S.B. 370

 

Senate Bill No. 370–Senator Schneider

 

March 16, 2001

____________

 

Referred to Committee on Judiciary

 

SUMMARY—Makes various changes relating to mechanics’ and materialmen’s liens. (BDR 9‑971)

 

FISCAL NOTE:            Effect on Local Government: No.

                                    Effect on the State: No.

 

~

 

EXPLANATION – Matter in bolded italics is new; matter between brackets [omitted material] is material to be omitted.

Green numbers along left margin indicate location on the printed bill (e.g., 5-15 indicates page 5, line 15).

 

AN ACT relating to liens; prohibiting the waiver or modification of rights relating to mechanics’ and materialmen’s liens except under certain circumstances; prohibiting certain provisions in a contract for a work of improvement; making various changes to provisions relating to mechanics’ and materialmen’s liens; and providing other matters properly relating thereto.

 

THE PEOPLE OF THE STATE OF NEVADA, REPRESENTED IN

SENATE AND ASSEMBLY, DO ENACT AS FOLLOWS:

 

1-1    Section 1. Chapter 108 of NRS is hereby amended by adding thereto

1-2  the provisions set forth as sections 2 to 26, inclusive, of this act.

1-3    Sec. 2.  As used in NRS 108.221 to 108.246, inclusive, and sections 2

1-4  to 26, inclusive, of this act, unless the context otherwise requires, the

1-5  words and terms defined in NRS 108.221 and sections 3 to 24, inclusive,

1-6  of this act have the meanings ascribed to them in those sections.

1-7    Sec. 3.  “Agent of the owner” means every architect, builder,

1-8  contractor, engineer, geologist, land surveyor, lessee, miner,

1-9  subcontractor or other person having charge or control of the property,

1-10  improvement or work of improvement of the owner, or any part thereof.

1-11    Sec. 4.  “Building” means a primary building or other

1-12  superstructure, together with all garages, outbuildings and other

1-13  structures appurtenant thereto.

1-14    Sec. 5.  “Commencement of construction” means the date on which:

1-15    1.  Work performed; or

1-16    2.  Materials or equipment provided,

1-17  produces visible results which are sufficient to make reasonably apparent

1-18  from an inspection of the site that a work of improvement has

1-19  commenced.

 

 


2-1    Sec. 6.  “Completion of the work of improvement” means:

2-2    1.  The occupation or use by the owner, an agent of the owner or a

2-3  representative of the owner of the work of improvement, accompanied by

2-4  the cessation of all work on the work of improvement;

2-5    2.  The acceptance by the owner, an agent of the owner or a

2-6  representative of the owner of the work of improvement, accompanied by

2-7  the cessation of work on the work of improvement; or

2-8    3.  The cessation of all work on a work of improvement for 30

2-9  consecutive days.

2-10    Sec. 7.  “Contract” means a written or oral agreement, including all

2-11  attachments and amendments thereto, for the provision of work,

2-12  materials or equipment for a work of improvement.

2-13    Sec. 8.  “Disinterested owner” means an owner who did not

2-14  personally or through an agent of the owner, directly or indirectly,

2-15  request, require, authorize, consent to, allow or cause an improvement to

2-16  be constructed, altered or repaired upon the property of the owner.

2-17    Sec. 9.  “Equipment” means tools, vehicles and machinery used in

2-18  the construction, alteration or repair of an improvement.

2-19    Sec. 10.  “Improvement” means the development, enhancement or

2-20  addition to property, by the provision of work, materials or equipment.

2-21  The term includes, without limitation:

2-22    1.  A building, railway, tramway, toll road, canal, water ditch, flume,

2-23  aqueduct, reservoir, bridge, fence, street, sidewalk, fixtures or other

2-24  structure or superstructure;

2-25    2.  A mine or a shaft, tunnel, adit or other excavation, designed or

2-26  used to prospect, drain or work a mine; or

2-27    3.  A system for irrigation, plants, sod or other landscaping.

2-28    Sec. 11.  “Lien” means the statutory rights and security interest in

2-29  property or any improvements thereon provided to a lien claimant by

2-30  NRS 108.221 to 108.246, inclusive, and sections 2 to 26, inclusive, of this

2-31  act.

2-32    Sec. 12.  “Lienable amount” means the amount of a lien to which a

2-33  lien claimant is entitled pursuant to subsection 1 of NRS 108.222.

2-34    Sec. 13.  “Lien claimant” means any person who provides work,

2-35  material or equipment with a value of $500 or more for the improvement

2-36  of the property or to be used in the construction, alteration or repair of

2-37  any improvement who is entitled to a lien on property pursuant to NRS

2-38  108.222. The term includes, without limitation, every architect, artisan,

2-39  builder, contractor, engineer, geologist, laborer, land surveyor, lessor of

2-40  equipment, materialman, miner, subcontractor or other person who

2-41  provides the work, material or equipment.

2-42    Sec. 14.  “Material” means the substances used or consumed in the

2-43  improvement of property or the construction, alteration or repair of a

2-44  work of improvement.

2-45    Sec. 15.  1.  “Owner” includes:

2-46    (a) The record owner or owners of property or of an improvement to

2-47  the property as evidenced by a conveyance or other instrument which

2-48  transfers that interest to him and is recorded in the office of the county

2-49  recorder in which the improvement or the property is located;


3-1    (b) The reputed owner or owners of the property or of an improvement

3-2  to the property;

3-3    (c) The owner or owners of the property or an improvement to the

3-4  property, as shown on the records of the county assessor for the county

3-5  where the property or improvement is located;

3-6    (d) The person or persons whose names appear as owner of the

3-7  property or an improvement to the property on the building permit; or

3-8    (e) A person who claims an interest in or possesses less than a fee

3-9  simple estate in the property or an improvement to the property.

3-10    2.  The term “owner” does not include:

3-11    (a) A mortgagee;

3-12    (b) A trustee or beneficiary of a deed of trust; or

3-13    (c) The owner or holder of a lien encumbering the property or an

3-14  improvement to the property.

3-15    Sec. 16.  “Notice of lien” means a notice recorded pursuant to NRS

3-16  108.226 to perfect a lien.

3-17    Sec. 17.  “Prevailing lien claimant” means a lien claimant to whom

3-18  an amount is found due by a court on a notice of lien or a claim against

3-19  a surety bond.

3-20    Sec. 18.  “Prime contract” means a contract between a prime

3-21  contractor and the owner of property about which the contract relates.

3-22    Sec. 19.  “Prime contractor” means a person who contracts with an

3-23  owner of property to provide work, materials or equipment to be used for

3-24  the improvement of the property, or in the construction, alteration or

3-25  repair of a work of improvement.

3-26    Sec. 20.  “Principal” means the person whose name appears as

3-27  principal on a surety bond.

3-28    Sec. 21.  “Property” means the land, real property or mining claim

3-29  of an owner occupied by an improvement or for which an improvement

3-30  was provided, together with a convenient space on, around and about the

3-31  same, or so much as may be required for the convenient use and

3-32  occupation thereof.

3-33    Sec. 22.  “Surety” means a corporation authorized to transact surety

3-34  business in this state pursuant to NRS 679A.030, who issues a surety

3-35  bond, and who has continuously maintained a rating of “A” or better by

3-36  Standard and Poor’s Ratings Services or A.M. Best Company’s ratings

3-37  for at least the 3 years immediately preceding the date of issuance of the

3-38  surety bond pursuant to NRS 108.2413 to 108.2425, inclusive.

3-39    Sec. 23.  “Surety bond” means a bond issued by a surety for the

3-40  release of a notice of lien pursuant to NRS 108.2413 to 108.2425,

3-41  inclusive.

3-42    Sec. 24.  “Work” means the labor and services provided for a work

3-43  of improvement, whether completed or partially completed, and includes

3-44  all labor and services provided by an architect, artisan, builder,

3-45  contractor, engineer, geologist, laborer, land surveyor, operator of

3-46  equipment, miner, subcontractor or other person providing labor or

3-47  services for the work of improvement.

 


4-1    Sec. 25.  1.  Except as otherwise provided in NRS 108.221 to

4-2  108.246, inclusive, and sections 2 to 26, inclusive, of this act, a person

4-3  may not waive or modify a right, obligation or liability set forth in the

4-4  provisions of NRS 108.221 to 108.246, inclusive, and sections 2 to 26,

4-5  inclusive, of this act.

4-6    2.  A condition, stipulation or provision in a contract or other

4-7  agreement for the improvement of property or for the construction,

4-8  alteration or repair of a work of improvement in this state which attempts

4-9  to do any of the following is void:

4-10    (a) Require a lien claimant to waive rights provided by law to lien

4-11  claimants or to limit the rights provided to lien claimants, other than as

4-12  expressly provided in NRS 108.221 to 108.246, inclusive, and sections 2

4-13  to 26, inclusive, of this act;

4-14    (b) Relieve a person of an obligation or liability imposed by the

4-15  provisions of NRS 108.221 to 108.246, inclusive, and sections 2 to 26,

4-16  inclusive, of this act;

4-17    (c) Make the contract or other agreement subject to the laws of a state

4-18  other than this state;

4-19    (d) Require any litigation, arbitration or other process for dispute

4-20  resolution on disputes arising out of the contract or other agreement to

4-21  occur in a state other than this state; or

4-22    (e) Require a contractor or subcontractor to limit or waive a claim he

4-23  may otherwise possess for delay damages or an extension of time for

4-24  delays incurred, for any delay which was unreasonable under the

4-25  circumstances, not within the contemplation of the parties at the time the

4-26  contract was entered into, and for which he is not responsible.

4-27    Sec. 26.  1.  Any term of a contract that attempts to waive or impair

4-28  the lien rights of a contractor, subcontractor or supplier is void. An

4-29  owner, contractor or subcontractor by any term of a contract, or

4-30  otherwise, may not obtain the waiver of, or impair the lien rights of, a

4-31  contractor, subcontractor or supplier, except as provided in this section.

