(REPRINTED WITH ADOPTED AMENDMENTS)

                                                  SECOND REPRINT                                                                  S.B. 274

 

Senate Bill No. 274–Committee on Commerce and Labor

 

March 5, 2001

____________

 

Referred to Committee on Commerce and Labor

 

SUMMARY—Revises provisions governing rights and duties of contractors and subcontractors under contracts or subcontracts. (BDR 54‑593)

 

FISCAL NOTE:  Effect on Local Government: No.

                             Effect on the State: No.

 

~

 

EXPLANATION – Matter in bolded italics is new; matter between brackets [omitted material] is material to be omitted.

Green numbers along left margin indicate location on the printed bill (e.g., 5-15 indicates page 5, line 15).

 

AN ACT relating to contractors; revising the provisions governing the rights and duties of contractors and subcontractors under contracts and subcontracts; and providing other matters properly relating thereto.

 

THE PEOPLE OF THE STATE OF NEVADA, REPRESENTED IN

SENATE AND ASSEMBLY, DO ENACT AS FOLLOWS:

 

1-1    Section 1. Chapter 624 of NRS is hereby amended by adding thereto

1-2  the provisions set forth as sections 2 to 9, inclusive, of this act.

1-3    Sec. 2.  As used in NRS 624.610, 624.620 and 624.630 and sections 2

1-4  to 9, inclusive, of this act, the words and terms defined in sections 3 and

1-5  4 of this act have the meanings ascribed to them in those sections.

1-6    Sec. 3.  “Higher-tiered subcontractor” means a subcontractor under

1-7  a contract who has entered into an oral or written subcontract with

1-8  another subcontractor pursuant to which the other subcontractor has

1-9  agreed to perform any of the duties of the subcontractor under the oral

1-10  or written subcontract.

1-11    Sec. 4.  “Lower-tiered subcontractor” means a subcontractor who

1-12  has agreed in an oral or written contract to perform any of the duties of

1-13  another subcontractor under another oral or written subcontract.

1-14  Sec. 5.  1.  Except as otherwise provided in this section, if a

1-15  contractor or higher-tiered subcontractor enters into:

1-16  (a) A written subcontract with a subcontractor that includes a

1-17  schedule for payments, the contractor or higher-tiered subcontractor

1-18  shall pay the subcontractor:

1-19      (1) On or before the date payment is due; or

 

 

 


2-1       (2) Within 10 days after the date the contractor or higher-tiered

2-2  subcontractor receives payment for all or a portion of the work, labor,

2-3  materials, equipment or services described in a request for payment

2-4  submitted by the subcontractor,

2-5  whichever is earlier.

2-6    (b) A written subcontract that does not contain a schedule for

2-7  payments, or a subcontract that is oral, the contractor or higher-tiered

2-8  subcontractor shall pay the subcontractor:

2-9       (1) Within 30 days after the date the subcontractor submits a

2-10  request for payment; or

2-11      (2) Within 10 days after the date the contractor or higher-tiered

2-12  subcontractor receives payment for all or a portion of the work, labor,

2-13  materials, equipment or services described in a request for payment

2-14  submitted by the subcontractor,

2-15  whichever is earlier.

2-16    2.  If a contractor or higher-tiered subcontractor has complied with

2-17  subsection 3, the contractor or higher-tiered subcontractor may:

2-18    (a) Withhold from any payment owed to the subcontractor:

2-19      (1) A retention amount that the subcontractor is authorized to

2-20  withhold pursuant to the contract;

2-21      (2) An amount equal to the sum of the value of:

2-22         (I) Any work or labor that has not been performed or materials

2-23  or equipment that has not been furnished for which payment is being

2-24  sought; and

2-25         (II) Costs and expenses reasonably necessary to correct or repair

2-26  any work which is the subject of the request for payment and which is

2-27  not materially in compliance with the subcontract to the extent that such

2-28  costs and expenses exceed 50 percent of the amount withheld pursuant to

2-29  subparagraph (1); and

2-30      (3) The amount the owner, contractor or higher-tiered

2-31  subcontractor has paid or is required to pay pursuant to an official notice

2-32  from a state agency or employee benefit trust fund, for which the owner,

2-33  contractor or higher-tiered subcontractor is or may reasonably be liable

2-34  for the subcontractor or his subcontractors in accordance with chapter

2-35  608, 612, 616A to 616D, inclusive, or 617 of NRS; and

2-36    (b) Require as a condition precedent to the payment of any amount

2-37  due, lien releases furnished by the subcontractor and his lower-tiered

2-38  subcontractors and suppliers. For purposes of this paragraph:

2-39      (1) If the amount due is paid with a check or is not paid

2-40  concurrently with the contractor’s or higher-tiered subcontractor’s

2-41  receipt of the lien releases, the lien releases must be conditioned upon the

2-42  check clearing the bank upon which it is drawn and the receipt of

2-43  payment and shall be deemed to become unconditional upon the receipt

2-44  of payment; and

2-45      (2) The lien releases must be limited to the amount of the payment

2-46  received.

