a

9-11 contract for the construction, alteration or repair of a public work, shall not:

9-12 (a) Commence such a project, for which the estimated cost exceeds

9-13 $100,000, unless it advertises in a newspaper of general circulation in the

9-14 state for bids for the project; or

9-15 (b) Divide such a project into separate portions to avoid the

9-16 requirements of paragraph (a).

9-17 2. Except as otherwise provided in subsection 6, a public body that

9-18 maintains a list of properly licensed contractors who are interested in

9-19 receiving offers to bid on public works projects for which the estimated

9-20 cost is more than $25,000 but less than $100,000 shall solicit bids from not

9-21 more than three of the contractors on the list for a contract of that value for

9-22 the construction, alteration or repair of a public work. The public body

9-23 shall select contractors from the list in such a manner as to afford each

9-24 contractor an equal opportunity to bid on a public works project. A

9-25 properly licensed contractor must submit a written request annually to the

9-26 public body to remain on the list. Offers for bids which are made pursuant

9-27 to this subsection must be sent by certified mail.

9-28 3. Approved plans and specifications for the bids must be on file at a

9-29 place and time stated in the advertisement for the inspection of all persons

9-30 desiring to bid thereon and for other interested persons. Contracts for the

9-31 project must be awarded on the basis of bids received.

9-32 4. Any or all bids received in response to an advertisement for bids

9-33 may be rejected if the person responsible for awarding the contract

9-34 determines that:

9-35 (a) The bidder is not responsive or responsible;

9-36 (b) The quality of the services, materials, equipment or labor offered

9-37 does not conform to the approved plan or specifications; or

9-38 (c) The public interest would be served by such a rejection.

9-39 5. Before an agency or political subdivision of the state may commence

9-40 a project subject to the provisions of this section, based upon a

9-41 determination that the public interest would be served by rejecting any bids

9-42 received in response to an advertisement for bids, it shall prepare and make

9-43 available for public inspection a written statement containing:

10-1 (a) A list of all persons, including supervisors, who the agency or

10-2 political subdivision intends to assign to the project, together with their

10-3 classifications and an estimate of the direct and indirect costs of their labor;

10-4 (b) A list of all equipment that the agency or political subdivision

10-5 intends to use on the project, together with an estimate of the number of

10-6 hours each item of equipment will be used and the hourly cost to use each

10-7 item of equipment;

10-8 (c) An estimate of the cost of administrative support for the persons

10-9 assigned to the project;

10-10 (d) An estimate of the total cost of the project; and

10-11 (e) An estimate of the amount of money the agency or political

10-12 subdivision expects to save by rejecting the bids and performing the project

10-13 itself.

10-14 6. This section does not apply to:

10-15 (a) Any utility subject to the provisions of chapter 318 or 710 of NRS;

10-16 (b) Any work of construction, reconstruction, improvement and

10-17 maintenance of highways subject to NRS 408.323 or 408.327;

10-18 (c) Normal maintenance of the property of a school district; [or]

10-19 (d) The Las Vegas Valley water district created pursuant to chapter 167,

10-20 Statutes of Nevada 1947 [.] ; or

10-21 (e) The design and construction of a public work for which a public

10-22 body contracts with a design-build team pursuant to sections 2 to 9,

10-23 inclusive, of this act.

10-24 Sec. 12. NRS 338.143 is hereby amended to read as follows:

10-25 338.143 1. Except as otherwise provided in subsection 6, an agency

10-26 or political subdivision of the state, or a public officer, public employee or

10-27 other person responsible for awarding a contract for the construction,

10-28 alteration or repair of a public work, shall not:

10-29 (a) Commence such a project, for which the estimated cost exceeds

10-30 $100,000, unless it advertises in a newspaper of general circulation in the

10-31 state for bids for the project; or

10-32 (b) Divide such a project into separate portions to avoid the

10-33 requirements of paragraph (a).

10-34 2. Except as otherwise provided in subsection 6, a public body that

10-35 maintains a list of properly licensed contractors who are interested in

10-36 receiving offers to bid on public works projects for which the estimated

10-37 cost is more than $25,000 but less than $100,000 shall solicit bids from not

10-38 more than three of the contractors on the list for a contract of that value for

10-39 the construction, alteration or repair of a public work. The public body

10-40 shall select contractors from the list in such a manner as to afford each

10-41 contractor an equal opportunity to bid on a public works project. A

10-42 properly licensed contractor must submit a written request annually to the

11-1 public body to remain on the list. Offers for bids which are made pursuant

11-2 to this subsection must be sent by certified mail.

11-3 3. Approved plans and specifications for the bids must be on file at a

11-4 place and time stated in the advertisement for the inspection of all persons

11-5 desiring to bid thereon and for other interested persons. Contracts for the

11-6 project must be awarded on the basis of bids received.

11-7 4. Any or all bids received in response to an advertisement for bids

11-8 may be rejected if the person responsible for awarding the contract

11-9 determines that:

11-10 (a) The bidder is not responsive or responsible;

11-11 (b) The quality of the services, materials, equipment or labor offered

11-12 does not conform to the approved plan or specifications; or

11-13 (c) The public interest would be served by such a rejection.

11-14 5. Before an agency or political subdivision of the state may commence

11-15 a project subject to the provisions of this section, based upon a

11-16 determination that the public interest would be served by rejecting any bids

11-17 received in response to an advertisement for bids, it shall prepare and make

11-18 available for public inspection a written statement containing:

11-19 (a) A list of all persons, including supervisors, who the agency or

11-20 political subdivision intends to assign to the project, together with their

11-21 classifications and an estimate of the direct and indirect costs of their labor;

11-22 (b) A list of all equipment that the agency or political subdivision

11-23 intends to use on the project, together with an estimate of the number of

11-24 hours each item of equipment will be used and the hourly cost to use each

11-25 item of equipment;

11-26 (c) An estimate of the cost of administrative support for the persons

11-27 assigned to the project;

11-28 (d) An estimate of the total cost of the project; and

11-29 (e) An estimate of the amount of money the agency or political

11-30 subdivision expects to save by rejecting the bids and performing the project

11-31 itself.

