(REPRINTED WITH ADOPTED AMENDMENTS)

                                                                                   THIRD REPRINT                    A.B. 133

 

Assembly Bill No. 133–Assemblyman Dini

 

February 14, 2001

____________

 

Referred to Committee on Judiciary

 

SUMMARY—Makes various changes concerning construction, constructional defects and common-interest communities. (BDR 3‑667)

 

FISCAL NOTE:  Effect on Local Government: No.

                             Effect on the State: No.

 

~

 

EXPLANATION – Matter in bolded italics is new; matter between brackets [omitted material] is material to be omitted.

Green numbers along left margin indicate location on the printed bill (e.g., 5-15 indicates page 5, line 15).

 

AN ACT relating to real property; requiring a claimant to provide notice concerning constructional defects to a contractor and allow the contractor to make repairs before commencing an action against the contractor; requiring a contractor to provide notice concerning constructional defects to a subcontractor, supplier or design professional and allow the subcontractor, supplier or design professional to make repairs before commencing an action against the subcontractor, supplier or design professional; requiring an affidavit in support of an action for professional negligence against a design professional; imposing certain restrictions to prevent property managers from being encouraged to file a claim for a constructional defect; requiring a contractor to provide certain information to the initial purchaser of a residence; revising the provisions governing commencement of certain civil actions by the association of a common-interest community; requiring the governing body of each city and county to require a geotechnical report as a condition to obtaining a building permit and additional information concerning a completed project; and providing other matters properly relating thereto.

 

THE PEOPLE OF THE STATE OF NEVADA, REPRESENTED IN

SENATE AND ASSEMBLY, DO ENACT AS FOLLOWS:

 

1-1    Section 1. Chapter 40 of NRS is hereby amended by adding thereto

1-2  the provisions set forth as sections 2 to 11, inclusive, of this act.

1-3    Sec. 2.  “Design professional” means a person who holds a

1-4  professional license or certificate issued pursuant to chapter 623, 623A

1-5  or 625 of NRS.

1-6    Sec. 3.  “Subcontractor” means a contractor who performs work on

1-7  behalf of another contractor in the construction of a residence or

1-8  appurtenance.

1-9    Sec. 4.  “Supplier” means a person who provides materials,

1-10  equipment or other supplies for the construction of a residence or

1-11  appurtenance.


2-1    Sec. 5.  Except as otherwise provided in NRS 40.670 and subsection

2-2  1 of section 9 of this act:

2-3    1.  Before a claimant may commence an action against a contractor

2-4  for damages arising from a constructional defect, the claimant must give

2-5  written notice by certified mail, return receipt requested, to the

2-6  contractor, at the contractor’s last address listed in the records of the

2-7  state contractors’ board, or at the contractor’s last known address if his

2-8  address is not listed in the records of the state contractors’ board,

2-9  specifying in reasonable detail the defects or any damages or injuries to

2-10  each residence or appurtenance that is the subject of the claim. The

2-11  notice must describe in reasonable detail the cause of the defects if the

2-12  cause is known, the nature and extent that is known of the damage or

2-13  injury resulting from the defects and the location of each defect within

2-14  each residence or appurtenance to the extent known.

2-15    2.  Within 15 days after receiving a notice pursuant to subsection 1, a

2-16  contractor shall forward a copy of the notice by certified mail, return

2-17  receipt requested, to each subcontractor, supplier and design

2-18  professional who the contractor reasonably believes is responsible for a

2-19  defect specified in the notice and include with the copy of the notice the

2-20  specific defect for which the contractor believes the subcontractor,

2-21  supplier or design professional is responsible.

2-22    3.  The claimant shall, upon reasonable notice, allow the contractor

2-23  and a subcontractor, supplier or design professional who received the

2-24  notice pursuant to subsection 2 to access the residence or appurtenance

2-25  that is the subject of the notice to determine the nature and extent of a

2-26  defect and the nature and extent of repairs necessary to remedy the

2-27  defect.

2-28    4.  Within 15 days after a subcontractor, supplier or design

2-29  professional receives a copy of a notice pursuant to subsection 2, he shall

2-30  provide the contractor with a statement indicating:

2-31    (a) Whether the subcontractor, supplier or design professional will

2-32  repair the defect for which the contractor believes the subcontractor,

2-33  supplier or design professional is responsible; and

2-34    (b) If the subcontractor, supplier or design professional decides to

2-35  repair the defect, an estimate of the length of time required for the repair,

2-36  and at least two proposed dates on and times at which the subcontractor,

2-37  supplier or design professional can begin making the repair.

2-38  5.  An alleged constructional defect which is discovered after an

2-39  action pursuant to NRS 40.600 to 40.695, inclusive, and sections 2 to 11,

2-40  inclusive, of this act, has been commenced may not be alleged in an

2-41  amended pleading until the contractor, subcontractor, supplier or design

2-42  professional who performed the original construction which is alleged to

2-43  be a constructional defect has been given:

2-44  (a) Written notice in the manner required by this section; and

2-45  (b) A reasonable opportunity to repair the alleged constructional

2-46  defect in the manner provided in section 6 of this act.

2-47  6.  A court shall dismiss an action commenced against a contractor,

2-48  subcontractor, supplier or design professional by a claimant who has

2-49  failed to comply with the requirements of this section.


3-1    Sec. 6.  Except as otherwise provided in NRS 40.670:

3-2    1.  Except as otherwise provided in NRS 40.672, a contractor who

3-3  receives notice of a constructional defect pursuant to subsection 1 of

3-4  section 5 of this act may make the repairs necessary to remedy the defects

3-5  and repair any damage or injury to the residence or appurtenance

3-6  described in the notice or arrange to have such repairs made by a

3-7  subcontractor, supplier or design professional to whom the contractor

3-8  forwarded notice of the defect pursuant to subsection 2 of section 5 of

3-9  this act. The contractor shall ensure that any such repairs are completed

3-10  within a reasonable time, but in any event:

3-11    (a) If the constructional defect is not part of a complex matter, not

3-12  later than 45 days after receiving the notice; or

3-13    (b) If the constructional defect is part of a complex matter, not later

3-14  than 90 days after receiving the notice,

3-15  unless the claimant and the contractor negotiate in good faith and agree

3-16  in writing to extend reasonably the time for completing the repairs in

3-17  which case the repairs must be completed not later than the time set forth

3-18  in the agreement.

3-19    2.  In making repairs pursuant to subsection 1, the contractor or a

3-20  subcontractor, supplier or design professional who is responsible for

3-21  making the repairs shall:

3-22    (a) Make the repairs at reasonable times that are agreed to in advance

3-23  by the claimant, or by the owner of the residence or appurtenance if the

3-24  claimant is a representative of a homeowner’s association;

3-25    (b) Ensure that all of the work to make the repairs is completed by

3-26  contractors and subcontractors who are properly licensed, bonded and

3-27  insured;

3-28    (c) Take any action necessary to prevent a mechanic’s lien from being

3-29  obtained on the property of the claimant on which the repairs are being

3-30  made, to remove such a mechanic’s lien if one is obtained, and to

3-31  indemnify the claimant against any expenses incurred by the claimant

3-32  concerning such a mechanic’s lien; and

3-33    (d) Provide to the claimant a written report of each repair made, the

3-34  method used to make the repair and the parts replaced in making such

3-35  repairs within 10 days after the repairs are made.

