Assembly Bill No. 133–Assemblyman Dini

 

February 14, 2001

____________

 

Referred to Committee on Judiciary

 

SUMMARY—Revises various provisions regarding claims against contractors for constructional defects and against design professionals for professional negligence. (BDR 3‑667)

 

FISCAL NOTE:            Effect on Local Government: No.

                                    Effect on the State: No.

 

~

 

EXPLANATION – Matter in bolded italics is new; matter between brackets [omitted material] is material to be omitted.

Green numbers along left margin indicate location on the printed bill (e.g., 5-15 indicates page 5, line 15).

 

AN ACT relating to real property; creating a rebuttable presumption concerning construction performed in substantial compliance with applicable building codes; requiring a claimant to provide notice of a claim to parties with an interest of record in certain real property; authorizing a contractor or subcontractor to repair certain constructional defects in complex matters; requiring an affidavit in support of an action for professional negligence against a design professional; revising various provisions governing claims against a contractor for constructional defects; and providing other matters properly relating thereto.

 

THE PEOPLE OF THE STATE OF NEVADA, REPRESENTED IN

SENATE AND ASSEMBLY, DO ENACT AS FOLLOWS:

 

1-1    Section 1.  Chapter 40 of NRS is hereby amended by adding thereto

1-2  the provisions set forth as sections 2 to 7, inclusive, of this act.

1-3    Sec. 2.  “Building code” means ordinances, plans, regulations or

1-4  rulings adopted by a governmental body to regulate and specify the

1-5  soundness of construction of structures.

1-6    Sec. 3.  1.  Approval of the design, construction, alteration, repair

1-7  or improvement of a residence or appurtenance by a building inspector

1-8  employed by a governmental body with jurisdiction creates a rebuttable

1-9  presumption that the residence or appurtenance was designed,

1-10  constructed, altered, repaired or improved in compliance with the

1-11  applicable building code in effect at the time the building permit for the

1-12  design, construction, alteration, repair or improvement of the residence

1-13  or appurtenance was issued.

1-14    2.  The provisions of this section do not preclude a claimant from

1-15  bringing a claim or action based on a claim governed by NRS 40.600 to

1-16  40.695, inclusive, and sections 2 to 7, inclusive, of this act when:


2-1    (a) A contractor has failed to comply with the requirements of a

2-2  building code relating to fire safety; or

2-3    (b) A building inspector employed by a governmental body with

2-4  jurisdiction certifies that there is an imminent threat to the health and

2-5  safety of the inhabitants of a residence.

2-6    Sec. 4.  1.  A claimant who provides written notice of defects to a

2-7  contractor pursuant to NRS 40.645, other than for a defect described in

2-8  NRS 40.670, shall, at the time that the notice is given, forward a copy of

2-9  the notice by certified mail, return receipt requested, to each person who

2-10  has an interest of record in the residence or appurtenance that is the

2-11  subject of the notice.

2-12    2.  A claimant who commences an action against a contractor

2-13  pursuant to NRS 40.682 shall, at the time that he serves the complaint

2-14  and written notice of defects upon the contractor, forward a copy of the

2-15  complaint and notice by certified mail, return receipt requested, to each

2-16  person with an interest of record in the residence or appurtenance that is

2-17  the subject of the complaint and notice.

2-18    3.  A claimant shall, at the time of providing the written notice of

2-19  defects pursuant to NRS 40.645 or at the time of serving the complaint

2-20  and the written notice of defects pursuant to NRS 40.682, file a notice of

2-21  the pendency of the action in the manner provided in NRS 14.010.

2-22    4.  Before a claimant may use any amount of money received from a

2-23  final judgment, order, settlement, award, compromise or otherwise, in an

2-24  action brought pursuant to NRS 40.600 to 40.695, inclusive, and sections

2-25  2 to 7, inclusive, of this act, the claimant shall provide written notice to

2-26  each person who has an interest of record in the residence or

2-27  appurtenance that was the subject of the claim. The notice must include

2-28  any amount of damages received in a final judgment, order, settlement,

2-29  award, compromise or otherwise, and the proposed distribution of the

2-30  amount received.

2-31    5.  If, after agreeing to make repairs or cause the repairs to be made

2-32  pursuant to this section, a contractor fails to complete the repairs

2-33  specified in the agreement in a good and workmanlike manner or in

2-34  substantial compliance with applicable building codes, the claimant may

2-35  commence an action against the contractor for damages arising from a

2-36  constructional defect without satisfying any other requirement of NRS

2-37  40.600 to 40.695, inclusive, and sections 2 to 7, inclusive, of this act.