2-47    3.  If, pursuant to subparagraph (2) or (3) of paragraph (a) of

2-48  subsection 2 or paragraph (b) of subsection 2, a contractor or higher-

2-49  tiered subcontractor intends to withhold any amount from a payment to


3-1  be made to a subcontractor, the contractor or higher-tiered subcontractor

3-2  must give, on or before the date the payment is due, a written notice to

3-3  the subcontractor of any amount that will be withheld and give a copy of

3-4  such notice to all reputed higher-tiered subcontractors, contractors and

3-5  the owner. The written notice must:

3-6    (a) Identify the amount of the request for payment that will be

3-7  withheld from the subcontractor;

3-8    (b) Give a reasonably detailed explanation of the reason the

3-9  contractor or higher-tiered subcontractor will withhold that amount,

3-10  including, without limitation, a specific reference to the provision or

3-11  section of the subcontract, and any documents relating thereto, and the

3-12  applicable building code, law or regulation with which the subcontractor

3-13  has failed to comply; and

3-14    (c) Be signed by an authorized agent of the contractor or higher-tiered

3-15  subcontractor.

3-16    4.  A subcontractor who receives a notice pursuant to subsection 3

3-17  may provide written notice to the contractor or higher-tiered

3-18  subcontractor of the correction of a condition described in the notice

3-19  received pursuant to subsection 3. The notice of correction must be

3-20  sufficient to identify the scope and manner of the correction of the

3-21  condition and be signed by an authorized representative of the

3-22  subcontractor. If a contractor or higher-tiered subcontractor receives a

3-23  written notice from the subcontractor of the correction of a condition

3-24  pursuant to this subsection, the contractor or higher-tiered subcontractor

3-25  must:

3-26    (a) Pay the amount withheld by the contractor or higher-tiered

3-27  subcontractor for that condition on or before the date the next payment is

3-28  due the subcontractor; or

3-29    (b) Object to the scope and manner of the correction of the condition,

3-30  on or before the date the next payment is due to the subcontractor, in a

3-31  written statement which sets forth the reason for the objection and which

3-32  complies with subsection 3. If the contractor or higher-tiered

3-33  subcontractor objects to the scope and manner of the correction of a

3-34  condition, he shall nevertheless pay to the subcontractor, along with

3-35  payment made pursuant to the subcontractor’s next payment request, the

3-36  amount withheld for the correction of conditions to which the contractor

3-37  or higher-tiered subcontractor no longer objects.

3-38    Sec. 6.  1.  If a contractor or higher-tiered subcontractor fails to:

3-39    (a) Pay the subcontractor within the time provided in subsection 1 or 4

3-40  of section 5 of this act;

3-41    (b) Pay the subcontractor within 45 days after the 25th day of the

3-42  month in which the subcontractor submits a request for payment, even if

3-43  the contractor or higher-tiered subcontractor has not been paid and the

3-44  subcontract contains a provision which requires the contractor or

3-45  higher-tiered subcontractor to pay the subcontractor only if or when the

3-46  contractor or higher-tiered subcontractor is paid; or

3-47    (c) Give the subcontractor written notice of any withholding in the

3-48  time and manner required by subsection 3 or 4 of section 5 of this

3-49  act,


4-1  the subcontractor may stop work under the subcontract until payment is

4-2  received if the subcontractor gives written notice to the contractor or

4-3  higher-tiered subcontractor at least 10 days before stopping work.

4-4    2.  If a subcontractor stops work pursuant to paragraph (a) or (c) of

4-5  subsection 1, the subcontractor may terminate the subcontract by giving

4-6  written notice of the termination to the contractor or higher-tiered

4-7  subcontractor after stopping work but at least 15 days before the

4-8  termination of the subcontract. If the subcontractor is paid the amount

4-9  due before the date for termination set forth in the written notice, the

4-10  subcontractor shall not terminate the subcontract and shall resume work.