11-32 6. This section does not apply to:

11-33 (a) Any utility subject to the provisions of chapter 318 or 710 of NRS;

11-34 (b) Any work of construction, reconstruction, improvement and

11-35 maintenance of highways subject to NRS 408.323 or 408.327;

11-36 (c) Normal maintenance of the property of a school district; [or]

11-37 (d) The Las Vegas Valley water district created pursuant to chapter 167,

11-38 Statutes of Nevada 1947 [.] ; or

11-39 (e) The design and construction of a public work for which a public

11-40 body contracts with a design-build team pursuant to sections 2 to 9,

11-41 inclusive, of this act.

12-1 Sec. 13. NRS 338.147 is hereby amended to read as follows:

12-2 338.147 1. [A] Except as otherwise provided in NRS 338.143 and

12-3 sections 2 to 9, inclusive, of this act, a public body shall award a contract

12-4 for a public work to the contractor who submits the best bid.

12-5 2. Except as otherwise provided in subsection [4] 8 or limited by

12-6 subsection [5,] 9, for the purposes of this section, a contractor who:

12-7 (a) Has been found to be a responsible and responsive contractor by the

12-8 public body; and

12-9 (b) At the time he submits his bid, provides to the public body [proof of

12-10 the payment of:] a copy of a certificate of eligibility to receive a

12-11 preference in bidding on public works issued to him by the state

12-12 contractors’ board pursuant to subsection 3,

12-13 shall be deemed to have submitted a better bid than a competing

12-14 contractor who has not provided a copy of such a valid certificate of

12-15 eligibility if the amount of his bid is not more than 5 percent higher than

12-16 the amount bid by the competing contractor.

12-17 3. The state contractors’ board shall issue a certificate of eligibility to

12-18 receive a preference in bidding on public works to a general contractor

12-19 who is licensed pursuant to the provisions of chapter 624 of NRS and

12-20 submits to the board an affidavit from a certified public accountant

12-21 setting forth that the general contractor has:

12-22 (a) Paid:

12-23 (1) The sales and use taxes imposed pursuant to chapters 372, 374

12-24 and 377 of NRS on materials used for construction in this state, including,

12-25 without limitation, construction that is undertaken or carried out on land

12-26 within the boundaries of this state that is managed by the Federal

12-27 Government or is on an Indian reservation or Indian colony, of not less

12-28 than $5,000 for each consecutive 12-month period for 60 months

12-29 immediately preceding the submission of [his bid;] the affidavit from the

12-30 certified public accountant;

12-31 (2) The motor vehicle privilege tax imposed pursuant to chapter 371

12-32 of NRS on the vehicles used in the operation of his business in this state of

12-33 not less than $5,000 for each consecutive 12-month period for 60 months

12-34 immediately preceding the submission of [his bid;] the affidavit from the

12-35 certified public accountant; or

12-36 (3) Any combination of such sales and use taxes and motor vehicle

12-37 privilege tax [,

12-38 shall be deemed to have submitted a better bid than a competing contractor

12-39 who has not provided proof of the payment of those taxes if the amount of

12-40 his bid is not more than 5 percent higher than the amount bid by the

12-41 competing contractor.

12-42 3. A contractor who has previously provided the public body awarding

12-43 a contract with the proof of payment required pursuant to subsection 2 may

13-1 update such proof on or before April 1, July 1, September 1 and December

13-2 1 rather than with each bid.

13-3 4.] ; or

13-4 (b) Acquired, by inheritance, gift or transfer through a stock option

13-5 plan for employees, all the assets and liabilities of a viable, operating

13-6 construction firm that possesses a:

13-7 (1) License as a general contractor pursuant to the provisions of

13-8 chapter 624 of NRS; and

13-9 (2) Certificate of eligibility to receive a preference in bidding on

13-10 public works.

13-11 4. For the purposes of complying with the requirements set forth in

13-12 paragraph (a) of subsection 3, a general contractor shall be deemed to

13-13 have paid:

13-14 (a) Sales and use taxes and motor vehicle privilege taxes paid in this

13-15 state by an affiliate or parent company of the contractor, if the affiliate

13-16 or parent company is also a general contractor; and

13-17 (b) Sales and use taxes paid in this state by a joint venture in which

13-18 the contractor is a participant, in proportion to the amount of interest the

13-19 contractor has in the joint venture.

13-20 5. A contractor who has received a certificate of eligibility to receive

13-21 a preference in bidding on public works from the state contractors’ board

13-22 pursuant to subsection 3 shall, at the time for the annual renewal of his

13-23 contractors’ license pursuant to NRS 624.283, submit to the board an

13-24 affidavit from a certified public accountant setting forth that the

13-25 contractor has, during the immediately preceding 12 months, paid the

13-26 taxes required pursuant to paragraph (a) of subsection 3 to maintain his

13-27 eligibility to hold such a certificate.

13-28 6. A contractor who fails to submit an affidavit to the board pursuant

13-29 to subsection 5 ceases to be eligible to receive a preference in bidding on

13-30 public works unless he reapplies for and receives a certificate of

13-31 eligibility pursuant to subsection 3.

13-32 7. If a contractor who applies to the state contractors’ board for a

13-33 certificate of eligibility to receive a preference in bidding on public works

13-34 submits false information to the board regarding the required payment of

13-35 taxes, the contractor is not eligible to receive a preference in bidding on

13-36 public works for a period of 5 years after the date on which the board

13-37 becomes aware of the submission of the false information.

13-38 8. If any federal statute or regulation precludes the granting of federal

13-39 assistance or reduces the amount of that assistance for a particular public

13-40 work because of the provisions of subsection 2, those provisions do not

13-41 apply insofar as their application would preclude or reduce federal

13-42 assistance for that work. The provisions of subsection 2 do not apply to any

13-43 contract for a public work which is expected to cost less than $250,000.

14-1 [5.] 9. Except as otherwise provided in [subsection 6,] subsection 2 of

14-2 section 8 of this act and subsection 2 of section 27 of this act, if a bid is

14-3 submitted by two or more contractors as a joint venture or by one of them

14-4 as a joint venturer, the provisions of subsection 2 apply only if both or all

14-5 of the joint venturers separately meet the requirements of that subsection.

14-6 [6. Except as otherwise provided in subsection 8, if a bid is submitted

14-7 by a joint venture and one or more of the joint venturers has responsibility

14-8 for the performance of the contract as described in subsection 7, the

14-9 provisions of subsection 2 apply only to those joint venturers who have

14-10 such responsibility.