4-32  Any written consent given by any lien claimant to waive or limit his lien

4-33  rights is unenforceable unless the lien claimant executes and delivers a

4-34  waiver and release in the form set forth in this section and the form is

4-35  signed by the lien claimant or his authorized agent, and, in the case of a

4-36  conditional waiver and release, if the lien claimant receives payment of

4-37  the amount identified in the conditional waiver and release.

4-38    2.  An oral or written statement purporting to waive, release or

4-39  otherwise adversely affect the rights of a lien claimant is not enforceable

4-40  and does not create any estoppel or impairment of a lien unless it is

4-41  pursuant to a waiver and release prescribed by this section or the lien

4-42  claimant has actually received payment in full for such a lien claim.

4-43    3.  This section does not affect the enforceability of either an accord

4-44  and satisfaction regarding a bona fide dispute or any agreement made in

4-45  settlement of an action pending in any court, provided the accord and

4-46  satisfaction or agreement and settlement make specific reference to the

4-47  lien rights waived or impaired and is signed by the lien claimant.


5-1    4.  The waiver and release given by any lien claimant is

5-2  unenforceable unless it is in the following forms in the following

5-3  circumstances:

5-4    (a) Where the lien claimant is required to execute a waiver and

5-5  release in exchange for or to induce the payment of a progress payment

5-6  and the lien claimant is not in fact paid in exchange for the waiver and

5-7  release or a single payee check or joint payee check is given in exchange

5-8  for the waiver and release, the waiver and release must be in the

5-9  following form:

 

5-10  Conditional Waiver and Release

5-11  Upon Progress Payment

 

5-12  Property Name:...................................................

5-13  Property Location:..............................................

5-14  Undersigned’s Customer:...................................

5-15  Invoice/Payment Application Number:..............

5-16  Payment Amount:..............................................

5-17  Payment Period:.................................................

 

5-18    Upon receipt by the undersigned of a check in the above referenced

5-19  Payment Amount payable to the undersigned, and when the check has

5-20  been properly endorsed and has been paid by the bank on which it is

5-21  drawn, this document becomes effective to release and the undersigned

5-22  shall be deemed to waive any notice of lien, any private bond right, any

5-23  claim for payment and any rights under any similar ordinance, rule or

5-24  statute related to payment rights that the undersigned has on the above

5-25  described Property to the following extent:

5-26    This release covers a progress payment for all work, materials or

5-27  equipment furnished by the undersigned to the Property or to the

5-28  Undersigned’s Customer, for only the Payment Amount or such portion

5-29  of the Payment Amount as the undersigned has actually paid, and does

5-30  not cover any retention withheld, any items, modifications or changes

5-31  pending approval, disputed items and claims, or items furnished or

5-32  invoiced after the Payment Period. Before any recipient of this document

5-33  relies on it, he should verify evidence of payment to the undersigned.

5-34    The undersigned warrants that he either has already paid or will use

5-35  the money he receives from this progress payment promptly to pay in full

5-36  all his laborers, subcontractors, materialmen and suppliers for all work,

5-37  materials or equipment that are the subject of this waiver and release.

 

5-38    DATED:........

5-39                                                                               ...........................

5-40                                                   (Company Name)

 

5-41                                                   By:.....................

 

5-42                                                   Its:......................


6-1    (b) Where the lien claimant has been paid the full amount provided

6-2  for in the progress payment, the waiver and release must be in the

6-3  following form:

 

6-4  Unconditional Waiver and Release

6-5  Upon Progress Payment

 

6-6  Property Name:....................................................

6-7  Property Location:...............................................

6-8  Undersigned’s Customer:....................................

6-9  Invoice/Payment Application Number:...............

6-10  Payment Amount:..............................................

6-11  Payment Period:.................................................

 

6-12    The undersigned has been paid and has received a progress payment

6-13  in the above referenced Payment Amount for all work, materials and

6-14  equipment the undersigned furnished to his Customer for the above

6-15  described Property and does hereby waive and release any notice of lien,

6-16  any private bond right, any claim for payment and any rights under any

6-17  similar ordinance, rule or statute related to payment rights that the

6-18  undersigned has on the above described Property to the following extent:

6-19    This release covers a progress payment for all work, materials and

6-20  equipment furnished by the undersigned to the Property or to the

6-21  Undersigned’s Customer, for only the Payment Amount or such portion

6-22  of the Payment Amount as the undersigned has actually paid, and does

6-23  not cover any retention withheld, any items, modifications or changes

6-24  pending approval, disputed items and claims, or items furnished or

6-25  invoiced after the Payment Period. Before any recipient of this document

6-26  relies on it, he should verify evidence of payment to the undersigned.

6-27    The undersigned warrants that he either has already paid or will use

6-28  the money he receives from this progress payment promptly to pay in full

6-29  all his laborers, subcontractors, materialmen and suppliers for all work,

6-30  materials or equipment that are the subject of this waiver and release.

 

6-31    DATED:........

6-32                                                                               ...........................

6-33                                                   (Company Name)

 

6-34                                                   By:.....................

 

6-35                                                   Its:......................

 

6-36  (Each unconditional waiver and release must contain the following

6-37  language, in type at least as large as the largest type otherwise on the

6-38  document:)

 

6-39  Notice: This document waives rights unconditionally and states that you

6-40  have been paid for giving up those rights. This document is enforceable

6-41  against you if you sign it, even if you have not been paid the full Payment


7-1  Amount or in full for the Payment Period. If you have not been paid, use

7-2  a conditional release form.

7-3    (c) Where the lien claimant is required to execute a waiver and release

7-4  in exchange for or to induce payment of a final payment and the lien

7-5  claimant is not paid in exchange for the waiver and release or a single

7-6  payee check or joint payee check is given in exchange for the waiver and

7-7  release, the waiver and release must be in the following form:

 

7-8  Conditional Waiver and Release

7-9  Upon Final Payment

 

7-10  Property Name:...................................................

7-11  Property Location:..............................................

7-12  Undersigned’s Customer:...................................

7-13  Invoice/Payment Application Number:..............

7-14  Payment Amount:..............................................

7-15  Amount of Disputed Claims:..............................

7-16  Description of Disputed Claims:.........................

 

7-17    Upon receipt by the undersigned of a check in the above referenced

7-18  Payment Amount payable to the undersigned, and when the check has

7-19  been properly endorsed and has been paid by the bank on which it is

7-20  drawn, this document becomes effective to release and the undersigned

7-21  shall be deemed to waive any notice of lien, any private bond right, any

7-22  claim for payment and any rights under any similar ordinance, rule or

7-23  statute related to payment rights that the undersigned has on the above

7-24  described Property to the following extent:

7-25    This release covers the final payment to the undersigned for all work,

7-26  materials or equipment furnished by the undersigned to the Property or

7-27  to the Undersigned’s Customer and does not cover payment for Disputed

7-28  Claims, if any. Before any recipient of this document relies on it, he

7-29  should verify evidence of payment to the undersigned.

7-30    The undersigned warrants that he either has already paid or will use

7-31  the money he receives from the final payment promptly to pay in full all

7-32  his laborers, subcontractors, materialmen and suppliers for all work,

7-33  materials or equipment that are the subject of this waiver and release.

 

7-34    DATED:........

7-35                                                                               ...........................

7-36                                                   (Company Name)

 

7-37                                                   By:.....................

 

7-38                                                   Its:......................

 

7-39    (d) Where the lien claimant has been paid the final payment, the

7-40  waiver and release must be in the following form:

 

 


8-1  Unconditional Waiver and Release

8-2  Upon Final Payment

 

8-3  Property Name:....................................................

8-4  Property Location:...............................................

8-5  Undersigned’s Customer:....................................

8-6  Invoice/Payment Application Number:...............

8-7  Amount of Disputed Claims:...............................

8-8  Description of Disputed Claims:..........................

 

8-9    The undersigned has been paid in full for all work, materials and

8-10  equipment the undersigned furnished to his Customer for the above

8-11  described Property and does hereby waive and release any notice of lien,

8-12  any private bond right, any claim for payment and any rights under any

8-13  similar ordinance, rule or statute related to payment rights that the

8-14  undersigned has on the above described Property, except for the payment

8-15  of Disputed Claims, if any.

8-16    The undersigned warrants that he either has already paid or will use

8-17  the money he receives from this final payment promptly to pay in full all

8-18  his laborers, subcontractors, materialmen and suppliers for all work,

8-19  materials and equipment that are the subject of this waiver and release.

 

8-20    DATED:........

8-21                                                                               ...........................

8-22                                                   (Company Name)

 

8-23                                                   By:.....................

 

8-24                                                   Its:......................

 

8-25  (Each unconditional waiver and release must contain the following

8-26  language, in type at least as large as the largest type otherwise on the

8-27  document:)

 

8-28  Notice: This document waives rights unconditionally and states that you

8-29  have been paid for giving up those rights. This document is enforceable

8-30  against you if you sign it, even if you have not been paid. If you have not

8-31  been paid, use a conditional release form.