2-38    Sec. 5.  1.  If an action is commenced in a complex matter, the

2-39  contractor may respond to a notice provided to him by the claimant

2-40  pursuant to paragraph (b) of subsection 1 of NRS 40.682. The response

2-41  may include:

2-42    (a) If the contractor or his subcontractor is licensed to make the

2-43  repairs, an agreement by the contractor or subcontractor to make the

2-44  repairs.

2-45    (b) An agreement by the contractor to cause the repairs to be made, at

2-46  the contractor’s expense, by another contractor who is licensed to make

2-47  the repairs, bonded and insured.

2-48    2.  If a contractor provides the claimant with a response pursuant to

2-49  paragraph (a) or (b) of subsection 1, the claimant shall, upon reasonable


3-1  notice from the contractor, allow the contractor reasonable access to the

3-2  residence or appurtenance to make repairs or cause the repairs to be

3-3  made. The contractor shall:

3-4    (a) Complete such repairs within 90 days after the date the response is

3-5  served to the claimant, subject to reasonable extensions agreed upon in

3-6  writing by the claimant and the contractor if completion is delayed by the

3-7  claimant or by other events beyond the control of the contractor or

3-8  subcontractor, or timely completion of repairs is not reasonably possible;

3-9    (b) Warrant to the claimant that the repairs will be completed in a

3-10  good and workmanlike manner; and

3-11    (c) Complete the repairs in substantial compliance with applicable

3-12  building codes.

3-13    3.  If a claimant prevents a contractor or subcontractor from making

3-14  repairs pursuant to this section, the claimant may not recover damages:

3-15    (a) Associated with the defect that the contractor or subcontractor was

3-16  prevented from repairing; or

3-17    (b) For damage to other parts of the residence or appurtenance that is

3-18  the proximate result of the refusal of the claimant to allow a contractor

3-19  or subcontractor to make repairs pursuant to this section.

3-20    Sec. 6.  1.  Except as otherwise provided in subsection 2, in an

3-21  action for the professional negligence of a design professional or of a

3-22  partnership, corporation, limited-liability company or other form of

3-23  business organization or association that employed a design professional

3-24  at the times relevant to the action, including, without limitation, an

3-25  action filed pursuant to NRS 40.600 to 40.695, inclusive, and sections 2

3-26  to 7, inclusive, of this act, concurrently with the service of the first

3-27  pleading in an action, the attorney for the complainant shall:

3-28    (a) File an affidavit with the court stating that the attorney:

3-29      (1) Has reviewed the facts of the case;

3-30      (2) Has consulted with a design professional who practices in this

3-31  state or who teaches at an accredited college or university in this state in

3-32  a discipline relevant to the action and naming the design professional

3-33  consulted;

3-34      (3) Reasonably believes the design professional who was consulted

3-35  is knowledgeable in the relevant discipline involved in the action; and

3-36      (4) Has concluded on the basis of his review and the consultation

3-37  with the design professional that the action has a reasonable basis in law

3-38  and fact; or

3-39    (b) File an affidavit with the court stating that:

3-40      (1) The attorney has consulted with at least five design

3-41  professionals who practice in this state in a discipline relevant to the

3-42  action and naming the design professionals consulted; and

3-43      (2) None of those design professionals will certify that there is a

3-44  reasonable basis for commencing the action.

3-45    2.  The attorney for the complainant may file the affidavit required

3-46  pursuant to subsection 1 at a later time if he could not consult with a

3-47  design professional and prepare the affidavit before filing the action

3-48  without causing the action to be impaired or barred by the statute of

3-49  limitations or repose. If the attorney must submit the affidavit late, he


4-1  shall file an affidavit concurrently with the service of the first pleading in

4-2  the action stating his reason for failing to comply with subsection 1 and

4-3  the attorney shall consult with a design professional and file the affidavit

4-4  required pursuant to subsection 1 not later than 45 days after filing the

4-5  action.

4-6    3.  In addition to the statement included in the affidavit pursuant to

4-7  paragraph (a) of subsection 1, a report must be attached to the affidavit.

4-8  The report must be prepared by the design professional consulted by the

4-9  attorney and include, without limitation:

4-10    (a) The resumé of the design professional;

4-11    (b) A statement that the design professional is licensed or registered in

4-12  this state and is experienced in each discipline which is the subject of the

4-13  report;

4-14    (c) A copy of each nonprivileged document reviewed by the design

4-15  professional in preparing his report, including, without limitation, each

4-16  record, report and related document that the design professional has

4-17  determined is relevant to the allegations of negligent conduct that are the

4-18  basis for the action;

4-19    (d) The conclusions of the design professional and the basis for the

4-20  conclusions; and

4-21    (e) A statement that the design professional has concluded that there

4-22  is a reasonable basis for filing the action.

