S.B. 274

 

Senate Bill No. 274–Committee on Commerce and Labor

 

March 5, 2001

____________

 

Referred to Committee on Commerce and Labor

 

SUMMARY—Revises provisions governing rights and duties of contractors and subcontractors under contracts or subcontracts. (BDR 54‑593)

 

FISCAL NOTE:            Effect on Local Government: No.

                                    Effect on the State: No.

 

~

 

EXPLANATION – Matter in bolded italics is new; matter between brackets [omitted material] is material to be omitted.

Green numbers along left margin indicate location on the printed bill (e.g., 5-15 indicates page 5, line 15).

 

AN ACT relating to contractors; revising the provisions governing the rights and duties of contractors and subcontractors under contracts and subcontracts; and providing other matters properly relating thereto.

 

THE PEOPLE OF THE STATE OF NEVADA, REPRESENTED IN

SENATE AND ASSEMBLY, DO ENACT AS FOLLOWS:

 

1-1    Section 1. Chapter 624 of NRS is hereby amended by adding thereto a

1-2  new section to read as follows:

1-3    1.  If a contractor or a higher-tiered subcontractor enters into a

1-4  written subcontract with a subcontractor that includes a schedule for

1-5  payments, the contractor or higher-tiered subcontractor shall pay the

1-6  subcontractor on or before the date payment is due pursuant to the

1-7  schedule for payments. If a written subcontract does not contain a

1-8  schedule for payments or if a subcontract is oral, and if the

1-9  subcontractor has performed under the subcontract, the contractor or

1-10  higher-tiered subcontractor shall pay the subcontractor:

1-11    (a) Within 30 days after the date the subcontractor submits a request

1-12  for payment; or

1-13    (b) Within 10 days after the date the contractor or higher-tiered

1-14  subcontractor receives payment for all or a portion of the work, labor,

1-15  materials, equipment or services described in a request for payment

1-16  submitted by the subcontractor,

1-17  whichever is earlier.

1-18    2.  If a contractor or a higher-tiered subcontractor fails to pay a

1-19  subcontractor within the time provided in subsection 1, the subcontractor

1-20  may stop work under the subcontract until payment is received if the

1-21  subcontractor gives written notice to the contractor or higher-tiered

1-22  subcontractor at least 5 working days before stopping work.


2-1    3.  If a subcontractor stops work pursuant to subsection 2, the

2-2  subcontractor may terminate the subcontract by giving written notice of

2-3  the termination to the contractor or higher-tiered subcontractor.

2-4    4.  If a contractor or a higher-tiered subcontractor through his own

2-5  act or neglect, or through the act or neglect of his agent, excluding acts

2-6  of God, floods, fires or strikes, causes the work to be stopped for a period

2-7  of 5 working days or more, the subcontractor may terminate the

2-8  subcontract if:

2-9    (a) The subcontractor gives written notice of his intent to terminate to

2-10  the contractor or higher-tiered subcontractor at least 5 working days

2-11  before terminating the subcontract; and

2-12    (b) The contractor or higher-tiered subcontractor fails to resume work

2-13  within 5 working days after receiving notice pursuant to paragraph (a).

2-14    5.  If a subcontractor terminates a subcontract pursuant to subsection

2-15  3 or 4, the subcontractor may recover from the contractor or higher-

2-16  tiered subcontractor with whom he has contracted the amount found by a

2-17  trier of fact to be due the subcontractor, plus 2 percent of that amount,

2-18  including, without limitation:

2-19    (a) The cost of all work, labor, materials, equipment and services

2-20  furnished by the subcontractor;

2-21    (b) The profit and overhead the subcontractor would have received if

2-22  the subcontract had been performed in full;

2-23    (c) Interest at the rate agreed upon in the subcontract, or if no interest

2-24  rate is so provided, then interest at a rate equal to the prime rate at the

2-25  largest bank in this state, as determined by the commissioner of financial

2-26  institutions on January 1 or July 1, as the case may be, immediately

2-27  preceding:

2-28      (1) The time the subcontract was signed; or

2-29      (2) If the subcontract was oral, the time the terms of the

2-30  subcontract were agreed to by the parties; and

2-31    (d) The attorneys’ fees and costs incurred by the subcontractor in

2-32  collecting the amount due.

2-33    6.  A subcontractor shall provide a copy of any notice given to a

2-34  contractor or higher-tiered subcontractor pursuant to this section to each

2-35  lower-tiered subcontractor with whom the subcontractor has contracted

2-36  who has not fully performed under that contract. Upon receipt of

2-37  payment pursuant to this section, the subcontractor shall notify all such

2-38  lower-tiered subcontractors in writing of his receipt of payment.