14-11 7. For the purposes of subsection 6, a joint venturer has responsibility

14-12 for the performance of a contract if he has at least one of the following

14-13 duties or obligations delegated to him in writing in the contract creating the

14-14 joint venture:

14-15 (a) Supplying the labor necessary to perform the contract and paying the

14-16 labor and any related taxes and benefits;

14-17 (b) Supplying the equipment necessary to perform the contract and

14-18 paying any charges related to the equipment;

14-19 (c) Contracting with and making payments to any subcontractors; or

14-20 (d) Performing the recordkeeping for the joint venture and making any

14-21 payments to persons who provide goods or services related to the

14-22 performance of the contract.

14-23 8. The provisions of subsection 6 do not apply to a joint venture which

14-24 is formed for the sole purpose of circumventing any of the requirements of

14-25 this section.]

14-26 10. The state contractors’ board shall adopt regulations and may

14-27 assess reasonable fees relating to the certification of contractors for a

14-28 preference in bidding on public works.

14-29 11. A person or entity who believes that a contractor wrongfully

14-30 holds a certificate of eligibility to receive a preference in bidding on

14-31 public works may challenge the validity of the certificate by filing a

14-32 written objection with the public body to which the contractor has

14-33 submitted a bid or proposal on a contract for the construction of a public

14-34 work. A written objection authorized pursuant to this subsection must:

14-35 (a) Set forth proof or substantiating evidence to support the belief of

14-36 the person or entity that the contractor wrongfully holds a certificate of

14-37 eligibility to receive a preference in bidding on public works; and

14-38 (b) Be filed with the public body at or after the time at which the

14-39 contractor submitted the bid or proposal to the public body and before

14-40 the time at which the public body awards the contract for which the bid

14-41 or proposal was submitted.

14-42 12. If a public body receives a written objection pursuant to

14-43 subsection 11, the public body shall determine whether the objection is

15-1 accompanied by the proof or substantiating evidence required pursuant

15-2 to paragraph (a) of that subsection. If the public body determines that the

15-3 objection is not accompanied by the required proof or substantiating

15-4 evidence, the public body shall dismiss the objection and may proceed

15-5 immediately to award the contract. If the public body determines that the

15-6 objection is accompanied by the required proof or substantiating

15-7 evidence, the public body shall determine whether the contractor

15-8 qualifies for the certificate pursuant to the provisions of this section and

15-9 may proceed to award the contract accordingly.

15-10 Sec. 13.5. NRS 338.147 is hereby amended to read as follows:

15-11 338.147 1. [A] Except as otherwise provided in NRS 338.143, a

15-12 public body shall award a contract for a public work to the contractor who

15-13 submits the best bid.

15-14 2. Except as otherwise provided in subsection [4] 8 or limited by

15-15 subsection [5,] 9, for the purposes of this section, a contractor who:

15-16 (a) Has been found to be a responsible and responsive contractor by the

15-17 public body; and

15-18 (b) At the time he submits his bid, provides to the public body [proof of

15-19 the payment of:] a copy of a certificate of eligibility to receive a

15-20 preference in bidding on public works issued to him by the state

15-21 contractors’ board pursuant to subsection 3,

15-22 shall be deemed to have submitted a better bid than a competing

15-23 contractor who has not provided a copy of such a valid certificate of

15-24 eligibility if the amount of his bid is not more than 5 percent higher than

15-25 the amount bid by the competing contractor.

15-26 3. The state contractors’ board shall issue a certificate of eligibility to

15-27 receive a preference in bidding on public works to a general contractor

15-28 who is licensed pursuant to the provisions of chapter 624 of NRS and

15-29 submits to the board an affidavit from a certified public accountant

15-30 setting forth that the general contractor has:

15-31 (a) Paid:

15-32 (1) The sales and use taxes imposed pursuant to chapters 372, 374

15-33 and 377 of NRS on materials used for construction in this state, including,

15-34 without limitation, construction that is undertaken or carried out on land

15-35 within the boundaries of this state that is managed by the Federal

15-36 Government or is on an Indian reservation or Indian colony, of not less

15-37 than $5,000 for each consecutive 12-month period for 60 months

15-38 immediately preceding the submission of [his bid;] the affidavit from the

15-39 certified public accountant;

15-40 (2) The motor vehicle privilege tax imposed pursuant to chapter 371

15-41 of NRS on the vehicles used in the operation of his business in this state of

15-42 not less than $5,000 for each consecutive 12-month period for 60 months

16-1 immediately preceding the submission of [his bid;] the affidavit from the

16-2 certified public accountant; or

16-3 (3) Any combination of such sales and use taxes and motor vehicle

16-4 privilege tax [,

16-5 shall be deemed to have submitted a better bid than a competing contractor

16-6 who has not provided proof of the payment of those taxes if the amount of

16-7 his bid is not more than 5 percent higher than the amount bid by the

16-8 competing contractor.

16-9 3. A contractor who has previously provided the public body awarding

16-10 a contract with the proof of payment required pursuant to subsection 2 may

16-11 update such proof on or before April 1, July 1, September 1 and December

16-12 1 rather than with each bid.

16-13 4.] ; or

16-14 (b) Acquired, by inheritance, gift or transfer through a stock option

16-15 plan for employees, all the assets and liabilities of a viable, operating

16-16 construction firm that possesses a:

16-17 (1) License as a general contractor pursuant to the provisions of

16-18 chapter 624 of NRS; and

16-19 (2) Certificate of eligibility to receive a preference in bidding on

16-20 public works.

16-21 4. For the purposes of complying with the requirements set forth in

16-22 paragraph (a) of subsection 3, a general contractor shall be deemed to

16-23 have paid:

16-24 (a) Sales and use taxes and motor vehicle privilege taxes paid in this

16-25 state by an affiliate or parent company of the contractor, if the affiliate

16-26 or parent company is also a general contractor; and

16-27 (b) Sales and use taxes paid in this state by a joint venture in which

16-28 the contractor is a participant, in proportion to the amount of interest the

16-29 contractor has in the joint venture.

16-30 5. A contractor who has received a certificate of eligibility to receive

16-31 a preference in bidding on public works from the state contractors’ board

16-32 pursuant to subsection 3 shall, at the time for the annual renewal of his

16-33 contractors’ license pursuant to NRS 624.283, submit to the board an

16-34 affidavit from a certified public accountant setting forth that the

16-35 contractor has, during the immediately preceding 12 months, paid the

16-36 taxes required pursuant to paragraph (a) of subsection 3 to maintain his

16-37 eligibility to hold such a certificate.