4-23    4.  A complainant whose attorney files an affidavit pursuant to

4-24  paragraph (b) of subsection 1 who does not prevail in the action is liable

4-25  for the reasonable attorney’s fees and costs of the design professional or

4-26  the partnership, corporation, limited-liability company or other form of

4-27  business organization or association that employed the design

4-28  professional against whom the action was brought from the time of the

4-29  filing of the statement.

4-30    5.  A design professional consulted by an attorney to prepare an

4-31  affidavit pursuant to this section must not be a party to the action.

4-32    6.  As used in this section, “design professional” means a person who

4-33  holds a professional license or certificate issued pursuant to chapter 623,

4-34  623A or 625 of NRS.

4-35    Sec. 7.  1.  The court shall dismiss an action for the professional

4-36  negligence of a design professional or of a partnership, corporation,

4-37  limited-liability company or other form of business organization or

4-38  association that employed a design professional at the times relevant to

4-39  the action if the attorney for a complainant fails to:

4-40    (a) File an affidavit required pursuant to section 6 of this act;

4-41    (b) File a report required pursuant to subsection 3 of section 6 of this

4-42  act; or

4-43    (c) Name the design professional consulted in the affidavit required

4-44  pursuant to subsection 1 of section 6 of this act.

4-45    2.  The fact that an attorney for a complainant has complied or failed

4-46  to comply with the provisions of section 6 of this act is admissible in the

4-47  action.

 

 


5-1    Sec. 8.  NRS 40.600 is hereby amended to read as follows:

5-2    40.600  As used in NRS 40.600 to 40.695, inclusive, and sections 2 to

5-3  7, inclusive, of this act, unless the context otherwise requires, the words

5-4  and terms defined in NRS 40.605 to 40.630, inclusive, and section 2 of

5-5  this act have the meanings ascribed to them in those sections.

5-6    Sec. 9.  NRS 40.615 is hereby amended to read as follows:

5-7    40.615  [“Constructional]

5-8    1.  Except as otherwise provided in subsection 2, “constructional

5-9  defect” includes , without limitation, a defect in the design, construction,

5-10  manufacture, repair or landscaping of a new residence, of an alteration of

5-11  or addition to an existing residence, or of an appurtenance. The term

5-12  includes physical damage to the residence, an appurtenance or the real

5-13  property to which the residence or appurtenance is affixed that is

5-14  proximately caused by a constructional defect.

5-15    2.  The term does not include the design, construction, manufacture,

5-16  repair or landscaping of a new residence, of an alteration of or addition

5-17  to an existing residence, or of an appurtenance that:

5-18    (a) Substantially complied with the applicable building code in effect

5-19  at the time the building permit was issued for the design, construction,

5-20  manufacture, repair or landscaping of a new residence, of an alteration

5-21  of or addition to an existing residence, or of an appurtenance; or

5-22    (b) Has not caused:

5-23      (1) Damage to the residence or appurtenance; or

5-24      (2) Injury to an inhabitant of the residence.

5-25    Sec. 10.  NRS 40.645 is hereby amended to read as follows:

5-26    40.645  Except as otherwise provided in this section and NRS 40.670:

5-27    1.  For a claim that is not a complex matter, at least 60 days before a

5-28  claimant commences an action against a contractor for damages arising

5-29  from a constructional defect, the claimant must give written notice by

5-30  certified mail, return receipt requested, to the contractor, at the contractor’s

5-31  last known address, specifying in reasonable detail the defects or any

5-32  damages or injuries to each residence or appurtenance that is the subject of

5-33  the claim. The notice must describe in reasonable detail the cause of the

5-34  defects if the cause is known, the nature and extent that is known of the

5-35  damage or injury resulting from the defects and the location of each defect

5-36  within each residence or appurtenance to the extent known. An expert

5-37  opinion concerning the cause of the defects and the nature and extent of the

5-38  damage or injury resulting from the defects based on a representative

5-39  sample of the components of the residences and appurtenances involved in

5-40  the action satisfies the requirements of this section. During the 45-day

5-41  period after the contractor receives the notice, on his written request, the

5-42  contractor is entitled to inspect the property that is the subject of the claim

5-43  to determine the nature and cause of the defect, damage or injury and the

5-44  nature and extent of repairs necessary to remedy the defect. The contractor

5-45  shall, before making the inspection, provide reasonable notice of the

5-46  inspection and shall make the inspection at a reasonable time. The

5-47  contractor may take reasonable steps to establish the existence of the

5-48  defect.


6-1    2.  If a residence or appurtenance that is the subject of the claim is

6-2  covered by a homeowner’s warranty that is purchased by or on behalf of a

6-3  claimant pursuant to NRS 690B.100 to 690B.180, inclusive, a claimant

6-4  shall diligently pursue a claim under the contract.