2-39    7.  If a subcontractor stops work pursuant to this section, each such

2-40  lower-tiered subcontractor may also stop work on the project. If a

2-41  subcontractor terminates a subcontract pursuant to this section, all such

2-42  lower-tiered subcontractors may terminate their contracts with the

2-43  subcontractor.

2-44    8.  The right of a subcontractor to stop work or terminate a

2-45  subcontract pursuant to this section is in addition to all other rights that

2-46  the subcontractor may have at law or in equity.

2-47    9.  No subcontractor or his lower-tiered subcontractors, or their

2-48  respective sureties, may be held liable for any delays or damages that an

2-49  owner, contractor or higher-tiered subcontractor may suffer as a result


3-1  of the subcontractor stopping his work or terminating a subcontract in

3-2  accordance with this section.

3-3    10.  A condition, stipulation or provision in a subcontract or other

3-4  agreement which requires a subcontractor to waive any rights provided

3-5  in this section or which limits those rights is void.

3-6    11.  All notices required pursuant to this section must be:

3-7    (a) Delivered personally;

3-8    (b) Sent by facsimile and delivered by regular mail; or

3-9    (c) Delivered by certified mail.

3-10    12.  As used in this section:

3-11    (a) “Higher-tiered subcontractor” means a subcontractor under a

3-12  contract who has entered into a subcontract with another subcontractor

3-13  pursuant to which the other subcontractor has agreed to perform any of

3-14  the duties of the subcontractor under the contract.

3-15    (b) “Lower-tiered subcontractor” means a subcontractor who has

3-16  agreed in a contract to perform any of the duties of another

3-17  subcontractor under another contract.

3-18    Sec. 2.  NRS 624.020 is hereby amended to read as follows:

3-19    624.020  [1.  For the purpose of this chapter, “contractor”] For the

3-20  purposes of this chapter, unless the context otherwise requires:

3-21    1.  “Contractor” is synonymous with “builder.”

3-22    2.  [Within the meaning of this chapter, a] A contractor is any person,

3-23  except a registered architect or a licensed professional engineer, acting

3-24  solely in his professional capacity, who in any capacity other than as the

3-25  employee of another with wages as the sole compensation, undertakes to,

3-26  [or] offers to undertake to, [or] purports to have the capacity to undertake

3-27  to, or submits a bid to, or does himself or by or through others, construct,

3-28  alter, repair, add to, subtract from, improve, move, wreck or demolish any

3-29  building, highway, road, railroad, excavation or other structure, project,

3-30  development or improvement, or to do any part thereof, including the

3-31  erection of scaffolding or other structures or works in connection

3-32  therewith. Evidence of the securing of any permit from a governmental

3-33  agency or the employment of any person on a construction project must be

3-34  accepted by the board or any court of this state as prima facie evidence that

3-35  the person securing that permit or employing any person on a construction

3-36  project is acting in the capacity of a contractor pursuant to the provisions of

3-37  this chapter.

3-38    3.  A contractor [within the meaning of this chapter] includes a

3-39  subcontractor or specialty contractor, but does not include anyone who

3-40  merely furnishes materials or supplies without fabricating them into, or

3-41  consuming them in the performance of, the work of a contractor.

3-42    4.  A contractor [within the meaning of this chapter] includes a

3-43  construction manager who performs management and counseling services

3-44  on a construction project for a professional fee.

3-45    Sec. 3.  NRS 624.610 is hereby amended to read as follows:

3-46    624.610  1.  [If, through no fault or act of a prime contractor or

3-47  anyone employed by him,] Except as otherwise provided in subsection 9,

3-48  if an owner of real property enters into a written or oral contract with a


4-1  contractor for the performance of work by the contractor and the owner

4-2  [fails] :

4-3    (a) Fails to pay that contractor[:

4-4    (a) Pursuant to their] on or before the date a payment is due pursuant

4-5  to a schedule for payments [under the contract, or within a reasonable time

4-6  after maturity and presentation of charges if] established in a written

4-7  contract; or

4-8    (b) If no such schedule is established[;

4-9    (b) Any sum certified by the architect, engineer or other supervisory

4-10  agent of the owner; or

4-11    (c) Such sum as is otherwise properly due,

4-12  or if the] or if the contract is oral, and if the contractor has performed

4-13  under the contract, fails to pay the contractor within 15 days after the

4-14  date the contractor submits a request for payment,

4-15  the contractor may stop work after giving written notice to the owner at

4-16  least 5 working days before stopping work. If a contractor stops work

4-17  pursuant to this subsection, the contractor may terminate the contract by

4-18  giving written notice of termination to the owner.