16-38 6. A contractor who fails to submit an affidavit to the board pursuant

16-39 to subsection 5 ceases to be eligible to receive a preference in bidding on

16-40 public works unless he reapplies for and receives a certificate of

16-41 eligibility pursuant to subsection 3.

16-42 7. If a contractor who applies to the state contractors’ board for a

16-43 certificate of eligibility to receive a preference in bidding on public works

17-1 submits false information to the board regarding the required payment of

17-2 taxes, the contractor is not eligible to receive a preference in bidding on

17-3 public works for a period of 5 years after the date on which the board

17-4 becomes aware of the submission of the false information.

17-5 8. If any federal statute or regulation precludes the granting of federal

17-6 assistance or reduces the amount of that assistance for a particular public

17-7 work because of the provisions of subsection 2, those provisions do not

17-8 apply insofar as their application would preclude or reduce federal

17-9 assistance for that work. The provisions of subsection 2 do not apply to any

17-10 contract for a public work which is expected to cost less than $250,000.

17-11 [5. Except as otherwise provided in subsection 6, if]

17-12 9. If a bid is submitted by two or more contractors as a joint venture or

17-13 by one of them as a joint venturer, the provisions of subsection 2 apply only

17-14 if both or all of the joint venturers separately meet the requirements of that

17-15 subsection.

17-16 [6. Except as otherwise provided in subsection 8, if a bid is submitted

17-17 by a joint venture and one or more of the joint venturers has responsibility

17-18 for the performance of the contract as described in subsection 7, the

17-19 provisions of subsection 2 apply only to those joint venturers who have

17-20 such responsibility.

17-21 7. For the purposes of subsection 6, a joint venturer has responsibility

17-22 for the performance of a contract if he has at least one of the following

17-23 duties or obligations delegated to him in writing in the contract creating the

17-24 joint venture:

17-25 (a) Supplying the labor necessary to perform the contract and paying the

17-26 labor and any related taxes and benefits;

17-27 (b) Supplying the equipment necessary to perform the contract and

17-28 paying any charges related to the equipment;

17-29 (c) Contracting with and making payments to any subcontractors; or

17-30 (d) Performing the recordkeeping for the joint venture and making any

17-31 payments to persons who provide goods or services related to the

17-32 performance of the contract.

17-33 8. The provisions of subsection 6 do not apply to a joint venture which

17-34 is formed for the sole purpose of circumventing any of the requirements of

17-35 this section.]

17-36 10. The state contractors’ board shall adopt regulations and may

17-37 assess reasonable fees relating to the certification of contractors for a

17-38 preference in bidding on public works.

17-39 11. A person or entity who believes that a contractor wrongfully

17-40 holds a certificate of eligibility to receive a preference in bidding on

17-41 public works may challenge the validity of the certificate by filing a

17-42 written objection with the public body to which the contractor has

18-1 submitted a bid or proposal on a contract for the construction of a public

18-2 work. A written objection authorized pursuant to this subsection must:

18-3 (a) Set forth proof or substantiating evidence to support the belief of

18-4 the person or entity that the contractor wrongfully holds a certificate of

18-5 eligibility to receive a preference in bidding on public works; and

18-6 (b) Be filed with the public body at or after the time at which the

18-7 contractor submitted the bid or proposal to the public body and before

18-8 the time at which the public body awards the contract for which the bid

18-9 or proposal was submitted.

18-10 12. If a public body receives a written objection pursuant to

18-11 subsection 11, the public body shall determine whether the objection is

18-12 accompanied by the proof or substantiating evidence required pursuant

18-13 to paragraph (a) of that subsection. If the public body determines that the

18-14 objection is not accompanied by the required proof or substantiating

18-15 evidence, the public body shall dismiss the objection and may proceed

18-16 immediately to award the contract. If the public body determines that the

18-17 objection is accompanied by the required proof or substantiating

18-18 evidence, the public body shall determine whether the contractor

18-19 qualifies for the certificate pursuant to the provisions of this section and

18-20 may proceed to award the contract accordingly.

18-21 Sec. 14. NRS 338.155 is hereby amended to read as follows:

18-22 338.155 [1.] If a public body enters into a contract with a design

18-23 professional who is not a member of a design-build team for the provision

18-24 of services in connection with a public work, the contract:

18-25 [(a)] 1. Must set forth:

18-26 [(1)] (a) The specific period within which the public body must pay

18-27 the design professional.

18-28 [(2)] (b) The specific period and manner in which the public body

18-29 may dispute a payment or portion thereof that the design professional

18-30 alleges is due.

18-31 [(3)] (c) The terms of any penalty that will be imposed upon the

18-32 public body if the public body fails to pay the design professional within

18-33 the specific period set forth in the contract pursuant to [subparagraph (1).

18-34 (4)] paragraph (a).

18-35 (d) That the prevailing party in an action to enforce the contract is

18-36 entitled to reasonable attorney’s fees and costs.

18-37 [(b)] 2. May set forth the terms of any discount that the public body

18-38 will receive if the public body pays the design professional within the

18-39 specific period set forth in the contract pursuant to [subparagraph (1) of]

18-40 paragraph (a) [.

18-41 2. As used in this section, "design professional" means a person with a

18-42 professional license or certificate issued pursuant to chapter 623, 623A or

18-43 625 of NRS.] of subsection 1.

19-1 Sec. 14.5. NRS 341.161 is hereby amended to read as follows:

19-2 341.161 1. The board may, with the approval of the interim finance

19-3 committee when the legislature is not in regular or special session, or with

19-4 the approval of the legislature by concurrent resolution when the legislature

19-5 is in regular or special session, let to a contractor licensed under chapter

19-6 624 of NRS a contract for services which assist the architect in the design

19-7 of a project of capital improvement. The board shall for that purpose

19-8 participate in the development of plans, outlines of specifications and

19-9 estimates of costs.

19-10 2. The board shall adopt regulations establishing procedures for:

19-11 (a) The determination of the qualifications of contractors to bid for

19-12 contracts for services described in subsection 1.

19-13 (b) The bidding and awarding of such contracts, subject to the

19-14 provisions of subsection 3.

19-15 (c) The awarding of construction contracts [, subject to the provisions of

19-16 subsection 4,] based on a final cost of the project which the contractor

19-17 guarantees will not be exceeded.