6-5    3.  Within 60 days after the contractor receives the notice, the

6-6  contractor shall make a written response to the claimant. The response:

6-7    (a) Must be served to the claimant by certified mail, return receipt

6-8  requested, at the claimant’s last known address.

6-9    (b) Must respond to each constructional defect set forth in the

6-10  claimant’s notice, and describe in reasonable detail the cause of the defect,

6-11  if known, the nature and extent of the damage or injury resulting from the

6-12  defect, and, unless the response is limited to a proposal for monetary

6-13  compensation, the method, adequacy and estimated cost of any proposed

6-14  repair.

6-15    (c) May include:

6-16      (1) A proposal for monetary compensation, which may include a

6-17  contribution from a subcontractor.

6-18      (2) If the contractor or his subcontractor is licensed to make the

6-19  repairs, an agreement by the contractor or subcontractor to make the

6-20  repairs.

6-21       (3) An agreement by the contractor to cause the repairs to be made, at

6-22  the contractor’s expense, by another contractor who is licensed to make the

6-23  repairs, bonded and insured.

6-24  [The repairs must be made within 45 days after the contractor receives

6-25  written notice of acceptance of the response, unless completion is delayed

6-26  by the claimant or by other events beyond the control of the contractor, or

6-27  timely completion of the repairs is not reasonably possible. The claimant

6-28  and the contractor may agree in writing to extend the periods prescribed by

6-29  this section.]

6-30    4.  If a contractor provides the claimant with a written response

6-31  pursuant to subparagraph (2) or (3) of paragraph (c) of subsection 3, the

6-32  claimant shall, upon reasonable notice from the contractor, allow the

6-33  contractor reasonable access to the residence or appurtenance to make

6-34  repairs or cause the repairs to be made. The contractor shall:

6-35    (a) Complete such repairs within 90 days after the date the response is

6-36  served to the claimant, subject to reasonable extensions agreed upon in

6-37  writing by the claimant and the contractor if completion is delayed by the

6-38  claimant or by other events beyond the control of the contractor or

6-39  subcontractor, or timely completion of repairs is not reasonably possible;

6-40    (b) Warrant to the claimant that the repairs will be completed in a

6-41  good and workmanlike manner; and

6-42    (c) Complete the repairs in substantial compliance with applicable

6-43  building codes.

6-44    5.  Not later than 15 days before the mediation required pursuant to

6-45  NRS 40.680 and upon providing 15 days’ notice, each party shall provide

6-46  the other party, or shall make a reasonable effort to assist the other party to

6-47  obtain, all relevant reports, photos, correspondence, plans, specifications,

6-48  warranties, contracts, subcontracts, work orders for repair, videotapes,


7-1  technical reports, soil and other engineering reports and other documents or

7-2  materials relating to the claim that are not privileged.

7-3    [5.] 6.  If the claimant is a representative of a homeowner’s association,

7-4  the association shall submit any response made by the contractor to each

7-5  member of the association.

7-6    [6.] 7.  If a claimant prevents a contractor or subcontractor from

7-7  making repairs pursuant to this section, the claimant may not recover

7-8  damages:

7-9    (a) Associated with the defect that the contractor or subcontractor was

7-10  prevented from repairing; or

7-11    (b) For damage to other parts of the residence or appurtenance that is

7-12  the proximate result of the refusal of the claimant to allow a contractor

7-13  or subcontractor to make repairs pursuant to this section.

7-14    8.  If, after agreeing to make or cause to be made repairs pursuant to

7-15  this section, a contractor fails to complete the repairs specified in the

7-16  agreement in a good and workmanlike manner or in substantial

7-17  compliance with applicable building codes, the claimant may commence

7-18  an action against the contractor for damages arising from a

7-19  constructional defect without satisfying any other requirement of NRS

7-20  40.600 to 40.695, inclusive, and sections 2 to 7, inclusive, of this act.

7-21    9.  As used in this section, “subcontractor” means a contractor who

7-22  performs work on behalf of another contractor in the construction of a

7-23  residence or appurtenance.

7-24    Sec. 11.  NRS 40.650 is hereby amended to read as follows:

7-25    40.650  1.  [If a claimant unreasonably rejects a reasonable written

7-26  offer of settlement made as part of a response made pursuant to NRS

7-27  40.645 or 40.682 or does not permit the contractor or independent

7-28  contractor a reasonable opportunity to repair the defect pursuant to an

7-29  accepted offer of settlement and thereafter commences an action governed

7-30  by NRS 40.600 to 40.695, inclusive, the court in which the action is

7-31  commenced may:

7-32    (a) Deny the claimant’s attorney’s fees and costs; and

7-33    (b) Award attorney’s fees and costs to the contractor.