4-19    2.  If the owner throughhis own act or neglect, or through the act or

4-20  neglect of his agent, excluding acts of God, floods, fires or strikes, causes

4-21  the work to be stopped for a period of 5 working days or more, the

4-22  contractor may[, after 5 working days’] terminate the contract if:

4-23    (a) The contractor gives written notice of his intent to terminate to the

4-24  owner[, stop work or terminate the contract and] at least 5 working days

4-25  before terminating the contract; and

4-26    (b) The owner fails to allow work to resume within 5 working days

4-27  after receiving notice pursuant to paragraph (a).

4-28    3.  If a contractor terminates a contract pursuant to subsection 1 or 2,

4-29  the contractor may recover from the owner payment [for] in an amount

4-30  found by a trier of fact to be due the contractor, plus 2 percent of that

4-31  amount, including, without limitation:

4-32    (a) The cost of all work [executed.

4-33    2.  If, through no fault of a subcontractor or anyone employed by him,

4-34  the contractor fails to pay that subcontractor:

4-35    (a) Pursuant to the schedule for payments under the subcontract, or

4-36  within a reasonable time after maturity and presentation of charges if no

4-37  schedule is established;

4-38    (b) Any sum certified by the architect, engineer or other supervisory

4-39  agent of the owner or contractor; or

4-40    (c) Such sum as is otherwise properly due,

4-41  or if the contractor through his own acts or neglect, excluding acts of God,

4-42  floods, fires or strikes, causes the work to be stopped for a period of 5

4-43  working days or more, the subcontractor may, after 5 working days’

4-44  written notice to the owner and the contractor, stop work or terminate the

4-45  subcontract and recover from the contractor payment for all work executed.

4-46  The subcontractor may not be held liable for nonperformance of that

4-47  subcontract and for the cost incurred by the contractor to complete the

4-48  work.


5-1    3.  The provisions of subsection 2 do not apply if the contractor’s

5-2  failure to pay is caused by his need to withhold money pursuant to an

5-3  official notice from a state agency that he is liable to make payments or

5-4  contributions for the subcontractor pursuant to chapter 608 or 612 or

5-5  chapters 616A to 616D, inclusive, or chapter 617 of NRS.] , labor,

5-6  materials, equipment and services furnished by the contractor;

5-7    (b) The profit and overhead that the contractor would have received if

5-8  the contract had been performed in full;

5-9    (c) Interest at the rate agreed upon in the contract, or if no interest

5-10  rate is so provided, then interest at a rate equal to the prime rate at the

5-11  largest bank in this state, as determined by the commissioner of financial

5-12  institutions on January 1 or July 1, as the case may be, immediately

5-13  preceding:

5-14      (1) The time the contract was signed; or

5-15      (2) If the contract was oral, the time the terms of the contract were

5-16  agreed to by the parties; and

5-17    (d) The attorneys’ fees and costs incurred by the contractor in

5-18  collecting the amount due.

5-19    4.  A contractor shall provide a copy of any notice given to an owner

5-20  pursuant to subsection 1 or 2 to each subcontractor with whom the

5-21  contractor has contracted who has not fully performed under that

5-22  contract. Upon receipt of payment pursuant to this section, the contractor

5-23  shall notify all such subcontractors in writing of his receipt of payment.

5-24    5.  If a contractor stops work pursuant to subsection 1, each such

5-25  subcontractor may also stop work on the project. If a contractor

5-26  terminates a contract pursuant to this section, all such subcontractors

5-27  may terminate their contracts with the contractor.

5-28    6.  The right of a contractor to stop work or terminate a contract

5-29  pursuant to this section is in addition to all other rights that the

5-30  contractor may have at law or in equity.

5-31    7.  No contractor or his subcontractors, or their respective sureties,

5-32  may be held liable for any delays or damages that an owner may suffer

5-33  as a result of the contractor stopping his work or terminating a contract

5-34  in accordance with this section.

5-35    8.  A condition, stipulation or provision in a contract or other

5-36  agreement which requires a contractor to waive any rights provided in

5-37  this section or which limits those rights is void.

5-38    9.  All notices required pursuant to this section must be:

5-39    (a) Delivered personally;

5-40    (b) Sent by facsimile and delivered by regular mail; or

5-41    (c) Delivered by certified mail.

5-42    10.  This section does not apply to a contract between a residential

5-43  contractor and a natural person who owns a single family residence for

5-44  the performance of qualified services with respect to the residence.

5-45    Sec. 4.  This act becomes effective on July 1, 2001.

 

5-46  H