4-11    3.  If an owner, contractor or a higher-tiered subcontractor through

4-12  his own act or neglect, or through an act or neglect of his agent,

4-13  excluding acts of God, floods, fires, labor disputes, strikes or reasonable

4-14  adjustments in work schedules, causes the work to be stopped for a

4-15  period of 15 days or more, the subcontractor may terminate the

4-16  subcontract if:

4-17    (a) The subcontractor gives written notice of his intent to terminate to

4-18  the contractor or higher-tiered subcontractor at least 10 days before

4-19  terminating the subcontract; and

4-20    (b) The contractor or higher-tiered subcontractor fails to allow the

4-21  subcontractor to resume the work within the time set forth in the written

4-22  notice given pursuant to paragraph (a).

4-23    4.  If a subcontractor stops work pursuant to paragraph (a) or (c) of

4-24  subsection 1, the contractor or higher-tiered subcontractor may

4-25  terminate the subcontract by giving the subcontractor written notice of

4-26  his intent to terminate at least 15 days before terminating the

4-27  subcontract.

4-28    5.  If the subcontract is terminated pursuant to subsection 3, or if the

4-29  subcontractor stops work in accordance with this section and the

4-30  subcontract is terminated pursuant to subsection 2 or 4, the

4-31  subcontractor is entitled to recover from the contractor or higher-tiered

4-32  subcontractor with whom he has contracted the amount found by a trier

4-33  of fact to be due the subcontractor, including, without limitation:

4-34    (a) The cost of all work, labor, materials, equipment and services

4-35  furnished by and through the subcontractor, including any profit and

4-36  overhead the subcontractor incurred or earned through the date of

4-37  termination;

4-38    (b) The profit that the subcontractor and his lower-tiered

4-39  subcontractors would have received if the subcontract had been

4-40  performed in full;

4-41    (c) Interest at a rate equal to the rate agreed upon in the subcontract,

4-42  or, if no interest rate is so provided, interest at a rate equal to the prime

4-43  rate at the largest bank in this state, as determined by the commissioner

4-44  of financial institutions on January 1 or July 1, as the case may be,

4-45  immediately preceding:

4-46      (1) The time the subcontract was signed; or

4-47      (2) If the subcontract was oral, the time the terms of the

4-48  subcontract were agreed upon by the parties,

4-49  plus 2 percent; and


5-1    (d) The reasonable costs, including court costs, incurred by the

5-2  subcontractor and his lower-tiered subcontractors in collecting the

5-3  amount due.

5-4  At any action brought to enforce the rights or obligations set forth in this

5-5  subsection, the trier of fact may award reasonable attorney’s fees to the

5-6  subcontractor or, if the trier of fact determines that the subcontractor

5-7  stopped work or terminated the contract without reasonable cause, the

5-8  trier of fact may award reasonable attorney’s fees to the contractor or

5-9  higher-tiered subcontractor.

5-10    6.  If a subcontractor stops work pursuant to this section, each lower-

5-11  tiered subcontractor with whom the subcontractor has contracted who

5-12  has not fully performed under the contract may also stop work on the

5-13  project. If a subcontractor terminates a subcontract pursuant to this

5-14  section, all such lower-tiered subcontractors may terminate their

5-15  contracts with the subcontractor.

5-16    7.  The right of a subcontractor to stop work or terminate a

5-17  subcontract pursuant to this section is in addition to all other rights that

5-18  the subcontractor may have at law or in equity and does not impair or

5-19  affect the right of a subcontractor to maintain a civil action or to submit

5-20  any controversy arising under the contract to arbitration.

5-21    8.  No subcontractor or his lower-tiered subcontractors, or their

5-22  respective sureties, may be held liable for any delays or damages that an

5-23  owner, contractor or higher-tiered subcontractor may suffer as a result

5-24  of the subcontractor or lower-tiered subcontractor stopping his work or

5-25  terminating a subcontract for reasonable cause and in accordance with

5-26  this section.

5-27    Sec. 7.  1.  A subcontractor shall provide a copy of any notice given

5-28  to a contractor or higher-tiered subcontractor pursuant to this section or

5-29  section 5 or 6 of this act to each lower-tiered subcontractor with whom

5-30  the subcontractor has contracted who has not fully performed under the

5-31  contract. Upon receipt of payment pursuant to section 5 of this act, the

5-32  subcontractor shall notify all such lower-tiered subcontractors in writing

5-33  of his receipt of payment.