8-32    Sec. 27.  NRS 108.221 is hereby amended to read as follows:

8-33    108.221  [As used in NRS 108.221 to 108.246, inclusive, unless the

8-34  context otherwise requires, “work] “Work of improvement” [or

8-35  “improvement”] means the entire structure or scheme of improvement as a

8-36  whole[.] , including, without limitation, all work, materials and

8-37  equipment to be used in or for the construction, alteration or repair of

8-38  the property or any improvement, whether under multiple prime

8-39  contracts or a single prime contract, except as follows:

8-40    1.  If a scheme of improvement consists of the construction of two or

8-41  more separate buildings and each building is constructed upon a

8-42  separate lot or parcel of land and pursuant to a separate prime contract


9-1  for only that building, then each building shall be deemed a separate

9-2  work of improvement; and

9-3    2.  If the improvement of the site is provided for in a prime contract

9-4  that is separate from all prime contracts for the construction of one or

9-5  more buildings on the property, the improvement of the site shall be

9-6  deemed a separate work of improvement from the construction of the

9-7  buildings and the commencement of construction of the improvement of

9-8  the site does not constitute the commencement of the construction of the

9-9  buildings. As used in this subsection, “improvement of the site” means

9-10  the development, enhancement or addition to the property, by providing

9-11  any of the following preparatory to the construction of a building:

9-12    (a) The demolition or removal of improvements, trees or other

9-13  vegetation;

9-14    (b) The drilling of test holes;

9-15    (c) Grading, grubbing, filling or excavating;

9-16    (d) Constructing or installing sewers or other public utilities; or

9-17    (e) Constructing a vault, cellar or room under sidewalks or making

9-18  improvements to the sidewalks in front of or adjoining the property.

9-19    Sec. 28.  NRS 108.222 is hereby amended to read as follows:

9-20    108.222  1.  Except as otherwise provided in subsection 2, a person

9-21  who performs [labor] work upon or furnishes material [of the] or

9-22  equipment with a value of $500 or more, to be used in the construction,

9-23  alteration or repair of any [building, or other superstructure, railway,

9-24  tramway, toll road, canal, water ditch, flume, aqueduct or reservoir, bridge,

9-25  fence or any other structure,] work of improvement, has a lien upon the

9-26  [premises and any building, structure] property, work of improvement and

9-27  any improvement [thereon] on the property for:

9-28    (a) If the parties entered into a contract, the unpaid balance of the price

9-29  agreed upon for[;] the work performed or material furnished or rented,

9-30  as the case may be, by each respectively, whether performed or furnished

9-31  at the request of the owner of the building or improvement, or at the

9-32  request of his agent; or

9-33    (b) [In absence of] If a specific price for some or all the work, material

9-34  or equipment is not set forth in a contract, an amount equal to the fair

9-35  market value of[, the labor] the work performed or material furnished or

9-36  rented, as the case may be, by each respectively, including a reasonable

9-37  allowance for overhead and a profit, whether performed or furnished at the

9-38  [instance] request of the owner of the building or other improvement, or at

9-39  the [instance] request of his agent.

9-40    2.  If a contractor’s license is required for the work, only a contractor

9-41  licensed pursuant to chapter 624 of NRS, an employee of such a contractor

9-42  or a person who furnishes material or equipment to be used in the project

9-43  may have a lien as described in subsection 1.

9-44    [3.  All miners, laborers and others who perform labor to the amount of

9-45  $500 or more in or upon any mine, or upon any shaft, tunnel, adit or other

9-46  excavation, designed or used to prospect, drain or work the mine, and all

9-47  persons who furnish any timber or other material, of the value of $500 or

9-48  more, to be used in or about a mine, whether performed or furnished at the


10-1  instance of the owner of the mine or his agent, have, and may each

10-2  respectively claim and hold, a lien upon that mine for:

10-3    (a) If the parties entered into a contract, the unpaid balance of the price

10-4  agreed upon for; or

10-5    (b) In absence of a contract, an amount equal to the fair market value of,

10-6  the labor so performed or material furnished, including a reasonable

10-7  allowance for overhead and a profit.

10-8    4.  Every contractor, subcontractor, engineer, land surveyor, geologist,

10-9  architect, builder or other person having charge or control of any mining

10-10  claim, or any part thereof, or of the construction, alteration or repair, either

10-11  in whole or in part, of any building or other improvement, as these terms

10-12  are used in subsection 1, shall be held to be the agent of the owner, for the

10-13  purposes of NRS 108.221 to 108.246, inclusive.]

10-14  Sec. 29.  NRS 108.225 is hereby amended to read as follows:

10-15  108.225  1.  The liens provided for in NRS 108.221 to 108.246,

10-16  inclusive, and sections 2 to 26, inclusive, of this act are preferred to:

10-17  (a) Any lien, mortgage or other encumbrance which may have attached

10-18  to the property after the [time when the building, improvement or structure

10-19  was commenced, work done, or materials were commenced to be

10-20  furnished.] commencement of construction of a work of improvement.

10-21  (b) Any lien, mortgage or other encumbrance of which the [lienholder]

10-22  lien claimant had no notice of and which was unrecorded against the

10-23  property at the [time the building, improvement or structure was

10-24  commenced, work done, or the materials were commenced to be
furnished.

10-25  For the purposes of this subsection, “work done” does not include any

10-26  work commenced before on-site construction has started.

10-27  2.  Except as otherwise provided in subsection 3, every]

10-28  commencement of construction of a work of improvement.

10-29  2.  Every mortgage or encumbrance imposed upon, or conveyance

10-30  made of, property affected by the liens provided for in NRS 108.221 to

10-31  108.246, inclusive, [between the time when the building, improvement,

10-32  structure or work thereon was commenced, or the materials thereof were

10-33  commenced to be furnished, and the expiration of the time fixed in NRS

10-34  108.221 to 108.246, inclusive, in which liens therefor may be recorded,

10-35  whatever the terms of payment may be,] and sections 2 to 26, inclusive, of

10-36  this act after the commencement of construction of a work of

10-37  improvement are subordinate and subject to [the liens in full authorized in]

10-38  all liens that are properly perfected pursuant to NRS 108.221 to 108.246,

10-39  inclusive, and sections 2 to 26, inclusive, of this act regardless of the date

10-40  of recording the notices of liens.

10-41  [3.  If any improvement at the site is provided for in a contract that is

10-42  separate from any contract for the construction of a building or other

10-43  structure, the improvement at the site shall be deemed a separate work of

10-44  improvement and the commencement thereof does not constitute the

10-45  commencement of the construction of the building or other structure. As

10-46  used in this subsection, “improvement at the site” means:

10-47  (a) The demolition or removal of improvements, trees or other

10-48  vegetation from;


11-1    (b) The drilling of test holes in;

11-2    (c) Grading, filling or otherwise improving; or

11-3    (d) Constructing or installing sewers or other public utilities
on,

11-4  any lot or tract of land or the street, highway or sidewalk in front of or

11-5  adjoining any lot or tract of land. The term includes the construction of any

11-6  vaults, cellars or rooms under the sidewalks or making improvements to

11-7  the sidewalks in front of or adjoining any tract of land.]

11-8    Sec. 30.  NRS 108.226 is hereby amended to read as follows:

11-9    108.226  1.  [Every person claiming the benefit of NRS 108.221 to

11-10  108.246, inclusive,] To perfect his lien, a lien claimant must record his

11-11  notice of lien in the office of the county recorder of the county where the

11-12  property or any improvement or some part thereof is located, in the form

11-13  provided in subsection [5:] 2:

11-14  (a) Within 90 days after the date on which the latest of the following

11-15  occurs:

11-16     (1) The completion of the work of improvement;

11-17  [(b) Within 90 days after the]

11-18     (2) The last delivery of material or furnishing of equipment by the

11-19  lien claimant[; or

11-20  (c) Within 90 days after the] for the work of improvement; or

11-21     (3) The last performance of [labor] work by the lien claimant[,

11-22  whichever is later.

11-23  2.  The time within which to perfect the lien by recording the notice of

11-24  lien is shortened if a] for the work of improvement; or

11-25  (b) Within 40 days after the recording of a notice of completion, if the

11-26  notice of completion is recorded [in a timely] and served in the manner

11-27  required pursuant to NRS 108.228 . [, in which event the notice of lien

11-28  must be recorded within 40 days after the recording of the notice of

11-29  completion.

11-30  3.  Any one of the following acts or events is equivalent to “completion

11-31  of the work of improvement” for all purposes of NRS 108.221 to 108.246,

11-32  inclusive:

11-33  (a) The occupation or use of a building, improvement or structure by the

11-34  owner, his agent or his representative and accompanied by cessation of

11-35  labor thereon.

11-36  (b) The acceptance by the owner, his agent or his representative of the

11-37  building, improvement or structure.

11-38  (c) The cessation from labor for 30 days upon any building,

11-39  improvement or structure, or the alteration, addition to or repair thereof.

11-40  (d) The recording of the notice of completion provided in NRS 108.228.

11-41  4.  For the purposes of this section, if a work of improvement consists

11-42  of the construction of more than one separate building and each building is

11-43  constructed pursuant to:

11-44  (a) A separate contract, each building shall be deemed a separate work

11-45  of improvement. The time within which to perfect the lien by recording the

11-46  notice of lien pursuant to subsection 1 commences to run upon the

11-47  completion of each separate building; or


12-1    (b) A single contract, the time within which to perfect the lien by

12-2  recording the notice of lien pursuant to subsection 1 commences to run

12-3  upon the completion of all the buildings constructed pursuant to
that contract.

12-4  As used in this subsection, “separate building” means one structure of a

12-5  work of improvement and any garages or other outbuildings appurtenant

12-6  thereto.

12-7    5.] 2. The notice of [mechanic’s lien must be recorded in the office of

12-8  the county recorder of the county where the property or some part thereof

12-9  is situated and] lien must contain:

12-10  (a) A statement of [his demand] the lienable amount after deducting all

12-11  just credits and offsets.

12-12  (b) The name of the owner , [or reputed owner] if known.

12-13  (c) The name of the person by whom he was employed or to whom he

12-14  furnished the material.

12-15  (d) A brief statement of the terms[, time given and conditions] of

12-16  payment of his contract.

12-17  (e) A description of the property to be charged with the notice of lien

12-18  sufficient for identification.

12-19  [6.  The claim]

12-20  3.  The notice of lien must be verified by the oath of the lien claimant

12-21  or some other person. The [claim] notice of lien need not be acknowledged

12-22  to be recorded.