3-36    3.  The claimant shall allow the contractor and a subcontractor,

3-37  supplier or design professional who is responsible for making repairs

3-38  pursuant to subsection 1 a reasonable opportunity to make repairs

3-39  pursuant to subsection 1. A court shall dismiss an action commenced

3-40  against a contractor, subcontractor, supplier or design professional by a

3-41  claimant who has failed to comply with the requirements of this

3-42  subsection.

3-43    4.  If the claimant is not satisfied with the repairs made pursuant to

3-44  subsection 1 or NRS 40.672 or the contractor does not make the repairs

3-45  or have the repairs made within the time set forth in subsection 1 or

3-46  within the time agreed to in writing by the claimant and the contractor,

3-47  the claimant may commence an action governed by NRS 40.600 to

3-48  40.695, inclusive, and sections 2 to 11, inclusive, of this act against the

3-49  contractor for a constructional defect or any damages or injuries that


4-1  were specified in the notice provided to the contractor pursuant to section

4-2  5 of this act. A claimant who is not satisfied with the repairs is required

4-3  to give additional notice pursuant to NRS 40.645 or 40.682 before

4-4  commencing such an action.

4-5    Sec. 7.  1.  Except as otherwise provided in subsection 3, a

4-6  contractor who does not provide a subcontractor, supplier or design

4-7  professional with notice of a constructional defect pursuant to subsection

4-8  2 of section 5 of this act who the contractor reasonably believes is

4-9  responsible for a defect specified in the notice provided to the contractor

4-10  pursuant to subsection 1 of section 5 of this act, may not recover

4-11  attorney’s fees, costs, fees for expert witnesses or fees for consultants

4-12  from the subcontractor, supplier or design professional that are incurred

4-13  by the contractor in defending an action against the contractor for the

4-14  constructional defect pursuant to NRS 40.600 to 40.695, inclusive, and

4-15  sections 2 to 11, inclusive, of this act.

4-16    2.  Except as otherwise provided in subsection 3, after a claimant files

4-17  a claim against a contractor that is governed by NRS 40.600 to 40.695,

4-18  inclusive, and sections 2 to 11, inclusive, of this act, a subcontractor,

4-19  supplier or design professional who is responsible for a constructional

4-20  defect involved in the claim and who did not receive notice of the defect

4-21  pursuant to subsection 2 of section 5 of this act or who received notice

4-22  pursuant to subsection 4 may present directly to the claimant an offer to

4-23  repair the defect. If the claimant accepts the offer, the subcontractor,

4-24  supplier or design professional repairs the defect to the satisfaction of the

4-25  claimant and the claimant provides a statement in writing to the

4-26  subcontractor, supplier or design professional indicating that the defect

4-27  was repaired to his satisfaction, the contractor against whom the claim

4-28  was filed may not pursue any claim related to the defect that was repaired

4-29  against the subcontractor, supplier or design professional who repaired

4-30  the defect.

4-31    3.  Except as otherwise provided in subsection 4, the provisions of this

4-32  section do not apply to a contractor who did not give notice of the

4-33  constructional defect to the subcontractor, supplier or design

4-34  professional if the contractor could not, after a good faith effort, identify

4-35  the subcontractor, supplier or design professional who may have been

4-36  responsible for the defect within the time set forth for providing a notice

4-37  to the subcontractor, supplier or design professional.

4-38  4.  If, after the expiration of the time set forth for a contractor to

4-39  provide a notice to a subcontractor, supplier or design professional

4-40  pursuant to section 5 of this act, a contractor identifies a subcontractor,

4-41  supplier or design professional who the contractor was not, after a good

4-42  faith effort, previously able to identify and who may be responsible for a

4-43  constructional defect alleged by the claimant, the contractor shall, before

4-44  commencing an action against such a subcontractor, supplier or design

4-45  professional:

4-46  (a) Provide notice to the subcontractor, supplier or design

4-47  professional in the manner provided in subsection 2 of section 5 of this

4-48  act; and


5-1    (b) Allow a reasonable opportunity for the subcontractor, supplier or

5-2  design professional to make repairs to the alleged constructional defect.

5-3    5.  Subject to the provisions of subsection 2, the claimant shall allow

5-4  a subcontractor, supplier or design professional notified pursuant to

5-5  subsection 4 a reasonable opportunity to make repairs.

5-6    6.  A court shall dismiss an action commenced against a

5-7  subcontractor, supplier or design professional by a contractor who has

5-8  failed to comply with the requirements of subsection 4.

5-9    Sec. 8.  1.  A contractor, subcontractor, supplier or design

5-10  professional who receives notice of a constructional defect pursuant to

5-11  section 5 or 7 of this act may present the notice to an insurer who issued

5-12  a policy of insurance covering all or part of the conduct or business of

5-13  the contractor, subcontractor, supplier or design professional.

5-14    2.  A notice provided to an insurer pursuant to subsection 1:

5-15    (a) Constitutes the making of a claim under the policy by the

5-16  contractor, subcontractor, supplier or design professional; and

5-17    (b) Requires the contractor, subcontractor, supplier or design

5-18  professional and the insurer to perform any obligations or duties

5-19  required by the policy upon the making of a claim.

5-20    Sec. 9.  1.  A claimant is not required to provide a contractor with

5-21  notice pursuant to section 5 of this act before commencing an action

5-22  against the contractor for damages arising from a constructional defect

5-23  if:

5-24    (a) The contractor has threatened or initiated legal proceedings

5-25  against the claimant at any time;

5-26    (b) The claimant has been sued by a third party or the contractor in

5-27  connection with or resulting from a constructional defect and the

5-28  claimant is filing a third-party complaint or cross-complaint against the

5-29  contractor concerning that constructional defect; or

5-30    (c) The contractor has threatened to commit or committed an act of

5-31  violence or a criminal offense against the claimant or the property of the

5-32  claimant, or the claimant has a reasonable belief that the contractor

5-33  intends to commit an act of violence or a criminal offense against the

5-34  claimant or the property of the claimant.

5-35    2.  Nothing in sections 5 to 9, inclusive, of this act affects the ability

5-36  of a claimant, contractor, subcontractor, supplier or design professional

5-37  to pursue any remedy available through the state contractors’ board

5-38  pursuant to chapter 624 of NRS.

5-39    Sec. 10.  1.  Except as otherwise provided in subsection 2, in an

5-40  action pursuant to NRS 40.600 to 40.695, inclusive, and sections 2 to 11,

5-41  inclusive, of this act for the professional negligence of a design

5-42  professional or a person primarily engaged in the practice of

5-43  professional engineering, land surveying, architecture or landscape

5-44  architecture, concurrently with the service of the first pleading in an

5-45  action, the attorney for the complainant shall file an affidavit with the

5-46  court stating that the attorney:

5-47    (a) Has reviewed the facts of the case;

5-48    (b) Has consulted with an expert;


6-1    (c) Reasonably believes the expert who was consulted is

6-2  knowledgeable in the relevant discipline involved in the action; and

6-3    (d) Has concluded on the basis of his review and the consultation with

6-4  the expert that the action has a reasonable basis in law and fact.