5-34    2.  A subcontractor shall provide a copy of any notice given to a

5-35  contractor or higher-tiered subcontractor pursuant to this section or

5-36  section 5 or 6 of this act to each reputed higher-tiered subcontractor,

5-37  contractor and the owner, if known. The failure of a subcontractor to

5-38  comply with this subsection does not invalidate any notice otherwise

5-39  properly given.

5-40    3.  A condition, stipulation or provision in a subcontract or other

5-41  agreement which requires a subcontractor to waive any rights provided

5-42  in this section or section 5 or 6 of this act, or which limits those rights, is

5-43  void.

5-44    4.  All notices required pursuant to this section or section 5 or 6 of

5-45  this act must be:

5-46    (a) Delivered personally, in which case the subcontractor shall obtain

5-47  a notarized statement from the person who delivered the notice as proof

5-48  of delivery;


6-1    (b) Sent by facsimile and delivered by regular mail, in which case the

6-2  subcontractor shall retain proof of a successful transmission of the

6-3  facsimile;

6-4    (c) Delivered by certified mail; or

6-5    (d) Delivered in the manner provided in the contract.

6-6    5.  Within 5 days after a contractor receives a written request for the

6-7  information set forth in paragraphs (a), (b) and (c) from a subcontractor

6-8  with respect to a subcontract that has not been fully performed, the

6-9  contractor shall notify the subcontractor in writing of the following:

6-10    (a) The date the contractor made a specified payment to his

6-11  subcontractor;

6-12    (b) Whether the contractor has paid his subcontractor the entire

6-13  amount of a specified payment; and

6-14    (c) The amount withheld by the contractor of a specified payment to

6-15  his subcontractor and the reason for the withholding.

6-16    Sec. 8.  1.  Except as otherwise provided in subsections 2 and 4 and

6-17  subsection 4 of section 9 of this act, if an owner of real property enters

6-18  into a written or oral contract with a contractor for the performance of

6-19  work by the contractor, the owner must:

6-20    (a) Pay that contractor on or before the date a payment is due

6-21  pursuant to a schedule for payments established in a written contract; or

6-22    (b) If no such schedule is established or if the contract is oral, pay the

6-23  contractor within 21 days after the date the contractor submits a request

6-24  for payment.

6-25    2.  If an owner has complied with subsection 3, the owner may:

6-26    (a) Withhold from any payment to be made to the contractor:

6-27      (1) A retention amount that the owner is authorized to withhold

6-28  pursuant to the contract;

6-29      (2) An amount equal to the sum of the value of:

6-30         (I) Any work or labor that has not been performed or materials

6-31  or equipment that has not been furnished for which payment is being

6-32  sought; and

6-33         (II) Costs and expenses reasonably necessary to correct or repair

6-34  any work which is the subject of the request for payment and which is

6-35  not materially in compliance with the contract to the extent that such

6-36  costs and expenses exceed 50 percent of the amount withheld pursuant to

6-37  subparagraph (1); and

6-38      (3) The amount the owner has paid or is required to pay pursuant

6-39  to an official notice from a state agency or employee benefit trust fund,

6-40  for which the owner is or may reasonably be liable for the contractor or

6-41  his subcontractors in accordance with chapter 608, 612, 616A to 616D,

6-42  inclusive, or chapter 617 of NRS; and

6-43    (b) Require as a condition precedent to the payment of any amount

6-44  due, lien releases furnished by the contractor and his subcontractors and

6-45  suppliers. For purposes of this paragraph:

6-46      (1) If the amount due is paid with a check or is not paid

6-47  concurrently with the owner’s receipt of the lien releases, the lien

6-48  releases must be conditioned upon the check clearing the bank upon


7-1  which it is drawn and the receipt of payment and shall be deemed to

7-2  become unconditional upon the receipt of payment; and

7-3       (2) The lien releases must be limited to the amount of the payment

7-4  received.

7-5    3.  If, pursuant to subparagraph (2) or (3) of paragraph (a) of

7-6  subsection 2 or paragraph (b) of subsection 2, an owner intends to

7-7  withhold any amount from a payment to be made to a contractor, the

7-8  owner must give, on or before the date the payment is due, a written

7-9  notice to the contractor of any amount that will be withheld. The written

7-10  notice must:

7-11    (a) Identify the amount of the request for payment that will be

7-12  withheld from the contractor;

7-13    (b) Give a reasonably detailed explanation of the reason the owner

7-14  will withhold that amount, including, without limitation, a specific

7-15  reference to the provision or section of the contract, and any documents

7-16  relating thereto, and the applicable building code, law or regulation with

7-17  which the contractor has failed to comply; and

7-18    (c) Be signed by an authorized agent of the owner.