12-23  [7.] 4. It is unlawful for a person knowingly to make a false statement

12-24  in or relating to the recording of a notice of lien pursuant to the provisions

12-25  of this section. A person who violates this subsection is guilty of a gross

12-26  misdemeanor and shall be punished by a fine of not less than $5,000 nor

12-27  more than $10,000.

12-28  5.  A notice of lien may be in substantially the following form:

 

12-29  Notice of Claim of Lien

 

12-30  The undersigned claims a lien upon the property described in this notice

12-31  for work, materials or equipment furnished for the improvement of the

12-32  property:

 

12-33  1.  The amount of the lien, after deducting all just credits and offsets,
is: $........................................................................ .

12-34  2.  The name of the owner, if known, of the property is: ............................................................ .

12-35  3.  The name of the person by whom the lien claimant was employed
or to whom the lien claimant furnished work, materials or equipment
is: .......................................................................... .

12-36  4.  A brief statement of the terms, time given and conditions of the lien

12-37  claimant’s contract is: ..................................... .

12-38  5.  A description of the property is: ................... .

 

12-39                                                                              ...................................

12-40                             (Print Name of Lien Claimant)

 


13-1  By:.......................

13-2  (Authorized Signature)

 

13-3  State of ......     )

13-4                            ) ss.

13-5  County of           )

 

13-6  ........................       (print name), being first duly sworn on oath

13-7  according to law, deposes and says:

13-8    I have read the foregoing Notice of Claim of Lien, know the contents

13-9  thereof and state that the same are true of my own personal knowledge,

13-10  except those matters stated upon information and belief, and, as to those

13-11  matters, I believe them to be true.

 

13-12                                                                              ........................................

13-13  Subscribed and sworn to before me

13-14  this ................................  day of the month of .........  of the year ................

 

13-15  ........................................

13-16  Notary Public in and for

13-17    the County and State

13-18  Sec. 31.  NRS 108.227 is hereby amended to read as follows:

13-19  108.227  1.  In addition to the requirements of NRS 108.226, a copy

13-20  of the [claim] notice of lien must be served upon the [record] owner of the

13-21  property within 30 days after recording the notice of lien, in one of the

13-22  following ways:

13-23  (a) By personally delivering a copy of the notice of lien to the [record

13-24  owner personally;

13-25  (b) If he is absent from his place of residence, or from his usual place of

13-26  business, by leaving a copy with some person of suitable age and discretion

13-27  at either place and mailing a copy addressed to the record owner at his

13-28  place of residence or place of business; or

13-29  (c) If his] owner or resident agent of the owner;

13-30  (b) By mailing a copy of the notice of lien by certified mail return

13-31  receipt requested to the owner at his place of residence or his usual place

13-32  of business or to the resident agent of the owner at the address of the

13-33  resident agent; or

13-34  (c) If the place of residence or business of the owner and the address of

13-35  the resident agent of the owner, if applicable, cannot be [ascertained, or a

13-36  person of suitable age or discretion cannot be found there,] determined, by:

13-37     (1) Fixing a copy of the notice of lien in a conspicuous place on the

13-38  property;

13-39     (2) Delivering a copy of the notice of lien to a person there residing,

13-40  if such a person can be found; and

13-41     (3) Mailing a copy of the notice of lien addressed to the [record]

13-42  owner at [the] :

13-43       (I) The place where the property is [situated.

13-44  2.  Failure] located;

13-45       (II) The address of the owner as identified in the deed; or


14-1        (III) The address identified in the records of the office of the

14-2  county assessor.

14-3    2.  If there is more than one owner, failure to serve a copy of the

14-4  [claim] notice of lien upon a particular [record] owner does not invalidate a

14-5  [claim based on a valid service] notice of lien if properly served upon

14-6  another [record] owner.

14-7    3.  [As used in this section, “record owner” means any person who

14-8  holds an interest in real property or any improvement thereon evidenced by

14-9  a conveyance or other instrument which transfers that interest to him and is

14-10  recorded in the office of the county recorder of the county in which the real

14-11  property is located, but does not include:

14-12  (a) A mortgagee;

14-13  (b) A trustee under, or a beneficiary of, a deed of trust; or

14-14  (c) The owner or holder of a lien encumbering real property or any

14-15  improvement thereon.] Each subcontractor who participates in the

14-16  construction, improvement, alteration or repair of a work of

14-17  improvement shall deliver a copy of each notice of lien required by NRS

14-18  108.226 to the prime contractor. The failure of a subcontractor to deliver

14-19  the notice to the prime contractor is a ground for disciplinary

14-20  proceedings pursuant to chapter 624 of NRS.

14-21  Sec. 32.  NRS 108.2275 is hereby amended to read as follows:

14-22  108.2275  1.  [The] Provided an order has not been entered pursuant

14-23  to NRS 108.2419 releasing the lien of a lien claimant upon the posting of

14-24  a surety bond, the debtor of the lien claimant or a party in interest in the

14-25  [premises] property subject to the notice of lien who believes the notice of

14-26  lien is frivolous and was made without reasonable cause, or that the

14-27  amount of the notice of lien is excessive, may apply by motion to the

14-28  district court for the county where the property or some part thereof is

14-29  [situated] located for an order directing the lien claimant to appear before

14-30  the court to show cause why the relief requested should not be granted.

14-31  2.  The motion must [set] :

14-32  (a) Set forth in detail the legal and factual grounds upon which relief is

14-33  requested ; and [must be]

14-34  (b) Be supported by [the affidavit of] :

14-35     (1) A notarized affidavit signed by the applicant [or his attorney]

14-36  setting forth [a concise statement of] in detail the facts upon which the

14-37  motion is based[.] ; and

14-38     (2) Documentary evidence, if any.

14-39  3.  If the court issues an order for a hearing, the applicant shall serve

14-40  notice of the application and order of the court on the lien claimant within

14-41  3 days after the court issues the order. The court shall conduct the hearing

14-42  within not less than [10] 15 days or more than [20] 30 days after the court

14-43  issues the order[.

14-44  2.] for a hearing.

14-45  4. The order for a hearing must include a statement that if the lien

14-46  claimant fails to appear at the time and place noted, the notice of lien will

14-47  be released with prejudice and the lien claimant will be ordered to pay the

14-48  reasonable costs [requested by] the applicant[, including reasonable

14-49  attorney’s fees.


15-1    3.] incurs in bringing the motion, including reasonable attorney’s fees.

15-2    5. If, at the time the application is filed, an action to foreclose the

15-3  notice of lien has not been filed, the clerk of the court shall assign a

15-4  number to the application and obtain from the applicant a filing fee of $85.

15-5  If an action has been filed to foreclose the notice of lien before the

15-6  application was filed pursuant to this section, the application must be made

15-7  a part of the action to foreclose the notice of lien.

15-8    [4.] 6. If, after a hearing on the matter, the court determines that[:

15-9    (a) The] the applicant:

15-10  (a) Has proven that the notice of lien is frivolous and was made

15-11  without reasonable cause, the court may make an order releasing the lien

15-12  and awarding costs and reasonable attorney’s fees to the applicant[.

15-13  (b) The] for bringing the motion.

15-14  (b) Has proven that the amount of the notice of lien is excessive, the

15-15  court may make an order reducing the notice of lien to an amount deemed

15-16  appropriate by the court and awarding costs and reasonable attorney’s fees

15-17  to the applicant[.

15-18  (c) The] for bringing the motion.

15-19  (c) Has not proven the notice of lien is [not] frivolous and was made

15-20  with reasonable cause [and] or that the amount of the notice of lien is [not]

15-21  excessive, the court may make an order awarding costs and reasonable

15-22  attorney’s fees to the lien claimant[.

15-23  5.] for defending the motion.

15-24  7. Proceedings conducted pursuant to this section do not affect any

15-25  other rights and remedies otherwise available to the parties.

15-26  [6.] 8. An appeal may be taken [by either party] from an order made

15-27  pursuant to subsection [4.] 6 on the same grounds as an appeal from a

15-28  grant or denial of a motion for summary judgment.

15-29  [7.] 9. If an order releasing or reducing a notice of lien is entered by

15-30  the court, and the order is not stayed, the [lien claimant shall, within 2]

15-31  applicant may, within 5 days after the order is entered, record a certified

15-32  copy of the order in the office of the county recorder of the county where

15-33  the property or some part thereof is [situated.] located. The recording of a

15-34  certified copy of the order releasing or reducing a notice of lien is notice to

15-35  any interested party that the notice of lien has been released or reduced.

15-36  10.  A notice of lien is frivolous and made without reasonable cause

15-37  when, in accordance with the standards applicable to a motion for

15-38  summary judgment, and viewed in the light most favorable to the lien

15-39  claimant, it is clear beyond legitimate dispute that the notice of lien is

15-40  baseless in both fact and law and without a good faith argument for the

15-41  extension of law thereto.

15-42  Sec. 33.  NRS 108.228 is hereby amended to read as follows:

15-43  108.228  1.  The owner may record a notice of completion after[:

15-44  (a) The] the completion of [any] the work of improvement . [; or

15-45  (b) There has been a cessation from labor thereon for a period of 30

15-46  days.]

15-47  2.  The notice of completion must be recorded in the office of the

15-48  county recorder of the county where the property is [situated] located and

15-49  must set forth:


16-1    (a) The date [when the work of improvement was completed, or the date

16-2  on which cessation from labor occurred first and the period of its duration.]

16-3  of completion of the work of improvement.

16-4    (b) The owner’s name or owners’ names, as the case may be, the

16-5  address of the owner or addresses of the owners, as the case may be, and

16-6  the nature of the title, if any, of the person signing the notice.

16-7    (c) A description of the property sufficient for identification.

16-8    (d) The name of the prime contractor[,] or prime contractors, if any.