6-5    2.  The attorney for the complainant may file the affidavit required

6-6  pursuant to subsection 1 at a later time if he could not consult with an

6-7  expert and prepare the affidavit before filing the action without causing

6-8  the action to be impaired or barred by the statute of limitations or repose,

6-9  or other limitations prescribed by law. If the attorney must submit the

6-10  affidavit late, he shall file an affidavit concurrently with the service of

6-11  the first pleading in the action stating his reason for failing to comply

6-12  with subsection 1 and the attorney shall consult with an expert and file

6-13  the affidavit required pursuant to subsection 1 not later than 45 days

6-14  after filing the action.

6-15    3.  In addition to the statement included in the affidavit pursuant to

6-16  subsection 1, a report must be attached to the affidavit. Except as

6-17  otherwise provided in subsection 4, the report must be prepared by the

6-18  expert consulted by the attorney and include, without limitation:

6-19    (a) The resumé of the expert;

6-20    (b) A statement that the expert is experienced in each discipline which

6-21  is the subject of the report;

6-22    (c) A copy of each nonprivileged document reviewed by the expert in

6-23  preparing his report, including, without limitation, each record, report

6-24  and related document that the expert has determined is relevant to the

6-25  allegations of negligent conduct that are the basis for the action;

6-26    (d) The conclusions of the expert and the basis for the conclusions;

6-27  and

6-28    (e) A statement that the expert has concluded that there is a

6-29  reasonable basis for filing the action.

6-30    4.  In an action brought by a claimant in which an affidavit is

6-31  required to be filed pursuant to subsection 1:

6-32    (a) The report required pursuant to subsection 3 is not required to

6-33  include the information set forth in paragraphs (c) and (d) of subsection

6-34  3 if the claimant or his attorney files an affidavit, at the time that the

6-35  affidavit is filed pursuant to subsection 1, stating that he made

6-36  reasonable efforts to obtain the nonprivileged documents described in

6-37  paragraph (c) of subsection 3, but was unable to obtain such documents

6-38  before filing the action;

6-39    (b) The claimant or his attorney shall amend the report required

6-40  pursuant to subsection 3 to include any documents and information

6-41  required pursuant to paragraph (c) or (d) of subsection 3 as soon as

6-42  reasonably practicable after receiving the document or information; and

6-43    (c) The court may dismiss the action if the claimant and his attorney

6-44  fail to comply with the requirements of paragraph (b).

6-45    5.  An expert consulted by an attorney to prepare an affidavit

6-46  pursuant to this section must not be a party to the action.

6-47    6.  As used in this section, “expert” means a person who is licensed in

6-48  a state to engage in the practice of professional engineering, land

6-49  surveying, architecture or landscape architecture.


7-1    Sec. 11.  1.  The court shall dismiss an action filed pursuant to NRS

7-2  40.600 to 40.695, inclusive, and sections 2 to 11, inclusive, of this act for

7-3  the professional negligence of a design professional or a person

7-4  primarily engaged in the practice of professional engineering, land

7-5  surveying, architecture or landscape architecture if the attorney for a

7-6  complainant fails to:

7-7    (a) File an affidavit required pursuant to section 10 of this act;

7-8    (b) File a report required pursuant to subsection 3 of section 10 of this

7-9  act; or

7-10    (c) Name the expert consulted in the affidavit required pursuant to

7-11  subsection 1 of section 10 of this act.

7-12    2.  The fact that an attorney for a complainant has complied or failed

7-13  to comply with the provisions of section 10 of this act is admissible in the

7-14  action.

7-15    Sec. 12.  NRS 40.600 is hereby amended to read as follows:

7-16    40.600  As used in NRS 40.600 to 40.695, inclusive, and sections 2 to

7-17  11, inclusive, of this act, unless the context otherwise requires, the words

7-18  and terms defined in NRS 40.605 to 40.630, inclusive, and sections 2 to

7-19  11, inclusive, of this act have the meanings ascribed to them in those

7-20  sections.

7-21    Sec. 13.  NRS 40.645 is hereby amended to read as follows:

7-22    40.645  Except as otherwise provided in this section and NRS 40.670:

7-23    1.  For a claim that is not a complex matter, if a contractor does not

7-24  take action to make repairs or attempt to make repairs pursuant to

7-25  subsection 1 of section 6 of this act within the time set forth in subsection

7-26  1 of section 6 of this act or within the time agreed to in writing by the

7-27  claimant and the contractor, at least 60 days before a claimant commences

7-28  an action against a contractor for damages arising from a constructional

7-29  defect, the claimant must give written notice by certified mail, return

7-30  receipt requested, to the contractor, at the contractor’s last known address,

7-31  specifying in reasonable detail the defects or any damages or injuries to

7-32  each residence or appurtenance that is the subject of the claim. The notice

7-33  must describe in reasonable detail the cause of the defects if the cause is

7-34  known, the nature and extent that is known of the damage or injury

7-35  resulting from the defects and the location of each defect within each

7-36  residence or appurtenance to the extent known. An expert opinion

7-37  concerning the cause of the defects and the nature and extent of the damage

7-38  or injury resulting from the defects based on a representative sample of the

7-39  components of the residences and appurtenances involved in the action

7-40  satisfies the requirements of this section. During the 45-day period after the

7-41  contractor receives the notice, on his written request, the contractor is

7-42  entitled to inspect the property that is the subject of the claim to determine

7-43  the nature and cause of the defect, damage or injury and the nature and

7-44  extent of repairs necessary to remedy the defect. The contractor shall,

7-45  before making the inspection, provide reasonable notice of the inspection

7-46  and shall make the inspection at a reasonable time. The contractor may

7-47  take reasonable steps to establish the existence of the defect.

7-48    2.  If a residence or appurtenance that is the subject of the claim is

7-49  covered by a homeowner’s warranty that is purchased by or on behalf of a


8-1  claimant pursuant to NRS 690B.100 to 690B.180, inclusive, a claimant

8-2  shall diligently pursue a claim under the contract.

8-3    3.  Within 60 days after the contractor receives [the notice,] notice

8-4  pursuant to subsection 1, the contractor shall make a written response to

8-5  the claimant. The response:

8-6    (a) Must be served to the claimant by certified mail, return receipt

8-7  requested, at the claimant’s last known address.

8-8    (b) Must respond to each constructional defect set forth in the

8-9  claimant’s notice, and describe in reasonable detail the cause of the defect,

8-10  if known, the nature and extent of the damage or injury resulting from the

8-11  defect, and, unless the response is limited to a proposal for monetary

8-12  compensation, the method, adequacy and estimated cost of any proposed

8-13  repair.

8-14    (c) May include[:

8-15      (1) A] a proposal for monetary compensation, which may include a

8-16  contribution from a subcontractor.

8-17      [(2) If the contractor or his subcontractor is licensed to make the

8-18  repairs, an agreement by the contractor or subcontractor to make the

8-19  repairs.