7-19    4.  A contractor who receives a notice pursuant to subsection 3 may

7-20  provide written notice to the owner of the correction of a condition

7-21  described in the notice received pursuant to subsection 3. The notice of

7-22  correction must be sufficient to identify the scope and manner of the

7-23  correction of the condition and be signed by an authorized representative

7-24  of the contractor. If an owner receives a written notice from the

7-25  contractor of the correction of a condition pursuant to this subsection,

7-26  the owner must:

7-27    (a) Pay the amount withheld by the owner for that condition on or

7-28  before the date the next payment is due the contractor; or

7-29    (b) Object to the scope and manner of the correction of the condition,

7-30  on or before the date the next payment is due to the contractor, in a

7-31  written statement which sets forth the reason for the objection and which

7-32  complies with subsection 3. If the owner objects to the scope and manner

7-33  of the correction of a condition, he shall nevertheless pay to the

7-34  contractor, along with payment made pursuant to the contractor’s next

7-35  payment request, the amount withheld for the correction of conditions to

7-36  which the owner no longer objects.

7-37    Sec. 9.  1.  A contractor shall provide a copy of any notice given to

7-38  an owner pursuant to subsection 1 or 2 of NRS 624.610 to each

7-39  subcontractor with whom the contractor has contracted who has not fully

7-40  performed under that contract. Upon receipt of payment pursuant to

7-41  section 8 of this act, the contractor shall notify all such subcontractors in

7-42  writing of his receipt of payment.

7-43    2.  A condition, stipulation or provision in a contract or other

7-44  agreement which requires a contractor to waive any rights provided in

7-45  this section, NRS 624.610 or section 8 of this act or which limits those

7-46  rights is void.

7-47    3.  All notices required pursuant to this section, NRS 624.610 and

7-48  section 8 of this act must be:


8-1    (a) Delivered personally, in which case the contractor shall obtain a

8-2  notarized statement from the person who delivered the notice as proof of

8-3  delivery;

8-4    (b) Sent by facsimile and delivered by regular mail, in which case the

8-5  contractor shall retain proof of a successful transmission of the

8-6  facsimile;

8-7    (c) Delivered by certified mail; or

8-8    (d) Delivered in the manner provided for in the contract.

8-9    4.  This section, NRS 624.610 and section 8 of this act do not apply to

8-10  a contract between:

8-11    (a) A residential contractor and a natural person who owns a single-

8-12  family residence for the performance of qualified services with respect to

8-13  the residence; and

8-14    (b) A public body and a contractor for the performance of work and

8-15  labor on a public work.

8-16    5.  Within 5 days after an owner receives a written request for the

8-17  information set forth in paragraphs (a), (b) and (c) from a subcontractor

8-18  with respect to a subcontract that has not been fully performed, the

8-19  owner shall notify the subcontractor in writing of the following:

8-20    (a) The date the owner made a specified payment to his contractor;

8-21    (b) Whether the owner has paid the entire amount of a specified

8-22  payment to his contractor; and

8-23    (c) The amount withheld by the owner from a specified payment to the

8-24  contractor and the reason for the withholding.

8-25    Sec. 10.  NRS 624.020 is hereby amended to read as follows:

8-26    624.020  [1.  For the purpose of this chapter, “contractor”] For the

8-27  purposes of this chapter, unless the context otherwise requires:

8-28    1.  “Contractor” is synonymous with “builder.”

8-29    2.  [Within the meaning of this chapter, a] A contractor is any person,

8-30  except a registered architect or a licensed professional engineer, acting

8-31  solely in his professional capacity, who in any capacity other than as the

8-32  employee of another with wages as the sole compensation, undertakes to,

8-33  [or] offers to undertake to, [or] purports to have the capacity to undertake

8-34  to, or submits a bid to, or does himself or by or through others, construct,

8-35  alter, repair, add to, subtract from, improve, move, wreck or demolish any

8-36  building, highway, road, railroad, excavation or other structure, project,

8-37  development or improvement, or to do any part thereof, including the

8-38  erection of scaffolding or other structures or works in connection

8-39  therewith. Evidence of the securing of any permit from a governmental

8-40  agency or the employment of any person on a construction project must be

8-41  accepted by the board or any court of this state as prima facie evidence that

8-42  the person securing that permit or employing any person on a construction

8-43  project is acting in the capacity of a contractor pursuant to the provisions of

8-44  this chapter.