19-18 (d) The scheduling and controlling of projects.

19-19 3. Bids on contracts for services which assist the architect in the design

19-20 of a project of capital improvement must state separately the contractor’s

19-21 cost for:

19-22 (a) Assisting the architect in the design of the project.

19-23 (b) Obtaining all bids for subcontracts.

19-24 (c) Administering the construction contract.

19-25 4. [A contractor who is:

19-26 (a) Qualified under the regulations of the board to bid for a contract for

19-27 services described in subsection 1; and

19-28 (b) Awarded that contract,

19-29 is entitled to be awarded the construction contract for the project if his

19-30 work under the contract for services is satisfactory to the board and he

19-31 guarantees a final cost for the project which the board is willing to accept.

19-32 5.] A person who furnishes services under a contract awarded pursuant

19-33 to subsection 1 is a contractor subject to all provisions pertaining to a

19-34 contractor in Title 28 of NRS.

19-35 Sec. 15. Chapter 408 of NRS is hereby amended by adding thereto the

19-36 provisions set forth as sections 16 to 28, inclusive, of this act.

19-37 Sec. 16. As used in sections 16 to 28, inclusive, of this act, unless the

19-38 context otherwise requires, the words and terms defined in sections 17 to

19-39 20, inclusive, of this act have the meanings ascribed to them in those

19-40 sections.

20-1 Sec. 17. "Design-build contract" means a contract between the

20-2 department and a design-build team in which the design-build team

20-3 agrees to design and construct a project.

20-4 Sec. 18. "Design-build team" means an entity that consists of:

20-5 1. At least one person who is licensed as a general engineering

20-6 contractor or a general building contractor pursuant to NRS 624.230 to

20-7 624.320, inclusive; and

20-8 2. At least one person who holds a certificate of registration to

20-9 practice architecture pursuant to chapter 623 of NRS or is licensed as a

20-10 professional engineer pursuant to chapter 625 of NRS.

20-11 Sec. 19. "Prime contractor" means a person who:

20-12 1. Contracts to construct an entire project;

20-13 2. Coordinates all work performed on the entire project;

20-14 3. Uses his own workforce to perform all or a part of the

20-15 construction of the project; and

20-16 4. Contracts for the services of any subcontractor or independent

20-17 contractor or is responsible for payment to any contracted subcontractors

20-18 or independent contractors.

20-19 Sec. 20. "Project" means a project for the construction,

20-20 reconstruction or improvement of a highway.

20-21 Sec. 21. 1. The department may contract with a design-build team

20-22 for the design and construction of a project if the department determines

20-23 that:

20-24 (a) Except as otherwise provided in subsection 2, the estimated cost of

20-25 the project exceeds $30,000,000; and

20-26 (b) Contracting with a design-build team will enable the department

20-27 to:

20-28 (1) Design and construct the project at a cost that is significantly

20-29 lower than the cost that the department would incur to design and

20-30 construct the project using a different method;

20-31 (2) Design and construct the project in a shorter time than would be

20-32 required to complete the project using a different method, if exigent

20-33 circumstances require that the project be designed and constructed

20-34 within a short time; or

20-35 (3) Ensure that the design and construction of the project is

20-36 properly coordinated, if the project is unique, highly technical and

20-37 complex in nature.

20-38 2. Notwithstanding the provisions of subsection 1, the department

20-39 may, once in each fiscal year, contract with a design-build team for the

20-40 design and construction of a project the estimated cost of which is at least

20-41 $5,000,000 but less than $30,000,000 if the department makes the

20-42 determinations otherwise required pursuant to paragraph (b) of

20-43 subsection 1.

21-1 Sec. 22. 1. The department shall not contract with a design-build

21-2 team with respect to a project unless the board makes the determinations,

21-3 at a public meeting, that are required pursuant to section 21 of this act.

21-4 2. If the department is required to hold a public meeting pursuant to

21-5 this section, the department shall publish notice of the meeting at least

21-6 once each week for 3 consecutive weeks in:

21-7 (a) A newspaper of general circulation published in each county in

21-8 which the project is proposed to be constructed or, if there is no such

21-9 newspaper, in a newspaper of general circulation in each county

21-10 published in this state; and

21-11 (b) A newspaper of general circulation in this state.

21-12 Sec. 23. If the department desires to contract with a design-build

21-13 team pursuant to sections 21 and 22 of this act, the department must

21-14 select the design-build team in accordance with sections 24 to 27,

21-15 inclusive, of this act.

21-16 Sec. 24. 1. The department shall advertise for preliminary

21-17 proposals for the design and construction of a project by a design-build

21-18 team at least twice each week for 3 consecutive weeks in:

21-19 (a) A newspaper of general circulation published in each county in

21-20 which the project is proposed to be constructed or, if there is no such

21-21 newspaper, in a newspaper of general circulation in each county

21-22 published in this state; and

21-23 (b) A newspaper of general circulation in this state.

21-24 2. A request for preliminary proposals published pursuant to

21-25 subsection 1 must include, without limitation:

21-26 (a) A description of the proposed project;

21-27 (b) Separate estimates of the costs of designing and constructing the

21-28 project;

21-29 (c) The dates on which it is anticipated that the separate phases of the

21-30 design and construction of the project will begin and end;

21-31 (d) A statement setting forth the place and time in which a design-

21-32 build team desiring to submit a proposal for the project may obtain the

21-33 information necessary to submit a proposal, including, without

21-34 limitation, the extent to which designs must be completed for both

21-35 preliminary and final proposals and any other requirements for the

21-36 design and construction of the project that the department determines to

21-37 be necessary;

21-38 (e) A list of the requirements set forth in section 25 of this act;

21-39 (f) A list of the factors that the department will use to evaluate design-

21-40 build teams who submit a proposal for the project, including, without

21-41 limitation:

21-42 (1) The relative weight to be assigned to each factor; and

22-1 (2) A disclosure of whether the factors that are not related to cost

22-2 are, when considered as a group, more or less important in the process of

22-3 evaluation than the factor of cost;

22-4 (g) Notice that a design-build team desiring to submit a proposal for

22-5 the project must include with its proposal the information used by the

22-6 department to determine finalists among the design-build teams

22-7 submitting proposals pursuant to subsection 2 of section 26 of this act

22-8 and a description of that information;

22-9 (h) A statement that a design-build team whose prime contractor

22-10 holds a certificate of eligibility to receive a preference in bidding on

22-11 public works issued pursuant to NRS 338.147 should submit a copy of

22-12 the certificate of eligibility with its proposal;

22-13 (i) A statement as to whether a bidding design-build team that is

22-14 selected as a finalist pursuant to section 26 of this act but is not awarded

22-15 the design-build contract pursuant to section 27 of this act will be

22-16 partially reimbursed for the cost of preparing a final proposal and, if so,

22-17 an estimate of the amount of the partial reimbursement; and

22-18 (j) The date by which preliminary proposals must be submitted to the

22-19 department, which must not be less than 30 days or more than 60 days

22-20 after the date on which the request for preliminary proposals is first

22-21 published in a newspaper pursuant to subsection 1.