7-34  Any sums paid under a homeowner’s warranty, other than sums paid in

7-35  satisfaction of claims that are collateral to any coverage issued to or by the

7-36  contractor, must be deducted from any recovery.

7-37    2.  If a contractor fails to:

7-38    (a) Make an offer of settlement;

7-39    (b) Make a good faith response to the claim asserting no liability;

7-40    (c) Complete, in a good and workmanlike manner, the repairs specified

7-41  in an accepted offer;

7-42    (d) Agree to a mediator or accept the appointment of a mediator

7-43  pursuant to NRS 40.680 or subsection 4 of NRS 40.682; or

7-44    (e) Participate in mediation,

7-45  the limitations on damages and defenses to liability provided in NRS

7-46  40.600 to 40.695, inclusive, do not apply and the claimant may commence

7-47  an action without satisfying any other requirement of NRS 40.600 to

7-48  40.695, inclusive.] Unless mediation is waived in writing by the

7-49  contractor and the claimant pursuant to NRS 40.680 or subsection 4 of


8-1  NRS 40.682, the claimant shall provide the contractor a written demand

8-2  for settlement of all claims against the contractor set forth in the written

8-3  notice of defects given or served pursuant to NRS 40.645 or 40.682 not

8-4  later than 45 days before the date set for the first session of the mediation

8-5  required pursuant to NRS 40.680. The written demand for settlement

8-6  must:

8-7    (a) Include, without limitation, the cost to repair each constructional

8-8  defect alleged in the written notice of defects; and

8-9    (b) Contain sufficient detail to allow the contractor to independently

8-10  evaluate the cost to repair each constructional defect alleged in the

8-11  written notice of defects.

8-12    2.  The contractor shall respond to the written demand for settlement

8-13  not later than 10 days before the date set for the first session of the

8-14  mediation. The response of the contractor must:

8-15    (a) Address the cost to repair each constructional defect contained in

8-16  the written demand for settlement of the claimant; and

8-17    (b) Contain sufficient detail to allow the claimant to evaluate the

8-18  response.

8-19    3.  If the parties do not reach an agreement concerning the matter

8-20  during the mediation and the claimant fails to recover an amount equal

8-21  to or greater than the amount of the written demand for settlement made

8-22  pursuant to this section, then the claimant is not entitled to recover from

8-23  the contractor:

8-24    (a) Attorney’s fees and costs of the claimant incurred after the

8-25  conclusion of mediation;

8-26    (b) Any prejudgment interest provided by statute; or

8-27    (c) Expert fees and costs incurred after the conclusion of mediation.

8-28    4.  If the parties do not reach an agreement concerning the matter

8-29  during mediation and the claimant recovers an amount greater than the

8-30  amount of the written demand for settlement made pursuant to this

8-31  section, then, in addition to the damages recoverable pursuant to NRS

8-32  40.655, the claimant is entitled to recover from the contractor, as

8-33  additional damages, an amount equal to the attorney’s fees awarded

8-34  pursuant to NRS 40.655.

8-35    [3.] 5.  If coverage under a homeowner’s warranty is denied by an

8-36  insurer in bad faith, the homeowner and the contractor have a right of

8-37  action for the sums that would have been paid if coverage had been

8-38  provided, plus reasonable attorney’s fees and costs.

8-39    Sec. 12.  NRS 40.655 is hereby amended to read as follows:

8-40    40.655  1.  Except as otherwise provided in NRS 40.650, in a claim

8-41  governed by NRS 40.600 to 40.695, inclusive, and sections 2 to 7,

8-42  inclusive, of this act, the claimant may recover only the following damages

8-43  to the extent proximately caused by a constructional defect:

8-44    (a) Any reasonable attorney’s fees;

8-45    (b) The reasonable cost of any repairs already made that were necessary

8-46  and of any repairs yet to be made that are necessary to cure any

8-47  constructional defect that the contractor failed to cure and the reasonable

8-48  expenses of temporary housing reasonably necessary during the repair [;


9-1    (c) The] or the reduction in market value of the residence or accessory

9-2  structure, if any, to the extent the reduction is because of structural failure

9-3  [;

9-4    (d) The loss of the use of all or any part of the residence;

9-5    (e)] , whichever is less;

9-6    (c) The reasonable value of any other property damaged by the

9-7  constructional defect;

9-8    [(f)] (d) Any additional costs reasonably incurred by the claimant,

9-9  including, but not limited to, any costs and fees incurred for the retention

9-10  of experts to:

9-11      (1) Ascertain the nature and extent of the constructional defects;

9-12      (2) Evaluate appropriate corrective measures to estimate the value of

9-13  loss of use; and

9-14      (3) Estimate the value of loss of use, the cost of temporary housing

9-15  and the reduction of market value of the residence; and

9-16    [(g)] (e) Any interest provided by statute.