16-9    3.  The notice must be verified by the owner or by some other person

16-10  on his behalf. The notice need not be acknowledged to be recorded.

16-11  4.  Upon recording the notice pursuant to this section, the owner shall,

16-12  within 10 days after the notice is recorded, deliver a copy of the notice by

16-13  certified mail, to:

16-14  (a) [Any general] Each prime contractor with whom the owner

16-15  contracted for all or any part of the work of improvement.

16-16  (b) [Any person] Each lien claimant who, before the notice was

16-17  recorded pursuant to this section, submitted a request to the owner to

16-18  receive the notice.

16-19  5.  The failure of the owner to deliver a copy of the notice of

16-20  completion in the time and manner as provided in this section renders

16-21  the notice of completion ineffective with respect to each prime contractor

16-22  and lien claimant.

16-23  Sec. 34.  NRS 108.229 is hereby amended to read as follows:

16-24  108.229  1.  At any time before the trial of any action to foreclose a

16-25  lien, a lien claimant may record an amended notice of lien to increase,

16-26  reduce, correct or clarify his notice of lien. The lien claimant shall serve

16-27  the owner of the property with an amended notice of lien in the same

16-28  manner as required for serving a notice of lien pursuant to NRS 108.227

16-29  and within 30 days after recording the amended notice of lien. A

16-30  variance between a notice of lien and an amended notice of lien must not

16-31  defeat the lien and shall not be deemed material unless the variance:

16-32  (a) Results from fraud or is made intentionally; or

16-33  (b) Misleads an adverse party to his prejudice, but then only with

16-34  respect to the adverse party who was prejudiced.

16-35  2.  Upon the trial of any action or suit to foreclose [such lien no] a lien,

16-36  a variance between the lien and the proof [shall] must not defeat the lien

16-37  [or] and shall not be deemed material unless the [same results] variance:

16-38  (a) Results from fraud or is made intentionally[, or has misled] ; or

16-39  (b) Misleads the adverse party to his prejudice, but [in] then only with

16-40  respect to the adverse party who was prejudiced.

16-41  In all cases of immaterial variance the [claim] notice of lien may be

16-42  amended, by amendment duly recorded, to conform to the proof.

16-43  [2.  No]

16-44  3.  An error or mistake in the name of the owner [or reputed owner]

16-45  contained in any [claim] notice of lien [shall] must not be held to defeat

16-46  the lien, unless a correction of the notice of lien in this particular would

16-47  prejudice the rights of an innocent bona fide purchaser or encumbrancer for

16-48  value[.


17-1    3.] , but then only with respect to the bona fide purchaser or

17-2  encumbrancer for value who is prejudiced.

17-3    4. Upon the trial, [however,] if it [shall appear] appears that an error or

17-4  mistake has been made in the name of the owner [or reputed owner,] or

17-5  that the wrong person has been named as owner [or reputed owner] in any

17-6  [such claim] notice of lien, the court shall order an amended [claim] notice

17-7  of lien to be recorded with the county recorder where the original [claim]

17-8  notice of lien was recorded[,] and shall issue to the person who is so made

17-9  to appear to be the original [or reputed] owner a notice directing [such] the

17-10  person or persons to be and appear before the court within the same time as

17-11  is provided by Nevada Rules of Civil Procedure for the appearance in other

17-12  actions after the service of summons, which notice [shall] must be served

17-13  in all respects as a summons is required to be served, and to show cause

17-14  why:

17-15  (a) He should not be substituted[,] in the action as the correct owner,

17-16  in the [claim] notice of lien and in the suit, in lieu of the person so made

17-17  defendant and alleged to be owner [or reputed owner] by mistake.

17-18  (b) He should not be bound by the judgment or decree of the court.

17-19  Such proceedings [shall] must be had therein as though the party so cited

17-20  to appear had been an original party defendant in the action or suit, and

17-21  originally named in the [claim] notice of lien as owner , [or reputed

17-22  owner,] and the rights of all parties [shall] must thereupon be fully

17-23  adjudicated.

17-24  [4.] 5. A notice of lien which contains therein the description of the

17-25  [real] property supplied by and set forth in the notice of completion

17-26  recorded pursuant to NRS 108.228 [shall,] must, for all purposes, be

17-27  sufficient as a description of the actual [real] property upon which the work

17-28  [or labor] was performed or materials or equipment were supplied[;] , and

17-29  amendment of the notice of lien [claim] or amendment of the pleading filed

17-30  by the lien claimant in a foreclosure action, or both, may be made to state

17-31  the correct description, and [such] the corrected description [shall] must

17-32  relate back to the time of recording [such] the notice of lien , [claim,]

17-33  unless a correction of the notice of lien in this particular would prejudice

17-34  the rights of an innocent bona fide purchaser or encumbrancer for value[.]

17-35  , but then only with respect to the bona fide purchaser or encumbrancer

17-36  for value who is prejudiced.

17-37  Sec. 35.  NRS 108.231 is hereby amended to read as follows:

17-38  108.231  1.  In every case in which [one claim] a notice of lien is

17-39  recorded against a work of improvement which includes two or more

17-40  separate buildings[,] or mining claims [or other improvements] and each

17-41  separate building or mining claim is located upon a separate lot or parcel

17-42  of land owned by the same person, at the time of recording the notice of

17-43  lien, the [person recording such claim must at the same time] lien claimant

17-44  must designate the lienable amount due to him on each [of such buildings,

17-45  mining claims or other improvements; otherwise the lien of such claim is

17-46  postponed to other liens.] building or mining claim. For purposes of this

17-47  subsection, the designation of a lien claimant’s lienable amount against

17-48  two or more buildings or mining claims must not invalidate or reduce a

17-49  notice of lien as against the buildings or mining claims, if the


18-1  designation was estimated by the lien claimant in good faith or was based

18-2  upon a pro rata division of the total lienable amount.

18-3    2.  The lien of [such claimant does not extend beyond] a lien claimant

18-4  only applies to the lienable amount designated[,] in the notice of lien,

18-5  plus all amounts that may be awarded by the court pursuant to NRS

18-6  108.237, as against other creditors having liens by judgment or otherwise,

18-7  upon [either of such buildings or other improvements, or upon the land

18-8  upon which the same are constructed.] the buildings or mining claims.

18-9  The lienable amount chargeable to the interest of the owner in each

18-10  building or mining claim must be the total amount of the lien claimant’s

18-11  notice of lien, without regard to the proportionate amount designated to

18-12  each separate building or mining claim in the lien claimant’s notice of

18-13  lien, plus all amounts that may be awarded by the court pursuant to NRS

18-14  108.237, but upon the trial thereof, the court may, where it deems it

18-15  equitable to do so, distribute the lien equitably as between the several

18-16  buildings and mining claims involved.

18-17  3.  If a lien claimant fails to designate in his notice of lien the amount

18-18  due to him on each separate building or mining claim, the lien

18-19  claimant’s notice of lien must be postponed to the notices of lien of other

18-20  lien claimants and other encumbrancers for value who have designated

18-21  the amount due on each building or mining claim but must not be

18-22  postponed to any rights or interests of the owner.

18-23  Sec. 36.  NRS 108.232 is hereby amended to read as follows:

18-24  108.232  The recorder in the county in which property that is subject

18-25  to a lien is located must record the [claim] notice of lien in a book kept by

18-26  him for that purpose, which record must be indexed as deeds and other

18-27  conveyances are required by law to be indexed, and for which he may

18-28  receive the same fees as are allowed by law for recording deeds and other

18-29  instruments.

18-30  Sec. 37.  NRS 108.233 is hereby amended to read as follows:

18-31  108.233  1.  [No] A lien provided for in NRS 108.221 to 108.246,

18-32  inclusive, [binds any building, mining claim, improvement or structure]

18-33  and sections 2 to 26, inclusive, of this act must not bind the property

18-34  subject to the lien for a [longer] period longer than 6 months after [such

18-35  lien has been] the date on which the notice of lien was recorded, unless:

18-36  (a) Proceedings are commenced in a proper court within that time to

18-37  enforce the same; or

18-38  (b) The time to commence the action is extended by a written

18-39  instrument signed by the [lienor] lien claimant and by a person or persons

18-40  in interest in the property subject to the lien, in which event, and as to only

18-41  that person or those persons in interest signing the agreement, the time is

18-42  extended , [;] but no extension [shall be] is valid unless in writing and

18-43  recorded in the county recorder’s office in which the notice of lien is

18-44  recorded and unless the extension agreement is recorded within [such] the

18-45  6-month period[; and such] , and the extension agreement, to be recorded,

18-46  must be acknowledged as required by law for the acknowledgment of

18-47  deeds. An action may be commenced within [such] the extended time only

18-48  [as to] against the persons signing the extension agreement and only as

18-49  their interests in the property are affected, and upon the lapse of the time


19-1  specified in the extension agreement, an action may not thereafter be

19-2  commenced, nor may a second extension be given.

19-3    2.  For all purposes, a [mechanic’s lien of record] notice of lien shall be

19-4  deemed to have expired as a lien against the property after the lapse of the

19-5  6-month period provided in subsection 1, and [such recording shall] the

19-6  recording of a notice of lien must not provide actual or constructive notice

19-7  after the lapse of [such] the 6-month period and as a lien on the [real]

19-8  property referred to in the [recorded] notice of lien, unless, [prior to] before

19-9  the lapse of [such] the 6-month period [the] an extension agreement has

19-10  been recorded, in which event, the lien [shall] will only continue as a lien

19-11  on the interests of those persons signing the extension for the period

19-12  specified in the extension . [and for no longer period.] An extension must

19-13  not be given for a period in excess of 1 year beyond the date on which the

19-14  notice of lien is recorded.