8-20      (3) An agreement by the contractor to cause the repairs to be made, at

8-21  the contractor’s expense, by another contractor who is licensed to make the

8-22  repairs, bonded and insured.

8-23  The repairs must be made within 45 days after the contractor receives

8-24  written notice of acceptance of the response, unless completion is delayed

8-25  by the claimant or by other events beyond the control of the contractor, or

8-26  timely completion of the repairs is not reasonably possible. The claimant

8-27  and the contractor may agree in writing to extend the periods prescribed by

8-28  this section.]

8-29    4.  Not later than 15 days before the mediation required pursuant to

8-30  NRS 40.680 and upon providing 15 days’ notice, each party shall provide

8-31  the other party, or shall make a reasonable effort to assist the other party to

8-32  obtain, all relevant reports, photos, correspondence, plans, specifications,

8-33  warranties, contracts, subcontracts, work orders for repair, videotapes,

8-34  technical reports, soil and other engineering reports and other documents or

8-35  materials relating to the claim that are not privileged.

8-36    5.  If the claimant is a representative of a homeowner’s association, the

8-37  association shall submit any response made by the contractor to each

8-38  member of the association.

8-39    [6.  As used in this section, “subcontractor” means a contractor who

8-40  performs work on behalf of another contractor in the construction of a

8-41  residence or appurtenance.]

8-42    Sec. 14.  NRS 40.650 is hereby amended to read as follows:

8-43    40.650  1.  If a claimant unreasonably rejects a reasonable written

8-44  offer of settlement made as part of a response made pursuant to NRS

8-45  40.645 or 40.682 or does not permit the contractor or independent

8-46  contractor a reasonable opportunity to repair the defect pursuant to [an

8-47  accepted offer of settlement] section 6 of this act and thereafter

8-48  commences an action governed by NRS 40.600 to 40.695, inclusive, and


9-1  sections 2 to 11, inclusive, of this act, the court in which the action is

9-2  commenced may:

9-3    (a) Deny the claimant’s attorney’s fees and costs; and

9-4    (b) Award attorney’s fees and costs to the contractor.

9-5  Any sums paid under a homeowner’s warranty, other than sums paid in

9-6  satisfaction of claims that are collateral to any coverage issued to or by the

9-7  contractor, must be deducted from any recovery.

9-8    2.  If a contractor fails to:

9-9    (a) Make an offer of settlement;

9-10    (b) Make a good faith response to the claim asserting no liability;

9-11    (c) Complete, in a good and workmanlike manner, the repairs [specified

9-12  in an accepted offer;] he makes pursuant to section 6 of this act;

9-13    (d) Agree to a mediator or accept the appointment of a mediator

9-14  pursuant to NRS 40.680 or subsection 4 of NRS 40.682; or

9-15    (e) Participate in mediation,

9-16  the limitations on damages and defenses to liability provided in NRS

9-17  40.600 to 40.695, inclusive, and sections 2 to 11, inclusive, of this act do

9-18  not apply and the claimant may commence an action without satisfying any

9-19  other requirement of NRS 40.600 to 40.695, inclusive [.] , and sections 2

9-20  to 11, inclusive, of this act.

9-21    3.  If coverage under a homeowner’s warranty is denied by an insurer

9-22  in bad faith, the homeowner and the contractor have a right of action for

9-23  the sums that would have been paid if coverage had been provided, plus

9-24  reasonable attorney’s fees and costs.

9-25    Sec. 15.  NRS 40.667 is hereby amended to read as follows:

9-26    40.667  1.  Except as otherwise provided in subsection 2, a written

9-27  waiver or settlement agreement executed by a claimant after a contractor

9-28  has corrected or otherwise repaired a constructional defect does not bar a

9-29  claim for the constructional defect if it is determined that the contractor

9-30  failed to correct or repair the defect properly.

9-31    2.  The provisions of subsection 1 do not apply to any written waiver or

9-32  settlement agreement described in subsection 1, unless:

9-33    (a) The claimant has obtained the opinion of an expert concerning the

9-34  constructional defect;

9-35    (b) The claimant has provided the contractor with a written notice of the

9-36  defect pursuant to NRS 40.645 [or 40.682] , 40.682 or section 5 of this act

9-37  and a copy of the expert’s opinion; and

9-38    (c) The claimant and the contractor have complied with the

9-39  requirements for inspection and repair as provided in NRS 40.600 to

9-40  40.695, inclusive [.] , and sections 2 to 11, inclusive, of this act.

9-41    3.  If a claimant does not prevail in any action which is not barred

9-42  pursuant to this section, the court may:

9-43    (a) Deny the claimant’s attorney’s fees, fees for an expert witness or

9-44  costs; and

9-45    (b) Award attorney’s fees and costs to the contractor.

9-46    Sec. 16.  NRS 40.682 is hereby amended to read as follows:

9-47    40.682  Except as otherwise provided in this section and NRS 40.670:


10-1    1.  Notwithstanding the provisions of subsection 1 of NRS 40.680, a

10-2  claimant may commence an action in district court in a complex matter. If

10-3  the claimant commences an action in district court he shall:

10-4    (a) File and serve the summons and complaint as required by law; and

10-5    (b) [At] If a contractor does not take action to make repairs or attempt

10-6  to make repairs pursuant to subsection 1 of section 6 of this act within

10-7  the time set forth in subsection 1 of section 6 of this act or within the time

10-8  agreed to in writing by the claimant and the contractor, at the same time

10-9  and in the same manner as the claimant serves the summons and complaint

10-10  upon the contractor, serve upon the contractor a written notice specifying

10-11  in reasonable detail, to the extent known, the defects and any damages or

10-12  injuries to each residence or appurtenance that is the subject of the claim.

10-13  The notice must describe in reasonable detail each defect, the specific

10-14  location of each defect, and the nature and extent that is known of the

10-15  damage or injury resulting from each defect. If an expert opinion has been

10-16  rendered concerning the existence or extent of the defects, a written copy

10-17  of the opinion must accompany the notice. An expert opinion that specifies

10-18  each defect to the extent known, the specific location of each defect to the

10-19  extent known, and the nature and extent that is known of the damage or

10-20  injury resulting from each defect, based on a valid and reliable

10-21  representative sample of the residences and appurtenances involved in the

10-22  action, satisfies the requirements of this section.

10-23  2.  The contractor shall file and serve an answer to the complaint as

10-24  required by law.

10-25  3.  Not later than 30 days after the date of service of the answer to the

10-26  complaint, the contractor and claimant shall meet to establish a schedule

10-27  for:

10-28  (a) The exchange of or reasonable access for the other party to all

10-29  relevant reports, photos, correspondence, plans, specifications, warranties,

10-30  contracts, subcontracts, work orders for repair, videotapes, technical

10-31  reports, soil and other engineering reports and other documents or

10-32  materials relating to the claim that are not privileged;

10-33  (b) The inspection of the residence or appurtenance that is the subject of

10-34  the claim to evaluate the defects set forth in the notice served pursuant to

10-35  subsection 1; and

10-36  (c) The conduct of any tests that are reasonably necessary to determine

10-37  the nature and cause of a defect or any damage or injury, and the nature

10-38  and extent of repairs necessary to remedy a defect or any damage or injury.