22-22 Sec. 25. To qualify to participate in the design and construction of a

22-23 project for the department, a design-build team must:

22-24 1. Obtain a performance bond and payment bond as the department

22-25 may require;

22-26 2. Obtain insurance covering general liability and liability for errors

22-27 and omissions;

22-28 3. Not have been found liable for breach of contract with respect to a

22-29 previous project, other than a breach for legitimate cause;

22-30 4. Not have been disqualified from being awarded a contract

22-31 pursuant to NRS 338.017, 338.145 or 408.333; and

22-32 5. Ensure that the members of the design-build team possess the

22-33 licenses and certificates required to carry out the functions of their

22-34 respective professions within this state.

22-35 Sec. 26. 1. At least 30 days after the date by which preliminary

22-36 proposals must be submitted to the department, the department shall

22-37 select at least three but not more than five finalists from among the

22-38 design-build teams that submitted preliminary proposals. If the

22-39 department does not receive at least three preliminary proposals from

22-40 design-build teams that the department determines to be qualified

22-41 pursuant to this section and section 25 of this act, the department may

22-42 not contract with a design-build team for the design and construction of

22-43 the project.

23-1 2. The department shall select finalists pursuant to subsection 1 by:

23-2 (a) Verifying that each design-build team which submitted a

23-3 preliminary proposal satisfies the requirements of section 25 of this act;

23-4 and

23-5 (b) Conducting an evaluation of the qualifications of each design-

23-6 build team that submitted a preliminary proposal, including, without

23-7 limitation, an evaluation of:

23-8 (1) The professional qualifications and experience of the members

23-9 of the design-build team;

23-10 (2) The performance history of the members of the design-build

23-11 team concerning other recent, similar projects completed by those

23-12 members, if any;

23-13 (3) The safety programs established and the safety records

23-14 accumulated by the members of the design-build team; and

23-15 (4) The proposed plan of the design-build team to manage the

23-16 design and construction of the project that sets forth in detail the ability

23-17 of the design-build team to design and construct the project.

23-18 Sec. 27. 1. After selecting the finalists pursuant to section 26 of

23-19 this act, the department shall provide to each finalist a request for final

23-20 proposals for the project. The request for final proposals must:

23-21 (a) Set forth the factors that the department will use to select a design-

23-22 build team to design and construct the project, including the relative

23-23 weight to be assigned to each factor; and

23-24 (b) Set forth the date by which final proposals must be submitted to

23-25 the department.

23-26 2. A final proposal submitted by a design-build team pursuant to this

23-27 section must be prepared thoroughly, be responsive to the criteria that the

23-28 department will use to select a design-build team to design and construct

23-29 the project described in subsection 1 and comply with the provisions of

23-30 NRS 338.144. If the cost of construction is a factor in the selection of a

23-31 design-build team, a design-build team whose prime contractor has

23-32 submitted with its proposal a certificate of eligibility to receive a

23-33 preference in bidding on public works issued pursuant to NRS 338.147

23-34 shall be deemed to have submitted a better proposal than a competing

23-35 design-build team whose prime contractor has not submitted such a

23-36 certificate of eligibility if the amount proposed by the design-build team

23-37 is not more than 5 percent higher than the amount proposed by the

23-38 competing design-build team.

23-39 3. At least 30 days after receiving the final proposals for the project,

23-40 the department shall:

23-41 (a) Select the most cost-effective and responsive final proposal, using

23-42 the criteria set forth pursuant to subsection 1; or

23-43 (b) Reject all the final proposals.

24-1 4. If the department selects a final proposal pursuant to paragraph

24-2 (a) of subsection 3, the department shall hold a public meeting to:

24-3 (a) Review and ratify the selection.

24-4 (b) Award the design-build contract to the design-build team whose

24-5 proposal is selected.

24-6 (c) Partially reimburse the unsuccessful finalists if partial

24-7 reimbursement was provided for in the request for preliminary proposals

24-8 pursuant to paragraph (i) of subsection 2 of section 24 of this act. The

24-9 amount of reimbursement must not exceed, for each unsuccessful

24-10 finalist, three percent of the total amount to be paid to the design-build

24-11 team as set forth in the design-build contract.

24-12 (d) Make available to the public a summary setting forth the factors

24-13 used by the department to select the successful design-build team and the

24-14 ranking of the design-build teams who submitted final proposals. The

24-15 department shall not release to a third party, or otherwise make public,

24-16 financial or proprietary information submitted by a design-build team.

24-17 5. A design-build team to whom a contract is awarded pursuant to

24-18 this section shall:

24-19 (a) Assume overall responsibility for ensuring that the design and

24-20 construction of the project is completed in a satisfactory manner; and

24-21 (b) Use the work force of the prime contractor on the design-build

24-22 team to construct at least 15 percent of the project.

24-23 Sec. 28. The department may employ a registered architect or

24-24 licensed professional engineer as a consultant to assist the department in

24-25 overseeing the construction of a project. An architect or engineer so

24-26 employed shall not:

24-27 1. Design, construct, reconstruct or improve the highway; or

24-28 2. Assume overall responsibility for ensuring that the design or

24-29 construction of the project is completed in a satisfactory manner.

24-30 Sec. 29. NRS 408.215 is hereby amended to read as follows:

24-31 408.215 1. The director has charge of all the records of the

24-32 department, keeping records of all proceedings pertaining to the department

24-33 and keeping on file information, plans, specifications, estimates, statistics

24-34 and records prepared by the department, except those financial statements

24-35 described in NRS 408.333 [,] and the financial or proprietary information

24-36 described in paragraph (d) of subsection 4 of section 27 of this act, which

24-37 must not become matters of public record.