19-15  3.  If there are other [claims] notices of lien outstanding against the

19-16  property, [no extension shall] an extension must not be given upon [the] a

19-17  notice of lien which will tend to delay or postpone the collection of other

19-18  [claims] liens evidenced by a notice of lien or encumbrances against the

19-19  property . [; and no extension shall be given for a period in excess of 1 year

19-20  beyond the recording of the lien.]

19-21  Sec. 38.  NRS 108.234 is hereby amended to read as follows:

19-22  108.234  [Every building or other improvement mentioned in NRS

19-23  108.222,]

19-24  1.  Except as otherwise provided in subsection 2, every improvement

19-25  constructed , altered or repaired upon [any lands with the knowledge of

19-26  the owner or the person having or claiming any interest therein, shall]

19-27  property must be held to have been constructed , altered or repaired at the

19-28  instance of [such owner or person] the owner having or claiming any

19-29  interest therein, and the interest owned or claimed [shall] must be subject

19-30  to any notice of lien recorded in accordance with the provisions of NRS

19-31  108.221 to 108.246, inclusive, [unless such owner or person having or

19-32  claiming an interest therein shall,] and sections 2 to 26, inclusive, of this

19-33  act.

19-34  2.  The interest of a disinterested owner in any improvement and the

19-35  property upon which an improvement is constructed, altered or repaired

19-36  is not subject to a notice of lien if the disinterested owner, within 3 days

19-37  after he [has obtained] first obtains knowledge of the construction,

19-38  alteration or repair, or the intended construction, alteration or repair, [give]

19-39  gives notice that he will not be responsible for [such] the improvement by

19-40  [filing] recording a notice in writing to that effect with the county recorder

19-41  of the county where the [land or building is situated;] property is located,

19-42  and, in the instance of[:

19-43  1.] a disinterested owner who is:

19-44  (a) A lessor, the notice of [lien] nonresponsibility shall be deemed

19-45  timely [filed if the same has been filed] recorded if it is recorded within 3

19-46  days immediately following the [execution] effective date of the lease [by

19-47  all parties as to that construction, alteration or repair, or intended

19-48  construction, alteration or repair, known to the lessor at] or the time of the

19-49  execution of the lease by all parties[.


20-1    2.] , whichever occurs first; or

20-2    (b) An optionor, the notice of [lien] nonresponsibility shall be deemed

20-3  timely filed if the same has been filed within 3 days immediately following

20-4  the [execution of the agreement permitting entry upon the real property by

20-5  all parties as to that construction, alteration, repair, or intended

20-6  construction, alteration, repair or other work known to the optionor at the

20-7  time of the execution of the agreement by all parties.] date on which the

20-8  option is exercised in writing.

20-9    3.  Each notice of nonresponsibility recorded pursuant to this section

20-10  must identify:

20-11  (a) The name and address of the owner;

20-12  (b) The location of the improvement and the property upon which the

20-13  improvement is or will be constructed, altered or repaired;

20-14  (c) The nature and extent of the disinterested owner’s interest in the

20-15  improvement and the property upon which the improvement is or will be

20-16  constructed, altered or repaired; and

20-17  (d) The date on which the disinterested owner first learned of the

20-18  construction, alteration or repair of the improvement that is the subject

20-19  of the notice of nonresponsibility.

20-20  Sec. 39.  NRS 108.235 is hereby amended to read as follows:

20-21  108.235  1.  [The contractor shall be entitled to] A prime contractor:

20-22  (a) May record and recover[,] upon a notice of lien , [recorded by him,

20-23  only such] a lienable amount as may be due to him [according to the terms

20-24  of his contract, after deducting all claims of other parties] , plus all

20-25  amounts that may be awarded to him by the court pursuant to NRS

20-26  108.237; and

20-27  (b) Upon receipt of the amount described in paragraph (a), shall pay

20-28  all liens for the work [done and material furnished,] , equipment or

20-29  materials which were furnished to him, as provided in NRS 108.221 to

20-30  108.246, inclusive[.] , and sections 2 to 26, inclusive, of this act.

20-31  2.  In all cases where a prime contractor has been paid for the work,

20-32  materials or equipment which are the subject of a notice of lien [is]

20-33  recorded under NRS 108.221 to 108.246, inclusive, [for work done or

20-34  materials furnished to any contractor,] and sections 2 to 26, inclusive, of

20-35  this act, he shall defend the owner in any action brought thereupon at his

20-36  own expense. [During the pendency of the action,]

20-37  3.  Except as otherwise provided in this subsection, if a lien claimant

20-38  records a notice of lien for the work, equipment or materials furnished to

20-39  the prime contractor, the owner may withhold from the prime contractor

20-40  the amount of money for which [such] the notice of lien is [filed.]

20-41  recorded. If the lien claimant’s notice of lien resulted from the owner’s

20-42  failure to pay the prime contractor for the lien claimant’s work, materials

20-43  or equipment, the owner shall not withhold the amount set forth in the

20-44  notice of lien from the prime contractor for which the prime contractor

20-45  has tendered a release of the lien of the lien claimant. In case of judgment

20-46  against the owner or his property [upon] which is the subject of the lien,

20-47  the owner [shall be entitled to] may deduct, from any amount due or to

20-48  become due by him to the prime contractor, the amount [of the judgment

20-49  and costs. If the amount of the judgment and costs exceeds the amount due


21-1  by him to the contractor, or if the owner has settled with the contractor,]

21-2  justly paid by the owner to the lien claimant for which the prime

21-3  contractor was liable, and the owner [shall be entitled to] may recover

21-4  back from the prime contractor any amount so paid by the owner in excess

21-5  of the [contract price, and for which the contractor was originally the party

21-6  liable.] amount the court has found that the owner owes to the prime

21-7  contractor.

21-8    Sec. 40.  NRS 108.236 is hereby amended to read as follows:

21-9    108.236  1.  In every case in which different notices of liens are

21-10  asserted against any property, the court, in the judgment, must declare the

21-11  rank of each lien[,] claimant, or class of [liens,] lien claimants, which

21-12  must be in the following order:

21-13  (a) First: All [labor] work whether performed at the instance or

21-14  direction of the owner, the subcontractor or the [original] prime contractor.

21-15  (b) Second: Material suppliers[.

21-16  Third: The subcontractors, architects, land surveyors, geologists and

21-17  engineers, if such architects, land surveyors, geologists and engineers] and

21-18  lessors of equipment.

21-19  (c) Third: All other lien claimants who have performed their [services,]

21-20  work, in whole or in part, under contract with the [general contractor.

21-21  Fourth: The original contractors, architects, land surveyors, geologists

21-22  and engineers, if such architects, land surveyors, geologists and engineers

21-23  have not performed their services, in whole or in part, under contract with

21-24  the general contractor, and all persons other than original contractors,

21-25  subcontractors, architects, land surveyors, geologists and engineers.] prime

21-26  contractor or any subcontractor.

21-27  (d) Fourth: All other lien claimants.

21-28  2.  The proceeds of the sale of the property must be applied to each lien

21-29  [,] claimant, or class of [liens,] lien claimants, in the order of its rank.

21-30  Sec. 41.  NRS 108.237 is hereby amended to read as follows:

21-31  108.237  1.  [Any number of persons claiming liens may join in the

21-32  same action. When separate actions are commenced the court may

21-33  consolidate them.] The court shall award to a prevailing lien claimant,

21-34  whether on its lien or on a surety bond, the following:

21-35  (a) The lienable amount found due to the lien claimant by the court;

21-36  (b) The cost of preparing and filing the lien claim, including, without

21-37  limitation, attorney’s fees, if any;

21-38  (c) The costs of the proceedings;

21-39  (d) Attorney’s fees and costs for representation of the lien claimant in

21-40  the proceedings;

21-41  (e) Interest; and

21-42  (f) Any other amounts as the court may find to be justly due and

21-43  owing to the lien claimant.

21-44  2.  The court [may also allow] shall calculate interest for purposes of

21-45  this section based upon:

21-46  (a) The rate of interest agreed upon in the lien claimant’s contract; or

21-47  (b) If a rate of interest is not provided in the lien claimant’s contract,

21-48  interest at a rate equal to the prime rate at the largest bank in Nevada, as

21-49  ascertained by the commissioner of financial institutions, on January 1 or


22-1  July 1, as the case may be, immediately preceding the date of judgment,

22-2  plus 2 percent, on the amount of the lien found payable. [The interest is

22-3  payable from the date that the payment is found to have been due, and the

22-4  court may allow, as part of the costs, the money paid for recording the

22-5  lien.] The rate of interest must be adjusted accordingly on each January 1

22-6  and July 1 thereafter until the amount of the lien is paid.

22-7    [3.  The court shall also allow to the prevailing party reasonable

22-8  attorney’s fees for the preparation of the lien and for representation of the

22-9  lien claimant in the action.]

22-10  Interest is payable from the date on which the payment is found to have

22-11  been due, as determined by the court.

22-12  Sec. 42.  NRS 108.238 is hereby amended to read as follows:

22-13  108.238  Nothing contained in NRS 108.221 to 108.246, inclusive, and

22-14  sections 2 to 26, inclusive, of this act shall be construed to impair or affect

22-15  the right of [any person] a lien claimant to whom any debt may be due for

22-16  work [done or material] , materials or equipment furnished to maintain a

22-17  [personal] civil action to recover [such] that debt against the person liable

22-18  therefor[.] or to submit any controversy arising under a contract to

22-19  arbitration to recover that amount.

22-20  Sec. 43.  NRS 108.239 is hereby amended to read as follows:

22-21  108.239  1.  [Liens] A notice of lien may be enforced by an action in

22-22  any court of competent jurisdiction, on setting out in the complaint the

22-23  particulars of the demand, with a description of the [premises] property to

22-24  be charged with the lien.

