Assembly Bill No. 79–Assemblymen Dini,
Neighbors, Carpenter, Price, Anderson, de Braga, Gibbons, Humke, Marvel and
Perkins
February 9, 2001
____________
Referred to Committee on Natural Resources, Agriculture, and Mining
SUMMARY—Revises provisions governing issuance of
permits for exploration projects and mining operations. (BDR 46‑1108)
FISCAL NOTE: Effect on Local Government: No.
~
EXPLANATION
– Matter in bolded italics is new; matter
between brackets [omitted material] is material to be omitted.
Green numbers along
left margin indicate location on the printed bill (e.g., 5-15 indicates page 5, line 15).
AN ACT relating to mining; providing for the issuance of interim permits to engage in an
exploration project or mining operation; and providing other matters properly
relating thereto.
THE PEOPLE OF THE STATE OF NEVADA, REPRESENTED IN
SENATE AND ASSEMBLY, DO ENACT AS FOLLOWS:
1-1 Section 1. Chapter 519A
of NRS is hereby amended by adding
1-2 thereto the provisions set
forth as sections 2 and 3 of this act.
1-3 Sec. 2. “Permit” means a
permit authorized by the provisions of this
1-4 chapter. The term includes an interim permit described in section 3
of
1-5 this act.
1-6 Sec. 3. 1. Within 15 days after the division receives an
application
1-7 for a permit pursuant to the provisions of NRS 519A.190 or
519A.210,
1-8 the division shall review the application and notify the applicant
if any
1-9 additional information is required to complete the application. The
notice
1-10 must state the additional information that is required.
1-11 2. If an applicant provides additional
information to the division to
1-12 complete an application pursuant to the provisions of subsection 1,
the
1-13 division shall, within 15 days after receiving the additional
information,
1-14 notify the applicant if more additional information is required.
The
1-15 notice must state the additional information that is required.
1-16 3. An applicant who submits to the division an
application specified
1-17 in subsection 1 shall be deemed to have been issued an interim
permit if:
1-18 (a) The division fails to
approve or deny an application specified in
1-19 subsection 1 within 30 days after the division receives it; and
2-1 (b) The applicant has filed
with the division a bond or other surety in
2-2 accordance with the provisions of:
2-3 (1) Subsection 5 of NRS
519A.190, if the application is for a permit
2-4 to engage in an exploration project; or
2-5 (2) Subsection 5 of NRS
519A.210, if the application is for a permit
2-6 to engage in a mining operation.
2-7 4. Except as otherwise provided in subsection 5,
an applicant who is
2-8 deemed to have been issued an interim permit pursuant to subsection
3 is
2-9 authorized to engage in the exploration project or mining operation
for
2-10 which he submitted his application, in the same manner and under
the
2-11 same conditions as if the division had approved his application and
2-12 issued a permit, from the 31st day after the application was
received by
2-13 the division or the date on which the requirements of paragraph (b)
of
2-14 subsection 3 are satisfied, whichever is later, until the division
approves
2-15 or denies the application.
2-16 5. If an applicant fails to provide additional
information requested by
2-17 the division within 15 days after he receives the request for
additional
2-18 information from the division, any interim permit deemed to have
been
2-19 issued to him for the project or operation to which the additional
2-20 information applies is suspended from the 16th day after he
receives the
2-21 request for additional information until the division receives the
2-22 additional information.
2-23 6. Any notice provided by the division to an
applicant and any
2-24 information provided by the applicant to the division pursuant to
the
2-25 provisions of this section must be served personally or by
certified mail,
2-26 return receipt requested.
2-27 7. The division shall not impose a fee for an
interim permit described
2-28 in this section.
2-29 Sec. 4. NRS 519A.020 is hereby amended to read as follows:
2-30 519A.020 As used in this
chapter, unless the context otherwise
2-31 requires, the words and
terms defined in NRS 519A.030 to 519A.130,
2-32 inclusive, and section 2 of this act
have the meanings ascribed to them in
2-33 those sections.
2-34 Sec. 5. This act becomes effective on July 1, 2001.
2-35 H