24-38 2. The director may photograph, microphotograph or film or dispose of

24-39 the records of the department referred to in subsection 1 as provided in

24-40 NRS 239.051, 239.080 and 239.085.

24-41 3. The director shall maintain an index or record of deeds or other

24-42 references of title or interests in and to all lands or interests in land owned

24-43 or acquired by the department.

25-1 4. The director shall adopt such regulations as may be necessary to

25-2 carry out and enforce the provisions of this chapter.

25-3 Sec. 30. NRS 408.317 is hereby amended to read as follows:

25-4 408.317 1. [All] Except as otherwise provided in sections 16 to 28,

25-5 inclusive, of this act, all work of construction, reconstruction,

25-6 improvement and maintenance of highways as provided under the

25-7 provisions of this chapter is under the supervision and direction of the

25-8 director and must be performed in accordance with the plans, specifications

25-9 and contracts prepared by him.

25-10 2. All maintenance and repair of highways when performed by the

25-11 department must be paid out of the state highway fund.

25-12 Sec. 31. NRS 408.327 is hereby amended to read as follows:

25-13 408.327 Except as otherwise provided in sections 16 to 28, inclusive,

25-14 of this act:

25-15 1. Whenever the provisions of NRS 408.323 do not apply, the director

25-16 shall advertise for bids for such work according to the plans and

25-17 specifications prepared by him.

25-18 2. The advertisement must state the place where the bidders may obtain

25-19 or inspect the plans and specifications and the time and place for opening

25-20 the plans and specifications.

25-21 3. Publication of the advertisement must be made at least once a week

25-22 for 2 consecutive weeks for a total of at least two publications in a

25-23 newspaper of general circulation in the county in which the major portion

25-24 of the proposed improvement or construction is to be made, and the

25-25 advertisement must also be published at least once a week for 2 consecutive

25-26 weeks for a total of at least two publications in one or more daily papers of

25-27 general circulation throughout the state. The first publication of the

25-28 advertisement in the daily newspapers having general circulation

25-29 throughout the state must be made not less than 15 days before the time set

25-30 for opening bids.

25-31 Sec. 32. NRS 408.333 is hereby amended to read as follows:

25-32 408.333 Except as otherwise provided in sections 16 to 28, inclusive,

25-33 of this act:

25-34 1. Before furnishing any person proposing to bid on any advertised

25-35 work with the plans and specifications for such work, the director shall

25-36 require from the person a statement, verified under oath, in the form of

25-37 answers to questions contained in a standard form of questionnaire and

25-38 financial statement, which must include a complete statement of the

25-39 person’s financial ability and experience in performing public work of a

25-40 similar nature.

25-41 2. Such statements must be filed with the director in ample time to

25-42 permit the department to verify the information contained therein in

25-43 advance of furnishing proposal forms, plans and specifications to any

26-1 person proposing to bid on the advertised public work, in accordance with

26-2 the regulations of the department.

26-3 3. Whenever the director is not satisfied with the sufficiency of the

26-4 answers contained in the questionnaire and financial statement, he may

26-5 refuse to furnish the person with plans and specifications and the official

26-6 proposal forms on the advertised project. Any bid of any person to whom

26-7 plans and specifications and the official proposal forms have not been

26-8 issued in accordance with this section must be disregarded, and the certified

26-9 check, cash or undertaking of such a bidder returned forthwith.

26-10 4. Any person who is disqualified by the director, in accordance with

26-11 the provisions of this section, may request, in writing, a hearing before the

26-12 director and present again his check, cash or undertaking and such further

26-13 evidence with respect to his financial responsibility, organization, plant and

26-14 equipment, or experience, as might tend to justify, in his opinion, issuance

26-15 to him of the plans and specifications for the work.

26-16 5. Such a person may appeal the decision of the director to the board

26-17 no later than 5 days before the opening of the bids on the project. If the

26-18 appeal is sustained by the board, the person must be granted the rights and

26-19 privileges of all other bidders.

26-20 Sec. 33. NRS 408.337 is hereby amended to read as follows:

26-21 408.337 Except as otherwise provided in sections 16 to 28, inclusive,

26-22 of this act:

26-23 1. All bids must be accompanied by an undertaking executed by a

26-24 corporate surety authorized to do business in the state, or by cash or a

26-25 certified check in an amount equal to at least 5 percent of the amount bid.

26-26 2. If the successful bidder fails to execute the contract in accordance

26-27 with his bid and give any bond required by law and the contract and bond

26-28 are not postmarked or delivered to the department within 20 days after

26-29 award of the contract, the undertaking, cash or certified check is forfeited

26-30 and the proceeds must be paid into the state highway fund.

26-31 3. The failure of the successful bidder to furnish any bond required of

26-32 him by law within the time fixed for his execution of the contract

26-33 constitutes a failure to execute the contract.

26-34 4. If the director deems it is for the best interests of the state, he may,

26-35 on refusal or failure of the successful bidder to execute the contract, award

26-36 it to the second lowest responsible bidder. If the second lowest responsible

26-37 bidder fails or refuses to execute the contract, the director may likewise

26-38 award it to the third lowest responsible bidder. On the failure or refusal to

26-39 execute the contract of the second or third lowest bidder to whom a

26-40 contract is so awarded, their bidder’s security is likewise forfeited to the

26-41 state.

26-42 5. The bidder’s security of the second and third lowest responsible

26-43 bidders may be withheld by the department until the contract has been

27-1 finally executed and the bond given as required under the provisions of the

27-2 contract, at which time the security must be returned. The bidder’s security

27-3 submitted by all other unsuccessful bidders must be returned to them within

27-4 10 days after the contract is awarded.

27-5 Sec. 34. NRS 408.343 is hereby amended to read as follows:

27-6 408.343 Except as otherwise provided in sections 16 to 28, inclusive,

27-7 of this act:

27-8 1. All bids must be submitted under sealed cover and received at the

27-9 address in Nevada stated in the advertisement for bids and must be opened

27-10 publicly and read at the time stated in the advertisement.

27-11 2. No bids may be received after the time stated in the advertisement

27-12 even though bids are not opened exactly at the time stated in the

27-13 advertisement. No bid may be opened before that time.