8-45    3.  A contractor [within the meaning of this chapter] includes a

8-46  subcontractor or specialty contractor, but does not include anyone who

8-47  merely furnishes materials or supplies without fabricating them into, or

8-48  consuming them in the performance of, the work of a contractor.


9-1    4.  A contractor [within the meaning of this chapter] includes a

9-2  construction manager who performs management and counseling services

9-3  on a construction project for a professional fee.

9-4    Sec. 11.  NRS 624.610 is hereby amended to read as follows:

9-5    624.610  1.  If [, through no fault or act of a prime contractor or

9-6  anyone employed by him, the] an owner fails to [pay that contractor:

9-7    (a) Pursuant to their schedule for payments under the contract, or within

9-8  a reasonable time after maturity and presentation of charges if no schedule

9-9  is established;

9-10    (b) Any sum certified by the architect, engineer or other supervisory

9-11  agent of the owner; or

9-12    (c) Such sum as is otherwise properly due, or if] :

9-13    (a) Pay the contractor in the time and manner required by subsection

9-14  1 or 4 of section 8 of this act; or

9-15    (b) Give the contractor written notice of any withholding in the time

9-16  and manner required by subsection 3 or 4 of section 8 of this

9-17  act,

9-18  the contractor may stop work after giving written notice to the owner at

9-19  least 10 days before stopping work. If a contractor stops work pursuant to

9-20  this subsection, the contractor may terminate the contract by giving

9-21  written notice of termination to the owner after stopping work but at least

9-22  15 days before terminating the contract. If the contractor is paid the

9-23  amount due before the date for termination of the contract set forth in

9-24  the written notice, the contractor shall not terminate the contract and

9-25  shall resume his work.

9-26    2.  If theowner throughhis own act or neglect, or through an act or

9-27  neglect of his agent, excluding acts of God, floods, fires [or strikes,] ,

9-28  labor disputes, strikes or reasonable adjustments to work schedules,

9-29  causes the work to be stopped for a period of [5 working] 15 days or more,

9-30  the contractor may[, after 5 working days’] terminate the contract if:

9-31    (a) The contractor gives written notice of his intent to terminate to the

9-32  owner[, stop work or terminate the contract and] at least 10 days before

9-33  terminating the contract; and

9-34    (b) The owner fails to allow work to resume within the time set forth

9-35  in the written notice given pursuant to paragraph (a).

9-36    3.  If a contractor stops work pursuant to subsection 1, the owner may

9-37  terminate the contract by giving the contractor written notice of his intent

9-38  to terminate at least 15 days before terminating the contract.

9-39    4.  If the contract is terminated pursuant to subsection 2, or if the

9-40  contractor stops work in accordance with this section and the contract is

9-41  terminated pursuant to subsection 1 or 3, the contractor is entitled to

9-42  recover from the owner payment [for] in an amount found by a trier of

9-43  fact to be due the contractor, including, without limitation:

9-44    (a) The cost of all work [executed.

9-45    2.  If, through no fault of a subcontractor or anyone employed by him,

9-46  the contractor fails to pay that subcontractor:

9-47    (a) Pursuant to the schedule for payments under the subcontract, or

9-48  within a reasonable time after maturity and presentation of charges if no

9-49  schedule is established;


10-1    (b) Any sum certified by the architect, engineer or other supervisory

10-2  agent of the owner or contractor; or

10-3    (c) Such sum as is otherwise properly due,

10-4  or if the contractor through his own acts or neglect, excluding acts of God,

10-5  floods, fires or strikes, causes the work to be stopped for a period of 5

10-6  working days or more, the subcontractor may, after 5 working days’

10-7  written notice to the owner and the contractor, stop work or terminate the

10-8  subcontract and recover from the contractor payment for all work executed.

10-9  The subcontractor may not be held liable for nonperformance of that

10-10  subcontract and for the cost incurred by the contractor to complete the

10-11  work.