9-17    2.  The amount of any attorney’s fees awarded pursuant to this section

9-18  must be approved by the court.

9-19    3.  If a contractor complies with the provisions of NRS 40.600 to

9-20  40.695, inclusive, and sections 2 to 7, inclusive, of this act, the claimant

9-21  may not recover from the contractor, as a result of the constructional

9-22  defect, anything other than that which is provided pursuant to NRS 40.600

9-23  to 40.695, inclusive [.] , and sections 2 to 7, inclusive, of this act.

9-24    4.  As used in this section, “structural failure” means physical damage

9-25  to the load-bearing portion of a residence or appurtenance caused by a

9-26  failure of the load-bearing portion of the residence or appurtenance.

9-27    Sec. 13.  NRS 40.665 is hereby amended to read as follows:

9-28    40.665  In addition to any other method provided for settling a claim

9-29  pursuant to NRS 40.600 to 40.695, inclusive, and sections 2 to 7,

9-30  inclusive, of this act, a contractor may, pursuant to a written agreement

9-31  entered into with a claimant, settle a claim by repurchasing the claimant’s

9-32  residence and the real property upon which it is located. The agreement

9-33  may include provisions which reimburse the claimant for:

9-34    1.  The market value of the residence as if no constructional defect

9-35  existed, except that if a residence is less than 2 years of age and was

9-36  purchased from the contractor against whom the claim is brought, the

9-37  market value is the price at which the residence was sold to the claimant;

9-38    2.  The value of any improvements made to the property by a person

9-39  other than the contractor;

9-40    3.  Reasonable attorney’s fees and fees for experts; and

9-41    4.  Any costs, including costs and expenses for moving and costs,

9-42  points and fees for loans.

9-43  [Any offer of settlement made that includes the items listed in this section

9-44  shall be deemed reasonable for the purposes of subsection 1 of NRS

9-45  40.650.]

9-46    Sec. 14.  NRS 40.670 is hereby amended to read as follows:

9-47    40.670  1.  [A contractor who receives written notice of] If a claimant

9-48  discovers a constructional defect resulting from work performed by the

9-49  contractor or his agent, employee or subcontractor which creates an


10-1  imminent threat to the health or safety of the inhabitants of the residence

10-2  [shall take reasonable steps to cure the defect as soon as practicable.] , the

10-3  claimant shall provide the contractor against whom the claim is alleged

10-4  with written notice of the alleged constructional defect and a report or

10-5  certification from an engineer or contractor licensed in this state or a

10-6  building inspector employed by a governmental body with jurisdiction

10-7  certifying that the alleged constructional defect presents an imminent

10-8  threat to the health or safety of the inhabitants of the residence.

10-9    2.  If a contractor receives the written notice and report or

10-10  certification as set forth in subsection 1, the contractor shall take

10-11  reasonable steps to cure the defect as soon as practicable. The contractor

10-12  shall not cure the defect by making any repairs for which he is not licensed

10-13  or by causing any repairs to be made by a person who is not licensed to

10-14  make those repairs. If the contractor fails to cure the defect in a reasonable

10-15  time, the owner of the residence may have the defect cured and may

10-16  recover from the contractor the reasonable cost of the repairs plus

10-17  reasonable attorney’s fees and costs in addition to any other damages

10-18  recoverable under any other law.

10-19  [2.  A contractor who does not cure a defect pursuant to this section

10-20  because he has determined, in good faith and after a reasonable inspection,

10-21  that there is not an imminent threat to the health or safety of the inhabitants

10-22  is not liable for attorney’s fees and costs pursuant to this section, except

10-23  that if a building inspector employed by a governmental body with

10-24  jurisdiction certifies that there is an imminent threat to the health and safety

10-25  of the inhabitants of the residence, the contractor is subject to the

10-26  provisions of subsection 1.]

10-27  Sec. 15.  NRS 40.680 is hereby amended to read as follows:

10-28  40.680  1.  Except as otherwise provided in this chapter, before an

10-29  action based on a claim governed by NRS 40.600 to 40.695, inclusive, and

10-30  sections 2 to 7, inclusive, of this act may be commenced in court, the

10-31  matter must be submitted to mediation, unless mediation is waived in

10-32  writing by the contractor and the claimant.