10-39  The party conducting the test shall provide reasonable notice of the test to

10-40  all other parties and conduct the test at a reasonable time.

10-41  4.  At the meeting held pursuant to subsection 3, the claimant and

10-42  contractor shall:

10-43  (a) Establish a schedule for the addition of any additional parties to the

10-44  complaint or to file any third-party complaint against an additional party

10-45  who may be responsible for all or a portion of the defects set forth in the

10-46  notice served pursuant to subsection 1;

10-47  (b) Unless the claimant and contractor agree otherwise in writing, select

10-48  a mediator and proceed with mediation as provided in subsections 2 to 6,

10-49  inclusive, of NRS 40.680; and


11-1    (c) If the claimant and contractor agree, select a special master and

11-2  jointly petition the court for his appointment pursuant to subsection 7.

11-3    5.  Each party added to the complaint or against whom a third-party

11-4  complaint is filed pursuant to subsection 4 shall file and serve an answer as

11-5  required by law.

11-6    6.  If the claimant or contractor adds a party to the complaint or files a

11-7  third-party complaint, then not later than 60 days after the date determined

11-8  pursuant to paragraph (a) of subsection 4, the contractor, claimant and each

11-9  party added to the complaint or against whom a third-party complaint is

11-10  filed shall meet to establish a schedule for the activities set forth in

11-11  paragraphs (a), (b) and (c) of subsection 3.

11-12  7.  If a special master has not been appointed, the contractor, claimant

11-13  or a party added to the complaint or against whom a third-party complaint

11-14  is filed may petition the court for the appointment of a special master at

11-15  any time after the meeting held pursuant to subsection 3. The special

11-16  master may:

11-17  (a) Take any action set forth in subsection 4 of NRS 40.680;

11-18  (b) Exercise any power set forth in Rule 53 of the Nevada Rules of Civil

11-19  Procedure; and

11-20  (c) Subject to the provisions of NRS 40.680, if the parties fail to

11-21  establish a schedule or determine a date as required in subsection 3, 4 or 6,

11-22  establish the schedule or determine the date.

11-23  8.  Unless the mediation required pursuant to paragraph (b) of

11-24  subsection 4 is completed or the contractor and claimant have agreed in

11-25  writing not to mediate the claim pursuant to paragraph (b) of subsection 4,

11-26  a party shall not propound interrogatories or requests for admission, take a

11-27  deposition or file a motion that is dispositive of the action except:

11-28  (a) Upon agreement of the parties; or

11-29  (b) With the prior approval of the court or special master.

11-30  9.  If a residence or appurtenance that is the subject of the claim is

11-31  covered by a homeowner’s warranty that is purchased by or on behalf of a

11-32  claimant pursuant to NRS 690B.100 to 690B.180, inclusive, a claimant

11-33  shall diligently pursue a claim under the contract.

11-34  10.  Unless the parties agree otherwise, not less than 60 days before the

11-35  date of the mediation pursuant to paragraph (b) of subsection 4 is

11-36  convened, the contractor shall make a written response to the claimant that

11-37  meets the requirements set forth in subsection 3 of NRS 40.645.

11-38  11.  If the claimant is a representative of a homeowner’s association,

11-39  the association shall submit any response made by the contractor to each

11-40  member of the association in writing not more than 30 days after the date

11-41  the claimant receives the response.

11-42  12.  The claimant shall respond to the written response of the contractor

11-43  within 45 days after the response of the contractor is mailed to the

11-44  claimant.

11-45  Sec. 17.  NRS 40.688 is hereby amended to read as follows:

11-46  40.688  1.  If a claimant attempts to sell a residence that is or has been

11-47  the subject of a claim governed by NRS 40.600 to 40.695, inclusive, and

11-48  sections 2 to 11, inclusive, of this act or the subject of a notice given

11-49  pursuant to section 5 of this act, he shall disclose, in writing, to any


12-1  prospective purchaser of the residence, not less than 30 days before the

12-2  close of escrow for the sale of the residence or, if escrow is to close less

12-3  than 30 days after the execution of the sales agreement, then immediately

12-4  upon the execution of the sales agreement or, if a claim is initiated or a

12-5  notice is given less than 30 days before the close of escrow, within 24

12-6  hours after giving written notice to the contractor pursuant to section 5 of

12-7  this act, subsection 1 of NRS 40.645 or subsection 1 of NRS 40.682:

12-8    (a) All notices given by the claimant to the contractor pursuant to NRS

12-9  40.600 to 40.695, inclusive, and sections 2 to 11, inclusive, of this act that

12-10  are related to the residence;

12-11  (b) All opinions the claimant has obtained from experts regarding a

12-12  constructional defect that is or has been the subject of the claim;

12-13  (c) The terms of any settlement, order or judgment relating to the claim;

12-14  and

12-15  (d) A detailed report of all repairs made to the residence by or on behalf

12-16  of the claimant as a result of a constructional defect that is or has been the

12-17  subject of the claim.

12-18  2.  Before taking any action on a claim pursuant to NRS 40.600 to

12-19  40.695, inclusive, and sections 2 to 11, inclusive, of this act or giving

12-20  notice pursuant to section 5 of this act, the attorney for a claimant shall

12-21  notify the claimant in writing of the provisions of this section.

12-22  Sec. 18.  NRS 40.692 is hereby amended to read as follows:

12-23  40.692  [If,] Except as otherwise provided in sections 5 and 7 of this

12-24  act, if after complying with the procedural requirements of sections 5 and

12-25  7 of this act and NRS 40.645 and 40.680, or NRS 40.682, a claimant

12-26  proceeds with an action for damages arising from a constructional defect:

12-27  1.  The claimant and each contractor who is named in the original

12-28  complaint when the action is commenced are not required, while the action

12-29  is pending, to comply with the requirements of sections 5 and 7 of this act,

12-30  NRS 40.645 or 40.680, or NRS 40.682, for any constructional defect that

12-31  the claimant includes in an amended complaint, if the constructional

12-32  defect:

12-33  (a) Is attributable, in whole or in part, to such a contractor;

12-34  (b) Is located on the same property described in the original complaint;

12-35  and

12-36  (c) Was not discovered before the action was commenced provided that

12-37  a good faith effort had been undertaken by the claimant.

12-38  2.  The claimant is not required to give written notice of a defect

12-39  pursuant to subsection 1 of NRS 40.645 or subsection 1 of NRS 40.682 to

12-40  any person who is joined to or intervenes in the action as a party after it is

12-41  commenced. If such a person becomes a party to the action:

12-42  (a) For the purposes of subsection 1 of NRS 40.645 or subsection 1 of

12-43  NRS 40.682, the person shall be deemed to have been given notice of the

12-44  defect by the claimant on the date on which the person becomes a party to

12-45  the action; and

12-46  (b) The provisions of NRS 40.600 to 40.695, inclusive, apply to the

12-47  person after that date.