10-12  3.  The provisions of subsection 2 do not apply if the contractor’s

10-13  failure to pay is caused by his need to withhold money pursuant to an

10-14  official notice from a state agency that he is liable to make payments or

10-15  contributions for the subcontractor pursuant to chapter 608 or 612 or

10-16  chapters 616A to 616D, inclusive, or chapter 617 of NRS.] , labor,

10-17  materials, equipment and services furnished by and through the

10-18  contractor, including any profit and overhead the contractor incurred or

10-19  earned through the date of termination;

10-20  (b) The profit that the contractor and his subcontractors would have

10-21  received if the contract had been performed in full;

10-22  (c) Interest at a rate equal to the rate agreed upon in the contract, or if

10-23  no interest rate is so provided, then interest at a rate equal to the prime

10-24  rate at the largest bank in this state, as determined by the commissioner

10-25  of financial institutions on January 1 or July 1, as the case may be,

10-26  immediately preceding:

10-27     (1) The time the contract was signed; or

10-28     (2) If the contract was oral, the time the terms of the contract were

10-29  agreed to by the parties,

10-30  plus 2 percent; and

10-31  (d) The reasonable costs, including court costs, incurred by the

10-32  contractor and his subcontractors in collecting the amount

10-33  due.

10-34  At any action brought to enforce the rights or obligations set forth in this

10-35  subsection, the trier of fact may award reasonable attorney’s fees to the

10-36  contractor or, if the trier of fact determines that the contractor stopped

10-37  work or terminated the contract without reasonable cause, the trier of

10-38  fact may award reasonable attorney’s fees to the owner.

10-39  5.  If a contractor stops work pursuant to subsection 1, each

10-40  subcontractor with whom the contractor has contracted who has not fully

10-41  performed under that contract may also stop work on the project. If a

10-42  contractor terminates a contract pursuant to this section, all such

10-43  subcontractors may terminate their contracts with the contractor.

10-44  6.  The right of a contractor to stop work or terminate a contract

10-45  pursuant to this section is in addition to all other rights that the

10-46  contractor may have at law or in equity and does not impair or affect the

10-47  right of a contractor to maintain a civil action or to submit any

10-48  controversy arising under the contract to arbitration.


11-1    7.  No contractor or his subcontractors, or their respective sureties,

11-2  may be held liable for any delays or damages that an owner may suffer

11-3  as a result of the contractor, subcontractor or lower-tiered subcontractor

11-4  stopping his work or terminating a contract for reasonable cause and in

11-5  accordance with this section or section 6 of this act.

11-6    Sec. 12.  NRS 624.620 is hereby amended to read as follows:

11-7    624.620  1.  Except as otherwise provided in [subsections 2, 3 and 5,]

11-8  this section, any money remaining unpaid for the construction [or

11-9  remodeling of a building] of a work of improvement is payable to the

11-10  contractor within 30 days after:

11-11  (a) Occupancy or use of the work of improvement by the owner or by a

11-12  person acting with the authority of the owner; or

11-13  (b) The availability of a [constructed or remodeled building] work of

11-14  improvement for its intended use. The contractor must have given a written

11-15  notice of availability to the owner on or before the day on which he claims

11-16  that the [building became available.

11-17  2.  The] work of improvement became available for use or occupancy.

11-18  2.  If the owner has complied with subsection 3, the owner may:

11-19  (a) Withhold payment for the amount of [any disputed or uncompleted

11-20  items if he notifies the contractor in writing at the time of withholding as to

11-21  any disputed items.] :

11-22     (1) Any work or labor that has not been performed or materials or

11-23  equipment that has not been furnished for which payment is sought;

11-24     (2) The costs and expenses reasonably necessary to correct or

11-25  repair any work that is not materially in compliance with the contract to

11-26  the extent that such costs and expenses exceed 50 percent of the amount

11-27  of retention being withheld pursuant to the terms of the contract; and

11-28     (3) Money the owner has paid or is required to pay pursuant to an

11-29  official notice from a state agency, or employee benefit trust fund, for

11-30  which the owner is liable for the contractor or his subcontractors in

11-31  accordance with chapter 608, 612, 616A to 616D, inclusive, or chapter

11-32  617 of NRS.

11-33  (b) Require, as a condition precedent to the payment of any [money]

11-34  unpaid amount under the construction contract, that [waivers of] lien

11-35  releases be furnished by the contractor’s subcontractors, suppliers or

11-36  employees. For purposes of this paragraph:

11-37     (1) If the amount due is paid with a check or is not paid

11-38  concurrently with the owner’s receipt of the lien releases, the lien

11-39  releases must be conditioned upon the check clearing the bank upon

11-40  which it is drawn and the receipt of payment and shall be deemed to

11-41  become unconditional upon the receipt of payment; and

11-42     (2) The lien releases must be limited to the amount of the payment

11-43  received.