10-33  2.  The claimant and contractor [must] shall select a mediator by

10-34  agreement. If the claimant and contractor fail to agree upon a mediator

10-35  within 45 days after a mediator is first selected by the claimant, either party

10-36  may petition the American Arbitration Association, the Nevada Arbitration

10-37  Association, Nevada Dispute Resolution Services or any other mediation

10-38  service acceptable to the parties for the appointment of a mediator. A

10-39  mediator so appointed may discover only those documents or records

10-40  which are necessary to conduct the mediation. [The] Except as otherwise

10-41  provided in subsection 7, the mediator shall convene the mediation within

10-42  60 days after the matter is submitted to him, unless the parties agree to

10-43  extend the time. Except in a complex matter, the claimant shall, before the

10-44  mediation begins, deposit $50 with the mediation service and the

10-45  contractor shall deposit with the mediation service the remaining amount

10-46  estimated by the mediation service as necessary to pay the fees and

10-47  expenses of the mediator for the first session of mediation, and the

10-48  contractor shall deposit additional amounts demanded by the mediation

10-49  service as incurred for that purpose. In a complex matter, each party shall


11-1  share equally in the deposits estimated by the mediation service. Unless

11-2  otherwise agreed, the total fees for each day of mediation and the mediator

11-3  must not exceed $750 per day.

11-4    3.  If the parties do not reach an agreement concerning the matter

11-5  during mediation or if the contractor fails to pay the required fees and

11-6  appear, the claimant may commence his action in court and:

11-7    (a) The reasonable costs and fees of the mediation are recoverable by

11-8  the prevailing party as costs of the action.

11-9    (b) Either party may petition the court in which the action is

11-10  commenced for the appointment of a special master.

11-11  4.  A special master appointed pursuant to subsection 3 may:

11-12  (a) Review all pleadings, papers or documents filed with the court

11-13  concerning the action.

11-14  (b) Coordinate the discovery of any books, records, papers or other

11-15  documents by the parties, including the disclosure of witnesses and the

11-16  taking of the deposition of any party.

11-17  (c) Order any inspections on the site of the property by a party and any

11-18  consultants or experts of a party.

11-19  (d) Order settlement conferences and attendance at those conferences by

11-20  any representative of the insurer of a party.

11-21  (e) Require any attorney representing a party to provide statements of

11-22  legal and factual issues concerning the action.

11-23  (f) Refer to the judge who appointed him or to the presiding judge of the

11-24  court in which the action is commenced any matter requiring assistance

11-25  from the court.

11-26  The special master shall not, unless otherwise agreed by the parties,

11-27  personally conduct any settlement conferences or engage in any ex parte

11-28  meetings regarding the action.

11-29  5.  Upon application by a party to the court in which the action is

11-30  commenced, any decision or other action taken by a special master

11-31  appointed pursuant to this section may be appealed to the court for a

11-32  decision.

11-33  6.  A report issued by a mediator or special master that indicates that

11-34  either party has failed to appear before him or to mediate in good faith is

11-35  admissible in the action, but a statement or admission made by either party

11-36  in the course of mediation is not admissible.

11-37  7.  An agreement by a contractor pursuant to NRS 40.645 or section 5

11-38  of this act to make repairs or cause the repairs to be made extends the

11-39  time required to convene the first session of mediation by a period of time

11-40  agreed upon in writing by the contractor and claimant for the completion

11-41  of the repairs.

11-42  Sec. 16.  NRS 40.682 is hereby amended to read as follows:

11-43  40.682  Except as otherwise provided in this section and NRS 40.670:

11-44  1.  Notwithstanding the provisions of subsection 1 of NRS 40.680, a

11-45  claimant may commence an action in district court in a complex matter. If

11-46  the claimant commences an action in district court , he shall:

11-47  (a) File and serve the summons and complaint as required by law; and

11-48  (b) At the same time and in the same manner as the claimant serves the

11-49  summons and complaint upon the contractor, serve upon the contractor a


12-1  written notice specifying in reasonable detail, to the extent known, the

12-2  defects and any damages or injuries to each residence or appurtenance that

12-3  is the subject of the claim. The notice must describe in reasonable detail

12-4  each defect, the specific location of each defect, and the nature and extent

12-5  that is known of the damage or injury resulting from each defect. If an

12-6  expert opinion has been rendered concerning the existence or extent of the

12-7  defects, a written copy of the opinion must accompany the notice. An

12-8  expert opinion that specifies each defect to the extent known, the specific

12-9  location of each defect to the extent known, and the nature and extent that

12-10  is known of the damage or injury resulting from each defect, based on a

12-11  valid and reliable representative sample of the residences and

12-12  appurtenances involved in the action, satisfies the requirements of this

12-13  section.

12-14  2.  The contractor shall file and serve an answer to the complaint as

12-15  required by law.