27-14 3. Any bid may be withdrawn at any time before the time stated in the

27-15 advertisement only by written request or telegram filed with the director

27-16 and executed by the bidder or his duly authorized representative. The

27-17 withdrawal of a bid does not prejudice the right of the bidder to file a new

27-18 bid before the time stated in the advertisement.

27-19 4. The department may reject any bid or all bids if, in the opinion of

27-20 the department, the bids are unbalanced, incomplete, contain irregularities

27-21 of any kind or for any good cause.

27-22 5. Until the final award of the contract, the department may reject or

27-23 accept any bids and may waive technical errors contained in the bids, as

27-24 may be deemed best for the interests of the state.

27-25 6. In awarding a contract, the department shall make the award to the

27-26 lowest responsible bidder who has qualified and submitted his bid in

27-27 accordance with the provisions of this chapter.

27-28 Sec. 35. NRS 625.530 is hereby amended to read as follows:

27-29 625.530 Except as otherwise provided in sections 2 to 9, inclusive,

27-30 and 16 to 28, inclusive, of this act:

27-31 1. The State of Nevada or any of its political subdivisions, including a

27-32 county, city or town, shall not engage in any public work requiring the

27-33 practice of professional engineering or land surveying, unless the maps,

27-34 plans, specifications, reports and estimates have been prepared by, and the

27-35 work executed under the supervision of, a professional engineer,

27-36 professional land surveyor or registered architect.

27-37 2. The provisions of this section do not:

27-38 (a) Apply to any public work wherein the expenditure for the complete

27-39 project of which the work is a part does not exceed $35,000.

27-40 (b) Include any maintenance work undertaken by the State of Nevada or

27-41 its political subdivisions.

28-1 (c) Authorize a professional engineer, registered architect or

28-2 professional land surveyor to practice in violation of any of the provisions

28-3 of chapter 623 of NRS or this chapter.

28-4 (d) Require the services of an architect registered pursuant to the

28-5 provisions of chapter 623 of NRS for the erection of buildings or structures

28-6 manufactured in an industrial plant, if those buildings or structures meet the

28-7 requirements of local building codes of the jurisdiction in which they are

28-8 being erected.

28-9 3. The selection of a professional engineer, professional land surveyor

28-10 or registered architect to perform services pursuant to subsection 1 must be

28-11 made on the basis of the competence and qualifications of the engineer,

28-12 land surveyor or architect for the type of services to be performed and not

28-13 on the basis of competitive fees. If, after selection of the engineer, land

28-14 surveyor or architect, an agreement upon a fair and reasonable fee cannot

28-15 be reached with him, the public agency may terminate negotiations and

28-16 select another engineer, land surveyor or architect.

28-17 Sec. 36. NRS 341.171 is hereby repealed.

28-18 Sec. 37. 1. The interim advisory committee to study the use of

28-19 design-build contracting within this state is hereby created. The interim

28-20 advisory committee consists of 12 members who are appointed as follows:

28-21 (a) One member appointed by the Northern Nevada Chapter of the

28-22 Associated General Contractors.

28-23 (b) One member appointed by the Southern Nevada Chapter of the

28-24 Associated General Contractors.

28-25 (c) One member appointed by the Northern Nevada Chapter of the

28-26 Associated Builders and Contractors.

28-27 (d) One member appointed by the Southern Nevada Chapter of the

28-28 Associated Builders and Contractors.

28-29 (e) One member appointed by the Nevada chapter of the American

28-30 Institute of Architecture.

28-31 (f) One member appointed by the American Consulting Engineers

28-32 Council of Nevada.

28-33 (g) One member appointed by the Department of Transportation of the

28-34 State of Nevada.

28-35 (h) One member appointed by the Southern Nevada Water Authority.

28-36 (i) One member appointed by the Board of County Commissioners of

28-37 Clark County.

28-38 (j) One member appointed by the governing body of the City of Las

28-39 Vegas.

28-40 (k) One member appointed by the governing body of the City of

28-41 Henderson.

29-1 (l) One member appointed by the governing body of the City of North

29-2 Las Vegas.

29-3 2. Members of the interim advisory committee shall serve without

29-4 compensation, travel expenses or subsistence allowances, except as they

29-5 may be provided by the members’ respective agencies and organizations.

29-6 3. The interim advisory committee created pursuant to subsection 1

29-7 shall:

29-8 (a) Examine the methods of design-build contracting that are authorized

29-9 to be used pursuant to the provisions of this act; and

29-10 (b) Submit a report regarding its findings to the 72nd session of the

29-11 Nevada Legislature, accompanied by any suggestions for legislation that

29-12 the interim advisory committee determines to be advisable.

29-13 Sec. 38. 1. This section becomes effective on October 1, 1999.

29-14 2. Sections 1 to 10, inclusive, 13 and 14 to 37, inclusive, of this act

29-15 become effective on October 1, 1999, and expire by limitation on October

29-16 1, 2003.

29-17 3. Section 11 of this act becomes effective on October 1, 1999, and

29-18 expires by limitation on May 1, 2013.

29-19 4. Section 13.5 of this act becomes effective at 12:01 a.m. on October

29-20 1, 2003.

29-21 5. Section 12 of this act becomes effective at 12:01 a.m. on May 1,

29-22 2013.

 

29-23 TEXT OF REPEALED SECTION

 

29-24 341.171 Single contract for design and construction of capital

29-25 improvement: Legislative approval; regulations.

29-26 1. The board may, with the approval of the interim finance committee

29-27 when the legislature is not in regular or special session, or with the

29-28 approval of the legislature by concurrent resolution when the legislature is

29-29 in regular or special session, let to a contractor licensed under chapter 624

29-30 of NRS a single contract for both the design and construction of a project

29-31 of capital improvement. The board shall for the purpose prepare a

29-32 comprehensive sketch plan and narrative of the scope of the work involved

29-33 in a project.

29-34 2. The board shall adopt regulations establishing procedures for:

29-35 (a) The determination of the qualifications of contractors to bid for

29-36 contracts for the design and construction of such projects. The board shall

29-37 consult with the American Institute of Architects and the Associated

29-38 General Contractors, or the successor of either if the named organization

29-39 ceases to exist, before adopting procedures under this paragraph.

30-1 (b) The board’s approval of designs and architects employed in a

30-2 project.

30-3 (c) The bidding and awarding of contracts for the design and

30-4 construction of projects based on a final cost of the project which the

30-5 contractor guarantees will not be exceeded.

30-6 (d) The scheduling and controlling of projects.

~