 

 


13-1    Sec. 19.  NRS 40.695 is hereby amended to read as follows:

13-2    40.695  1.  Except as otherwise provided in subsection 2, statutes of

13-3  limitation or repose applicable to a claim based on a constructional defect

13-4  governed by NRS 40.600 to 40.695, inclusive, and sections 2 to 11,

13-5  inclusive, of this act are tolled from the time notice of the claim is given[,]

13-6  or notice of a defect, damage or injury is given pursuant to section 5 of

13-7  this act, until 30 days after mediation is concluded or waived in writing

13-8  pursuant to NRS 40.680 or subsection 4 of NRS 40.682.

13-9    2.  Tolling under this section applies [:

13-10  (a) Only to a claim that is not a complex matter.

13-11  (b) To] to a third party regardless of whether the party is required to

13-12  appear in the proceeding.

13-13  Sec. 20.  Chapter 113 of NRS is hereby amended by adding thereto a

13-14  new section to read as follows:

13-15  1.  Each contractor who develops, constructs or landscapes a new

13-16  residence shall, within 30 days after the close of escrow of the initial

13-17  purchase of the residence, provide in writing to the initial purchaser of

13-18  the residence:

13-19  (a) The name, license number, business address and telephone

13-20  number of each subcontractor who performed any work related to the

13-21  development, construction or landscaping of the residence; and

13-22  (b) A brief description so the work performed by each subcontractor

13-23  identified pursuant to paragraph (a).

13-24  2.  As used in this section, “subcontractor” has the meaning ascribed

13-25  to it in section 3 of this act.

13-26  Sec. 21.  Chapter 116 of NRS is hereby amended by adding thereto the

13-27  provisions set forth as sections 22 to 25, inclusive, of this act.

13-28  Sec. 22.  1.  A person shall not provide or offer to provide anything

13-29  of monetary value to a property manager of an association or to a

13-30  member or officer of an executive board to induce the property manager,

13-31  member or officer to encourage or discourage the association to file a

13-32  claim for damages arising from a constructional defect.

13-33  2.  A property manager shall not accept anything of value given to

13-34  him in exchange for encouraging or discouraging the association that he

13-35  manages to file a claim for damages arising from a constructional defect.

13-36  3.  A member or officer of an executive board shall not accept

13-37  anything of value given to him in exchange for encouraging or

13-38  discouraging the association of which he is a member or officer of the

13-39  executive board to file a claim for damages arising from a constructional

13-40  defect.

13-41  4.  If a property manager violates the provisions of this section:

13-42  (a) The real estate division of the department of business and industry

13-43  shall suspend or revoke his permit to engage in property management

13-44  issued pursuant to chapter 645 of NRS, if he has been issued such a

13-45  permit; and

13-46  (b) The real estate commission shall suspend or revoke his certificate

13-47  issued pursuant to NRS 116.31139, if he has been issued such a

13-48  certificate.


14-1  5.  If a member or officer of an executive board violates the

14-2  provisions of this section, the executive board shall remove the officer or

14-3  member from the board.

14-4  6.  Any person who willfully violates the provisions of this section is

14-5  guilty of a misdemeanor.

14-6  7.  As used in this section, “constructional defect” has the meaning

14-7  ascribed to it in NRS 40.615.

14-8  Sec. 23.  1.  An association may bring an action to recover damages

14-9  resulting from constructional defects in any of the units, common

14-10  elements or limited common elements of the common-interest

14-11  community, or submit such a claim to mediation pursuant to NRS

14-12  40.680, only:

14-13  (a) If the association first obtains the written approval of each unit’s

14-14  owner whose unit or interest in the common elements or limited common

14-15  elements will be the subject of the action or claim;

14-16  (b) Upon a vote of the units’ owners to which at least a majority of the

14-17  votes of the members of the association are allocated; and

14-18  (c) Upon a vote of the executive board of the association.

14-19  2.  If an action is brought by an association to recover damages

14-20  resulting from constructional defects in any of the units, common

14-21  elements or limited common elements of the common-interest

14-22  community, or such a claim is submitted to mediation pursuant to NRS

14-23  40.680, the attorney representing the association shall provide to the

14-24  executive board of the association and to each unit’s owner a statement

14-25  that includes, in reasonable detail:

14-26  (a) The defects and damages or injuries to the units, common

14-27  elements or limited common elements;

14-28  (b) The cause of the defects, if the cause is known;

14-29  (c) The nature and the extent that is known of the damage or injury

14-30  resulting from the defects;

14-31  (d) The location of each defect within the units, common elements or

14-32  limited common elements, if known;

14-33  (e) A reasonable estimate of the cost of the action or mediation,

14-34  including reasonable attorney’s fees;

14-35  (f) An explanation of the potential benefits of the action or mediation

14-36  and the potential adverse consequences if the association does not

14-37  commence the action or submit the claim to mediation or if the outcome

14-38  is not favorable to the association; and

14-39  (g) All disclosures that are required to be made upon the sale of the

14-40  property.

14-41  3.  An association or an attorney for an association shall not employ

14-42  a person to perform destructive tests to determine any damage or injury

14-43  to a unit, common element or limited common element caused by a

14-44  constructional defect unless:

14-45  (a) The person is licensed as a contractor pursuant to chapter 624 of

14-46  NRS;

14-47  (b) The association has obtained the prior written approval of each

14-48  unit’s owner whose unit or interest in the common element or limited

14-49  common element will be affected by such testing;


15-1  (c) The person has provided a written schedule for repairs;

15-2  (d) The person is required to repair all damage resulting from such

15-3  tests in accordance with state laws and local ordinances relating thereto;

15-4  and

15-5  (e) The association or the person so employed obtains all permits

15-6  required to conduct such tests and to repair any damage resulting from

15-7  such tests.

15-8  4.  As used in this section, “constructional defect” has the meaning

15-9  ascribed to it in NRS 40.615.

15-10  Sec. 24.  1.  Except as otherwise provided in subsection 2 and

15-11  section 23 of this act, an association may commence a civil action only

15-12  upon a vote or written agreement of the owners of the units to which at

15-13  least a majority of the votes of the members of the association are

15-14  allocated. In such a case, the association shall provide written notice to

15-15  the owner of each unit of the meeting at which the commencement of a

15-16  civil action is to be considered or action is to be taken within 21 calendar

15-17  days before the meeting.

15-18  2.  The provisions of subsection 1 do not apply to a civil action that is

15-19  commenced:

15-20  (a) By an association for a time-share project governed by the

15-21  provisions of chapter 119A of NRS;

15-22  (b) To enforce the payment of an assessment;

15-23  (c) To enforce the declaration, bylaws or rules of the association;

15-24  (d) To proceed with a counterclaim; or

15-25  (e) To enforce or rescind a contract to which the association is a

15-26  party.

15-27  Sec. 25.  1.  Notwithstanding any other provision of this chapter, the

15-28  executive board of an association may, without giving notice to the units’

15-29  owners, employ a contractor licensed pursuant to the provisions of

15-30  chapter 624 of NRS and such other persons as are necessary to make

15-31  such repairs to a unit or common element within the common-interest

15-32  community as are required to protect the health, safety and welfare of the

15-33  units’ owners.