12-16  3.  Not later than 30 days after the date of service of the answer to the

12-17  complaint, the contractor and claimant shall meet to establish a schedule

12-18  for:

12-19  (a) The exchange of or reasonable access for the other party to all

12-20  relevant reports, photos, correspondence, plans, specifications, warranties,

12-21  contracts, subcontracts, work orders for repair, videotapes, technical

12-22  reports, soil and other engineering reports and other documents or

12-23  materials relating to the claim that are not privileged;

12-24  (b) The inspection of the residence or appurtenance that is the subject of

12-25  the claim to evaluate the defects set forth in the notice served pursuant to

12-26  subsection 1; and

12-27  (c) The conduct of any tests that are reasonably necessary to determine

12-28  the nature and cause of a defect or any damage or injury, and the nature

12-29  and extent of repairs necessary to remedy a defect or any damage or injury.

12-30  The party conducting the test shall provide reasonable notice of the test to

12-31  all other parties and conduct the test at a reasonable time.

12-32  4.  At the meeting held pursuant to subsection 3, the claimant and

12-33  contractor shall:

12-34  (a) Establish a schedule for the addition of any additional parties to the

12-35  complaint or to file any third-party complaint against an additional party

12-36  who may be responsible for all or a portion of the defects set forth in the

12-37  notice served pursuant to subsection 1;

12-38  (b) Unless the claimant and contractor agree otherwise in writing, select

12-39  a mediator and proceed with mediation as provided in subsections 2 to [6,]

12-40  7, inclusive, of NRS 40.680; and

12-41  (c) If the claimant and contractor agree, select a special master and

12-42  jointly petition the court for his appointment pursuant to subsection 7.

12-43  5.  Each party added to the complaint or against whom a third-party

12-44  complaint is filed pursuant to subsection 4 shall file and serve an answer as

12-45  required by law.

12-46  6.  If the claimant or contractor adds a party to the complaint or files a

12-47  third-party complaint, then not later than 60 days after the date determined

12-48  pursuant to paragraph (a) of subsection 4, the contractor, claimant and each

12-49  party added to the complaint or against whom a third-party complaint is


13-1  filed shall meet to establish a schedule for the activities set forth in

13-2  paragraphs (a), (b) and (c) of subsection 3.

13-3    7.  If a special master has not been appointed, the contractor, claimant

13-4  or a party added to the complaint or against whom a third-party complaint

13-5  is filed may petition the court for the appointment of a special master at

13-6  any time after the meeting held pursuant to subsection 3. The special

13-7  master may:

13-8    (a) Take any action set forth in subsection 4 of NRS 40.680;

13-9    (b) Exercise any power set forth in Rule 53 of the Nevada Rules of Civil

13-10  Procedure; and

13-11  (c) Subject to the provisions of NRS 40.680, if the parties fail to

13-12  establish a schedule or determine a date as required in subsection 3, 4 or 6,

13-13  establish the schedule or determine the date.

13-14  8.  Unless the mediation required pursuant to paragraph (b) of

13-15  subsection 4 is completed or the contractor and claimant have agreed in

13-16  writing not to mediate the claim pursuant to paragraph (b) of subsection 4,

13-17  a party shall not propound interrogatories or requests for admission, take a

13-18  deposition or file a motion that is dispositive of the action except:

13-19  (a) Upon agreement of the parties; or

13-20  (b) With the prior approval of the court or special master.

13-21  9.  If a residence or appurtenance that is the subject of the claim is

13-22  covered by a homeowner’s warranty that is purchased by or on behalf of a

13-23  claimant pursuant to NRS 690B.100 to 690B.180, inclusive, a claimant

13-24  shall diligently pursue a claim under the contract.

13-25  10.  [Unless] Except as otherwise provided in section 5 of this act or if

13-26  the parties agree otherwise, not less than 60 days before the date of the

13-27  mediation pursuant to paragraph (b) of subsection 4 is convened, the

13-28  contractor shall make a written response to the claimant that meets the

13-29  requirements set forth in subsection 3 of NRS 40.645.

13-30  11.  If the claimant is a representative of a homeowner’s association,

13-31  the association shall submit any response made by the contractor to each

13-32  member of the association in writing not more than 30 days after the date

13-33  the claimant receives the response.

13-34  12.  The claimant shall respond to the written response of the contractor

13-35  within 45 days after the response of the contractor is mailed to the

13-36  claimant.

13-37  Sec. 17.  The amendatory provisions of this act do not apply to a claim

13-38  initiated or an action commenced pursuant to NRS 40.600 to 40.695,

13-39  inclusive, and sections 2 to 7, inclusive, of this act, unless the claim was

13-40  initiated or the action was commenced on or after October 1, 2001.

 

13-41  H