11-44  3.  If pursuant to paragraph (a) of subsection 2, an owner intends to

11-45  withhold any amount from a payment to be made to a contractor, the

11-46  owner must, on or before the date the payment is due, give written notice

11-47  to the contractor of any amount that will be withheld. The written notice

11-48  must:

11-49  (a) Identify the amount that will be withheld from the contractor;


12-1    (b) Give a reasonably detailed explanation of the reason the owner

12-2  will withhold that amount, including, without limitation, a specific

12-3  reference to the provision or section of the contract, and any documents

12-4  relating thereto, and the applicable building code, law or regulation with

12-5  which the contractor has failed to comply; and

12-6    (c) Be signed by an authorized agent of the owner.

12-7    4.  A contractor who receives a notice pursuant to subsection 3 may

12-8  provide written notice to the owner of the correction of a condition

12-9  described in the notice received pursuant to subsection 3. The notice of

12-10  correction must be sufficient to identify the scope and manner of the

12-11  correction of the condition and be signed by an authorized representative

12-12  of the contractor. If an owner receives a written notice from the

12-13  contractor of the correction of a condition described in an owner’s notice

12-14  of withholding pursuant to subsection 3, the owner must, within 10 days

12-15  after receipt of such notice:

12-16  (a) Pay the amount withheld by the owner for that condition; or

12-17  (b) Object to the scope and manner of the correction of the condition

12-18  in a written statement that sets forth the reason for the objection and

12-19  complies with subsection 3. If the owner objects to the scope and manner

12-20  of the correction of a condition, he shall nevertheless pay to the

12-21  contractor, along with payment made pursuant to the contractor’s next

12-22  payment request, the amount withheld for the correction of conditions to

12-23  which the owner no longer objects.

12-24  5.  The partial occupancy or availability of a building requires payment

12-25  in direct proportion to the value of the part of the building which is

12-26  partially occupied or partially available. For projects which involve more

12-27  than one building, each building must be considered separately in

12-28  determining the amount of money which is payable to the contractor.

12-29  [4.] 6. Unless otherwise provided in the construction contract, any

12-30  money which is payable to a contractor pursuant to this section accrues

12-31  interest at a rate equal to the lowest daily prime rate at the [three largest

12-32  United States banking institutions on the date the contract is executed plus]

12-33  largest bank in this state, as determined by the commissioner of financial

12-34  institutions on January 1 or July 1, as the case may be, immediately

12-35  preceding:

12-36  (a) The time the contract was signed; or

12-37  (b) If the contract was oral, the time the terms of the contract were

12-38  agreed to by the parties,

12-39  plus 2 percent . [,from 30 days after the date on which the money became

12-40  payable until the date of payment.

12-41  5.] 7. This section does not apply to:

12-42  (a) Any residential building; or

12-43  (b) Public works.

12-44  8.  As used in this section, unless the context otherwise requires,

12-45  “work of improvement” has the meaning ascribed to it in NRS 108.221.

12-46  Sec. 13.  NRS 99.040 is hereby amended to read as follows:

12-47  99.040  1.  When there is no express contract in writing fixing a

12-48  different rate of interest, interest must be allowed at a rate equal to the

12-49  prime rate at the largest bank in Nevada, as ascertained by the


13-1  commissioner of financial institutions, on January 1 or July 1, as the case

13-2  may be, immediately preceding the date of the transaction, plus 2 percent,

13-3  upon all money from the time it becomes due, in the following cases:

13-4  (a) Upon contracts, express or implied, other than book accounts.

13-5  (b) Upon the settlement of book or store accounts from the day on

13-6  which the balance is ascertained.

13-7  (c) Upon money received to the use and benefit of another and detained

13-8  without his consent.

13-9  (d) Upon wages or salary, if it is unpaid when due, after demand

13-10  therefor has been made.

13-11  The rate must be adjusted accordingly on each January 1 and July 1

13-12  thereafter until the judgment is satisfied.

13-13  2.  The provisions of this section do not apply to money owed:

13-14  (a) For the construction [or remodeling of a building] of a work of

13-15  improvement pursuant to NRS 624.620; or

13-16  (b) By a contractor to his subcontractor pursuant to NRS 624.630.

 

13-17  H