22-25  2.  At the time of filing the complaint and issuing the summons, the

22-26  [plaintiff] lien claimant shall:

22-27  (a) File a notice of pendency of the action in the manner provided in

22-28  NRS 14.010; and

22-29  (b) Cause a notice of foreclosure to be published at least once a week

22-30  for 3 successive weeks, in one newspaper published in the county, and if

22-31  there is no newspaper published in the county, then in such mode as the

22-32  court may determine, notifying all persons holding or claiming notices of

22-33  liens pursuant to the provisions of NRS 108.221 to 108.246, inclusive, and

22-34  sections 2 to 26, inclusive, of this act on the [premises] property to file

22-35  with the clerk and serve on the [plaintiff] lien claimant and also on the

22-36  defendant, if the defendant is within the state or is represented by counsel,

22-37  written statements of the facts constituting their liens, together with the

22-38  dates and amounts thereof. [The statements must be filed]

22-39  3.  All persons holding or claiming a notice of lien may join a lien

22-40  claimant’s action by filing a statement of facts within 10 days after the

22-41  last publication of the notice[. The plaintiff] of foreclosure. Any number

22-42  of persons claiming liens may join in the same action if they timely file a

22-43  statement of facts in the lien claimant’s action. The lien claimant and

22-44  other parties adversely interested must be allowed [5] 20 days to answer

22-45  the statements.

22-46  [3.] 4. If it appears from the records of the county recorder that there

22-47  are other [lien claims] notices of liens recorded against the same

22-48  [premises] property at the time of the commencement of the action, the

22-49  [plaintiff] lien claimant shall, in addition to and after the initial publication


23-1  of the notice of foreclosure as provided in paragraph (b) of subsection 2,

23-2  mail to those other lien claimants, by registered or certified mail, or deliver

23-3  in person a copy of the notice of foreclosure as published.

23-4    [4.] 5. At the time of any change in the venue of the action, the

23-5  [plaintiff] lien claimant shall file a notice of pendency of the action, in the

23-6  manner provided in NRS 14.010, and include in the notice the court and

23-7  county to which the action is changed.

23-8    [5.] 6. When separate actions are commenced by lien claimants to

23-9  foreclose on their respective notices of lien, the court may consolidate all

23-10  the actions.

23-11  7.  The court shall enter judgment according to the right of the parties,

23-12  and shall, by decree, proceed to hear and determine the claims in a

23-13  summary way, or may, if it be the district court, refer the claims to a

23-14  special master to ascertain and report upon the liens and the amount justly

23-15  due thereon. No consequential damages may be recovered in an action

23-16  pursuant to this section. All liens not so exhibited shall be deemed to be

23-17  waived in favor of those which are so exhibited.

23-18  [6.] 8. Upon petition by a lien claimant for a preferential trial

23-19  setting:

23-20  (a) The court shall give preference in setting a date for the trial of an

23-21  action brought pursuant to this section; and

23-22  (b) If a lien action is designated as complex by the court, the court

23-23  may take into account the rights and claims of all lien claimants in

23-24  setting a date for the preferential trial.

23-25  9.  If the lienable amount of a lien claimant’s lien is the subject of

23-26  binding arbitration:

23-27  (a) The court may, at the request of a party to the arbitration, stay the

23-28  lien claimant’s action to foreclose the lien pending the outcome of the

23-29  binding arbitration. If the foreclosure on the lien involves the rights of

23-30  other lien claimants or persons whose claims are not the subject of the

23-31  binding arbitration, the court may stay the lien claimant’s foreclosure

23-32  proceeding only upon terms that are just and which afford the lien

23-33  claimant a fair opportunity to protect his lien rights and priorities with

23-34  respect to other lien claimants and persons.

23-35  (b) Upon the granting of an award by the arbitrator, any party to the

23-36  arbitration may seek an order from the court in the action to foreclose on

23-37  the lien confirming or adopting the award and determining the lienable

23-38  amount of the lien claimant’s lien in accordance with the order, if any.

23-39  Upon determining the lienable amount, the court shall enter a judgment

23-40  or decree for the lienable amount, plus all amounts that may be awarded

23-41  by the court to the lien claimant pursuant to NRS 108.237, and the court

23-42  may include as part of the lien all costs and attorney’s fees awarded to

23-43  the lien claimant by the arbitrator and all costs and attorney’s fees

23-44  incurred by the lien claimant pertaining to any application or motion to

23-45  confirm, adopt, modify or correct the award of the arbitrator. A judgment

23-46  or decree entered by the court pursuant to this subsection may be

23-47  enforced against the property as provided in subsections 10, 11 and 12.

23-48  10.  On ascertaining the whole amount of the liens with which the

23-49  [premises are] property is justly chargeable, as provided in NRS 108.221 to


24-1  108.246, inclusive, and sections 2 to 26, inclusive, of this act, the court

24-2  shall cause the [premises] property to be sold in satisfaction of [the] all

24-3  liens and the costs[, including costs of suit,] of sale, including all

24-4  amounts awarded to all lien claimants pursuant to NRS 108.237, and any

24-5  party in whose favor judgment may be rendered may cause the [premises]

24-6  property to be sold within the time and in the manner provided for sales on

24-7  execution, issued out of any district court, for the sale of real property.

24-8    [7.] 11. If the proceeds of sale, after the payment of the costs[,] of

24-9  sale, are not sufficient to satisfy [the whole amount of the] all liens to be

24-10  included in the decree of sale, including all amounts awarded to all lien

24-11  claimants pursuant to NRS 108.237, the proceeds must be apportioned

24-12  according to the right of the [several parties.] various lien claimants. If the

24-13  proceeds of the sale amount to more than the sum of [the] all liens and the

24-14  cost of sale, the remainder must be paid over to the owner of the property.

24-15  [8.] 12. Each party whose claim is not satisfied in the manner

24-16  provided in this section is entitled to personal judgment for the residue

24-17  against the party legally liable for it if that person has been personally

24-18  summoned or has appeared in the action.

24-19  Sec. 44.  NRS 108.2413 is hereby amended to read as follows:

24-20  108.2413  A [mechanic’s lien of record upon real property] notice of

24-21  lien may be released upon the posting of a surety bond in the manner

24-22  provided in NRS 108.2415 to 108.2425, inclusive.

24-23  Sec. 45.  NRS 108.2415 is hereby amended to read as follows:

24-24  108.2415  The [debtor of the lien claimant or a party in interest in the

24-25  premises subject to the lien must obtain a surety bond executed by the]

24-26  debtor of the lien claimant or a party in interest in the [premises] property

24-27  subject to the lien, as principal, and [executed by] a corporation authorized

24-28  to transact surety business in this state, as surety, shall execute a surety

24-29  bond in [substantially] the following form:

 

24-30  (Title of court and cause, if action has been commenced)

 

24-31  WHEREAS, ................................ (name of [owner, contractor, or other

24-32  person disputing lien)] principal) desires to give a bond for releasing the

24-33  following described [real] property from that certain [claim of mechanic’s]

24-34  notice of lien in the sum of $................ recorded ..... (month) ..... (day) .....

24-35  (year) in the office of the recorder in ................................ (name of county

24-36  where the [real] property is [situated):] located):

 

24-37  (legal description)

 

24-38  NOW, THEREFORE, the undersigned principal and surety do hereby

24-39  obligate themselves to the lien claimant named in the [mechanic’s] notice

24-40  of lien, ................................, (name of lien claimant) under the conditions

24-41  prescribed by NRS 108.2413 to 108.2425, inclusive, in the sum of

24-42  $................ (1 1/2 x claim), from which sum they will pay the lien claimant

24-43  [such] that amount as a court of competent jurisdiction may adjudge to

24-44  have been secured by his lien, [with interest, costs and attorney’s fees.]

24-45  including the total amount awarded pursuant to NRS 108.237.


25-1  IN TESTIMONY WHEREOF, the principal and surety have executed this

25-2  bond at ................................, Nevada, on the ....... day of the month of .......

25-3  of the year .......

 

25-4  ....................................

25-5  (Signature of Principal)

25-6  (SURETY CORPORATION)

25-7  BY.....................................

25-8  (Its Attorney in Fact)

 

25-9  State of Nevada   }

25-10                                      }ss.

25-11  County of............ }

25-12  On ..... (month) ..... (day) ..... (year) before me, the undersigned, a notary

25-13  public of this county and state, personally appeared .................................

25-14  who acknowledged that he executed the foregoing instrument as principal

25-15  for the purposes therein mentioned and also personally appeared

25-16  ................................ known (or satisfactorily proved) to me to be the

25-17  attorney in fact of the [corporation] surety that executed the foregoing

25-18  instrument, known to me to be the person who executed that instrument on

25-19  behalf of the [corporation] surety therein named, and he acknowledged to

25-20  me that [that corporation] the surety executed the foregoing instrument.

 

25-21                                                                              .........................................

25-22                                      (Notary Public in and for

25-23                                        the County and State)

25-24  Sec. 46.  NRS 108.2417 is hereby amended to read as follows:

25-25  108.2417  1.  A petition for the release of a [mechanic’s] notice of

25-26  lien must be filed in the district court in the county in which the property

25-27  is located and set forth:

25-28  (a) The title of the cause, thus: “In the matter of the petition of

25-29  ................................ (name of petitioner) for release of [mechanic’s] notice

25-30  of lien of .............................. (name of [mechanic’s] lien claimant) upon

25-31  posting surety bond.”

25-32  (b) An allegation of the purchase of by payment of the premium for the

25-33  bond, and the dates of purchase and payment. A copy of the receipt for

25-34  payment of the premium for the bond must be attached to the petition.

25-35  (c) An allegation incorporating [any] by reference a true copy of the

25-36  bond, which copy must be attached to the petition.

25-37  (d) The name or names of the owner [or reputed owners] of the [land]

25-38  property subject to the notice of lien.