15-34  2.  If the governing documents of the association require such action

15-35  to be taken at a meeting of the executive board of the association, the

15-36  executive board shall, within 90 days after employing any person

15-37  pursuant to subsection 1, provide written notice to the units’ owners of its

15-38  action and include the action on the agenda of its next regularly

15-39  scheduled meeting.

15-40  Sec. 26.  NRS 116.1203 is hereby amended to read as follows:

15-41  116.1203  1.  Except as otherwise provided in subsection 2, if a

15-42  planned community contains no more than 12 units and is not subject to

15-43  any developmental rights, it is subject only to NRS 116.1105, 116.1106

15-44  and 116.1107 unless the declaration provides that this entire chapter is

15-45  applicable.

15-46  2.  Except for NRS 116.3104, 116.31043, 116.31046 and 116.31138,

15-47  NRS 116.3101 to 116.3119, inclusive, and section 14 of Assembly Bill No.

15-48  621 of this session and sections 22 to 25, inclusive, of this act and

15-49  116.110305 to 116.110393, inclusive, to the extent necessary in construing


16-1  any of those sections, apply to a residential planned community containing

16-2  more than six units.

16-3    Sec. 27.  NRS 116.31139 is hereby amended to read as follows:

16-4    116.31139  1.  An association may employ a person engaged in

16-5  property management for the common-interest community.

16-6    2.  Except as otherwise provided in this section, a person engaged in

16-7  property management for a common-interest community must:

16-8    (a) Hold a permit to engage in property management that is issued

16-9  pursuant to the provisions of chapter 645 of NRS; or

16-10  (b) Hold a certificate issued by the real estate commission pursuant to

16-11  subsection 3.

16-12  3.  The real estate commission shall provide by regulation for the

16-13  issuance of certificates for the management of common-interest

16-14  communities to persons who are not otherwise authorized to engage in

16-15  property management pursuant to the provisions of chapter 645 of NRS.

16-16  The regulations:

16-17  (a) Must establish the qualifications for the issuance of such a

16-18  certificate, including the education and experience required to obtain such

16-19  a certificate;

16-20  (b) May require applicants to pass an examination in order to obtain a

16-21  certificate;

16-22  (c) Must establish standards of practice for persons engaged in property

16-23  management for a common-interest community;

16-24  (d) Must establish the grounds for initiating disciplinary action against a

16-25  person to whom a certificate has been issued, including, without limitation,

16-26  the grounds for placing conditions, limitations or restrictions on a

16-27  certificate and for the suspension or revocation of a certificate; and

16-28  (e) Must establish rules of practice and procedure for conducting

16-29  disciplinary hearings.

16-30  The real estate division of the department of business and industry may

16-31  investigate the property managers to whom certificates have been issued to

16-32  ensure their compliance with section 22 of this act and the standards of

16-33  practice adopted pursuant to this subsection and collect a fee for the

16-34  issuance of a certificate by the commission in an amount not to exceed the

16-35  administrative costs of issuing the certificate.

16-36  4.  The provisions of subsection 2 do not apply to:

16-37  (a) A person who is engaged in property management for a common-

16-38  interest community on October 1, 1999, and is granted an exemption from

16-39  the requirements of subsection 2 by the administrator upon demonstration

16-40  that he is qualified and competent to engage in property management for a

16-41  common-interest community.

16-42  (b) A financial institution.

16-43  (c) An attorney licensed to practice in this state.

16-44  (d) A trustee.

16-45  (e) An employee of a corporation who manages only the property of the

16-46  corporation.

16-47  (f) A declarant.

16-48  (g) A receiver.


17-1    5.  As used in this section, “property management” means the physical,

17-2  administrative or financial maintenance and management of real property,

17-3  or the supervision of those activities for a fee, commission or other

17-4  compensation or valuable consideration.

17-5    Sec. 28.  NRS 116.3115 is hereby amended to read as follows:

17-6    116.3115  1.  Until the association makes an assessment for common

17-7  expenses, the declarant shall pay all common expenses. After an

17-8  assessment has been made by the association, assessments must be made at

17-9  least annually, based on a budget adopted at least annually by the

17-10  association in accordance with the requirements set forth in NRS

17-11  116.31151. Except for an association for a time-share project governed by

17-12  the provisions of chapter 119A of NRS, and unless the declaration imposes

17-13  more stringent standards, the budget must include a budget for the daily

17-14  operation of the association and the money for the reserve required by

17-15  paragraph (b) of subsection 2.

17-16  2.  Except for assessments under subsections 4 to 7, inclusive:

17-17  (a) All common expenses, including a reserve, must be assessed against

17-18  all the units in accordance with the allocations set forth in the declaration

17-19  pursuant to subsections 1 and 2 of NRS 116.2107.

17-20  (b) The association shall establish an adequate reserve, funded on a

17-21  reasonable basis, for the repair, replacement and restoration of the major

17-22  components of the common elements. The reserve may be used only for

17-23  those purposes, including, without limitation, repairing, replacing and

17-24  restoring roofs, roads and sidewalks, and must not be used for daily

17-25  maintenance.

17-26  3.  Any past due assessment for common expenses or installment

17-27  thereof bears interest at the rate established by the association not

17-28  exceeding 18 percent per year.

17-29  4.  To the extent required by the declaration:

17-30  (a) Any common expense associated with the maintenance, repair,

17-31  restoration or replacement of a limited common element must be assessed

17-32  against the units to which that limited common element is assigned,

17-33  equally, or in any other proportion the declaration provides;

17-34  (b) Any common expense or portion thereof benefiting fewer than all of

17-35  the units must be assessed exclusively against the units benefited; and

17-36  (c) The costs of insurance must be assessed in proportion to risk and the

17-37  costs of utilities must be assessed in proportion to usage.

17-38  5.  Assessments to pay a judgment against the association may be made

17-39  only against the units in the common-interest community at the time the

17-40  judgment was entered, in proportion to their liabilities for common

17-41  expenses.

17-42  6.  If any common expense is caused by the misconduct of any unit’s

17-43  owner, the association may assess that expense exclusively against his unit.

17-44  7.  The association of a common-interest community created before

17-45  January 1, 1992, is not required to make an assessment against a vacant lot

17-46  located within the community that is owned by the declarant.

17-47  8.  If liabilities for common expenses are reallocated, assessments for

17-48  common expenses and any installment thereof not yet due must be

17-49  recalculated in accordance with the reallocated liabilities.


18-1  9.  The association shall provide written notice to the owner of each

18-2  unit of a meeting at which an assessment for a capital improvement [or the

18-3  commencement of a civil action] is to be considered or action is to be taken

18-4  on such an assessment at least 21 calendar days before the meeting.

18-5  [Except as otherwise provided in this subsection, the association may

18-6  commence a civil action only upon a vote or written agreement of the

18-7  owners of units to which at least a majority of the votes of the members of

18-8  the association are allocated. The provisions of this subsection do not apply

18-9  to a civil action that is commenced:

18-10  (a) By an association for a time-share project governed by the

18-11  provisions of chapter 119A of NRS;

18-12  (b) To enforce the payment of an assessment;

18-13  (c) To enforce the declaration, bylaws or rules of the association;

18-14  (d) To proceed with a counterclaim; or

18-15  (e) To protect the health, safety and welfare of the members of the

18-16  association. If a civil action is commenced pursuant to this paragraph

18-17  without the required vote or agreement, the action must be ratified within

18-18  90 days after the commencement of the action by a vote or written

18-19  agreement of the owners of the units to which at least a majority of votes of

18-20  the members of the association are allocated. If the association, after

18-21  making a good faith effort, cannot obtain the required vote or agreement to

18-22  commence or ratify such a civil action, the association may thereafter seek

18-23  to dismiss the action without prejudice for that reason only if a vote or

18-24  written agreement of the owners of the units to which at least a majority of

18-25  votes of the members of the association are allocated was obtained at the

18-26  time the approval to commence or ratify the action was sought.

18-27  10.  At least 10 days before an association commences or seeks to

18-28  ratify the commencement of a civil action, the association shall provide a

18-29  written statement to all units’ owners that includes:

18-30  (a) A reasonable estimate of the costs of the civil action, including

18-31  reasonable attorney’s fees;

18-32  (b) An explanation of the potential benefits of the civil action and the

18-33  potential adverse consequences if the association does not commence the

18-34  action or if the outcome of the action is not favorable to the association;

18-35  and

18-36  (c) All disclosures that are required to be made upon the sale of the

18-37  property.

18-38  11.  No person other than a unit’s owner may request the dismissal of a

18-39  civil action commenced by the association on the ground that the

18-40  association failed to comply with any provision of this section.]

18-41  Sec. 29.  NRS 119A.165 is hereby amended to read as follows:

18-42  119A.165  1.  If a matter governed by this chapter is also governed by

18-43  chapter 116 of NRS, compliance with the provisions of chapter 116 of

18-44  NRS governing the matter which are in addition to or different from the

18-45  provisions in this chapter governing the same matter is not required. In the

18-46  event of a conflict between provisions of this chapter and chapter 116 of

18-47  NRS, the provisions of this chapter prevail.

18-48  2.  Without limiting the generality of subsection 1, the provisions of

18-49  NRS 116.11145, 116.12065, 116.3103, 116.31031, 116.31034, 116.3106,


19-1  116.31065, 116.3108 to 116.311, inclusive, 116.31139, 116.31145 to

19-2  116.31158, inclusive, 116.31162, 116.31175, 116.31177, 116.41095 and

19-3  116.4117 and section 22 of this act do not apply to a time share or a time-

19-4  share project.

19-5  Sec. 30.  Chapter 278 of NRS is hereby amended by adding thereto the

19-6  provisions set forth as sections 31 and 32 of this act.

19-7  Sec. 31.  1.  Except as otherwise provided in this subsection, the

19-8  governing body of each city and county shall not accept an application

19-9  for a building permit for a project that includes the construction of new

19-10  footings or a new foundation for a structure or that requires excavation

19-11  or embankment of more than 5,000 cubic yards of earth, unless the

19-12  application is submitted with a geotechnical report. The governing body

19-13  may waive the requirement of the geotechnical report for any project

19-14  other than a project involving a residential dwelling unit.

19-15  2.  The geotechnical report required pursuant to subsection 1 must

19-16  include:

19-17  (a) Information concerning the soil and geology of the site where the

19-18  project will be carried out;

19-19  (b) Information concerning the ground water on the site where the

19-20  project will be carried out and the potential that the ground water may

19-21  adversely affect the foundation of the project;

19-22  (c) A written statement from the architect, civil engineer or structural

19-23  engineer who was responsible for the design of the project verifying that

19-24  the design of the project is compatible with the geotechnical conditions

19-25  described in paragraphs (a) and (b);

19-26  (d) A written statement from a geotechnical engineer who has

19-27  reviewed the plans for the grading and foundation of the project

19-28  verifying that the project is geotechnically in compliance with the

19-29  geotechnical conditions of the site as described in paragraphs (a) and

19-30  (b); and

19-31  (e) Any other information required by the governing body.

19-32  3.  The governing body of each city and county shall require by

19-33  ordinance the submission of a final report concerning grading of the

19-34  property, the elevation of the finished floor and the drainage on the

19-35  property for each construction project for which a geotechnical report is

19-36  required pursuant to subsection 1.

19-37  4.  The ordinance adopted pursuant to subsection 3 must require:

19-38  (a) The final report concerning grading of the property to include

19-39  certification that the grading and the excavating or embanking work

19-40  complies with the requirements set forth in the geotechnical report

19-41  completed pursuant to subsection 1 and any supplements or addenda to

19-42  the report;

19-43  (b) The final report concerning the elevation of the finished floor to

19-44  include certification that the lowest elevation of the finished floor of the

19-45  project that is habitable complies with the plans for the project that were

19-46  approved by the governing body; and

19-47  (c) The final report concerning the drainage on the property to

19-48  include:


20-1      (1) A statement that the conditions of the drainage system on the

20-2  site of the project at the completion of the project complies with the plan

20-3  for drainage or the plan for the plot and grading that was approved by

20-4  the governing body; and

20-5      (2) If the plans for the project that were approved by the governing

20-6  body required a drainage system or facilities, structures or devices for

20-7  drainage that were designed by an engineer, verification from a civil

20-8  engineer that the drainage system and any facilities, structures or devices

20-9  for drainage were installed and constructed in compliance with those

20-10  plans. Devices for drainage include, without limitation, detention of

20-11  drainage on the site, drainage from one lot to another lot and devices for

20-12  conveying drainage.

20-13  5.  The governing body of each city and county shall adopt an

20-14  ordinance that requires a developer to provide a person who purchases a

20-15  completed construction project described in subsection 1 with a written

20-16  report concerning the applicable building codes and regulations and any

20-17  recommendations of a geotechnical engineer and a civil engineer

20-18  concerning the use of the project. The ordinance must provide that this

20-19  report is part of the sales documents that must be acknowledged by the

20-20  buyer.

20-21  6.  As used in this section, “residential dwelling unit” has the

20-22  meaning ascribed to it in NRS 278.4977.

20-23  Sec. 32.  The governing body of each city and county shall adopt

20-24  ordinances to ensure the prevention and mitigation of harm to a building

20-25  or structure caused by water that is standing under the building or

20-26  structure.

20-27  Sec. 33.  NRS 278.010 is hereby amended to read as follows:

20-28  278.010  As used in NRS 278.010 to 278.630, inclusive, and sections

20-29  31 and 32 of this act, unless the context otherwise requires, the words and

20-30  terms defined in NRS 278.0105 to 278.0195, inclusive, have the meanings

20-31  ascribed to them in those sections.

20-32  Sec. 34.  The amendatory provisions of this act do not apply to a claim

20-33  initiated or an action commenced pursuant to NRS 40.600 to 40.695,

20-34  inclusive, and sections 2 to 11, inclusive, of this act, unless the claim was

20-35  initiated or the action was commenced on or after the effective date of this

20-36  act.

20-37  Sec. 35.  This act becomes effective upon passage and approval.

 

20-38  H