25-39  (e) A description of the [real] property subject to the notice of lien, and

25-40  the book and document number of the notice of lien as given by the county

25-41  recorder’s office[.] of the county in which the property is located.

25-42  (f) A prayer for an order releasing the notice of lien.

25-43  2.  The petitioner shall obtain an order from a judge of the district court

25-44  setting forth the time and date of the hearing on the petition, which time

25-45  and date must be at least [5] 15 days after the date of the order and not

25-46  more than [10] 30 days after the date of the order.


26-1    3.  A copy of the petition and a copy of the order must be served on the

26-2  lien claimant at least 2 days [before the date set for the hearing,] after the

26-3  court issues the order and must be served in the manner provided by law

26-4  for service of summons.

26-5    Sec. 47.  NRS 108.2419 is hereby amended to read as follows:

26-6    108.2419  1.  Upon the hearing, the court shall enter its order

26-7  releasing the [mechanic’s] notice of lien upon the petitioner’s [filing] :

26-8    (a) Filing in open court the original bond[, and introducing] which

26-9  must be in the form required by NRS 108.2415; and

26-10  (b) Introducing in evidence a receipt for payment of the premium.

26-11  2.  The entry of the order by the court must refer to the property which

26-12  is the subject of the notice of lien and the notice of lien itself, by document

26-13  number and book number, and must recite that the notice of lien is released

26-14  of record for all purposes to the same extent as if released of record by the

26-15  [lienor.] lien claimant.

26-16  3.  Upon entry of the order, the lien is released of record in its entirety

26-17  and for all purposes and the [real] property, the subject of the lien, released

26-18  from the encumbrances of the notice of lien.

26-19  4.  There is no appeal from the entry of the order and upon entry the

26-20  order is final for all purposes.

26-21  Sec. 48.  NRS 108.2421 is hereby amended to read as follows:

26-22  108.2421  1.  The lien claimant is entitled to bring an action against

26-23  [the lien claimant’s debtor and to join therein] , or if an action has been

26-24  commenced, the lien claimant is entitled to join in the pending action, the

26-25  principal and surety on the bond[.] and the lien claimant’s debtor. A

26-26  judgment for [the] a lien claimant on the bond may not be made against the

26-27  property. [The rights of the lien claimant include and the court may award

26-28  to him in that action:

26-29  (a) The amount found due to the lien claimant by the court;

26-30  (b) The cost of preparing and filing the lien claim, including attorney’s

26-31  fees, if any;

26-32  (c) The costs of the proceedings;

26-33  (d) Attorney’s fees for representation of the lien claimant in the

26-34  proceedings; and

26-35  (e) Interest at a rate established pursuant to NRS 99.040 from the date

26-36  found by the court that the sum was due.

26-37  2.  Proceedings pursuant to subsection 1 are entitled to priority of

26-38  hearing second only to criminal hearings. The plaintiff]

26-39  2.  At any time after the filing of a joint case conference report

26-40  pursuant to Rule 16.1 of the Nevada Rules of Civil Procedure, or, if the

26-41  case is designated by the court as complex litigation, after the approval of

26-42  the initial case management order by the court, each lien claimant in the

26-43  action may serve upon the adverse party a “demand for [30-day setting,” in

26-44  the proper form,] a preferential trial setting” and file the demand with the

26-45  clerk of the court. Upon filing, the clerk of the court shall, before the

26-46  Friday after the demand is filed, vacate a case or cases in a department of

26-47  the court and set the lien claimant’s case for hearing, on a day or days

26-48  certain, to be heard within [30] 60 days after the filing of the “demand for

26-49  [30-day] a preferential trial setting.” Only one such preferential setting


27-1  need be given by the court, unless the hearing date is vacated without

27-2  stipulation of counsel for the [plaintiff] lien claimant in writing. If the

27-3  hearing date is vacated without that stipulation, upon service and filing, a

27-4  new preferential trial setting must be given.

27-5    3.  A lien claimant shall, at the time of making his demand for a

27-6  preferential trial, and each other party to the preferential trial shall,

27-7  within 20 days after the lien claimant’s service of the demand, serve upon

27-8  all parties to the preferential trial the following documents and

27-9  information:

27-10  (a) A copy of all documents upon which the party intends to rely at the

27-11  time of the trial;

27-12  (b) A list of witnesses whom the party intends to call at the time of the

27-13  trial which must include for each witness:

27-14     (1) The name of the witness;

27-15     (2) The company identification and title of the witness; and

27-16     (3) A brief summary of the expected testimony of the witness;

27-17  (c) Any supplemental discovery responses as required by the Nevada

27-18  Rules of Civil Procedure;

27-19  (d) The identity of each person whom the party expects to call as an

27-20  expert witness at the trial, together with a statement of the substance of

27-21  the facts and opinions to which the expert witness is expected to testify

27-22  and a summary of the grounds for each opinion;

27-23  (e) Any expert reports not previously disclosed; and

27-24  (f) A detailed summary of all claims, offsets and defenses that the

27-25  party intends to rely upon at trial.

27-26  4.  Within 20 days after receipt of an opposing party’s identification

27-27  of an expert witness, a party who desires to do so must identify each

27-28  person whom the party expects to call as a rebuttal expert witness at trial,

27-29  and must provide a statement of the substance of the facts and opinions

27-30  to which the rebuttal expert witness is expected to testify and a summary

27-31  of the grounds for each opinion.

27-32  5.  A prevailing lien claimant on a claim against a bond must be

27-33  awarded the lienable amount plus the total amount that may be awarded

27-34  by the court pursuant to NRS 108.237.

27-35  Sec. 49.  NRS 108.2423 is hereby amended to read as follows:

27-36  108.2423  1.  By entering into a bond given pursuant to NRS

27-37  108.2415, the surety submits himself to the jurisdiction of the court in

27-38  which the bond is filed in the proceeding or release of the lien, and the

27-39  surety irrevocably appoints the clerk of that court as its agent upon whom

27-40  any papers affecting its liability on the bond may be served. [Its] The

27-41  liability of the surety may be enforced on motion without necessity of an

27-42  independent action. The motion and such notice of motion as the court

27-43  prescribes may be served on the clerk of the court, who shall forthwith mail

27-44  copies to the surety if his address is known.

27-45  2.  The motion described in subsection 1 must not be instituted until

27-46  [the lapse of] 30 days [following] after:

27-47  (a) If a notice of appeal from the judgment is not filed, the giving of

27-48  notice of entry of judgment in the action against the lien claimant’s debtor,

27-49  [if no notice of appeal from the judgment is filed, nor may the motion be


28-1  instituted until the lapse of 30 days following] or the giving of notice of

28-2  entry of judgment in an action against the principal and surety on the

28-3  bond, if the lien claimant’s debtor was not joined therein; or

28-4    (b) If an appeal has been taken from the judgment, the filing of the

28-5  remittitur from the supreme court . [, if an appeal has been taken from the

28-6  judgment.]

28-7    Sec. 50.  NRS 108.2425 is hereby amended to read as follows:

28-8    108.2425  1.  The lien claimant may, within [2] 15 days after the

28-9  service of a copy of the petition and a copy of the bond attached thereto,

28-10  file with the clerk of the court in the action a notice excepting to the

28-11  sufficiency of the surety on the bond, and shall, at the same time and

28-12  together with that notice, file an affidavit setting forth the grounds and

28-13  basis of the exceptions to the surety, and shall serve a copy of the notice

28-14  and a copy of the affidavit upon the attorney or the petitioner [on the same

28-15  date as] within 2 days after the date of filing. A hearing must be had upon

28-16  the justification of the surety at the same time as that set for the hearing on

28-17  the petition for the order to release the notice of lien.

28-18  2.  If , during the time a bond is posted pursuant to NRS 108.2415 to

28-19  108.2425, inclusive, the surety becomes unauthorized to transact surety

28-20  business in this state pursuant to NRS 679A.030, or should the surety’s

28-21  rating with Standard and Poor’s Ratings Services or A.M. Best Company

28-22  be downgraded to lower than an “A” rating, or if good cause otherwise

28-23  exists therefor, a lien claimant [fails to file and serve the notice and

28-24  affidavit within 2 days after the service of the petition for release of the

28-25  lien, he shall be deemed to have waived all objection to the justification

28-26  and sufficiency of the surety.] or other person having an interest in the

28-27  bond may apply to the district court in a pending action or commence an

28-28  action if none is pending for an order to require additional security, or to

28-29  change, substitute or add sureties, or to enforce or change any other

28-30  matter affecting the security provided by the bond. This section does not

28-31  authorize or require the reduction of any bond to an amount less than

28-32  1.5 times the amount of the lien claimant’s notice of lien. If the court

28-33  finds that the amount of the bond is insufficient to pay the total amount

28-34  that may be awarded by the court pursuant to NRS 108.237, the court

28-35  shall increase the amount of the bond to 1.5 times that amount. Any

28-36  surety who posts or consents to the posting of a surety bond shall remain

28-37  fully liable on the bond regardless of the payment or nonpayment of any

28-38  bond premium.

28-39  Sec. 51.  NRS 108.243 is hereby amended to read as follows:

28-40  108.243  1.  Any notice of lien may be assigned in the same manner

28-41  as any other chose in action after it has been perfected by recording.

28-42  2.  [No] An assignment of a lien [prior to recording shall] before

28-43  recording will not be effective until written notice of the assignment has

28-44  been given to the owner by the assignee. [Any such notice shall] The

28-45  notice will be sufficient if delivered in person or mailed by certified mail to

28-46  the [person named as owner in the building permit.] owner. After such

28-47  notice the assignee may perfect the lien in his own name.

28-48  3.  [Two] One or more lien claimants of the same class may assign

28-49  their notices of lien [claims] by written assignment, signed by each


29-1  assignor, to any other person or lien claimant of the same class, and the

29-2  assignee may commence and prosecute the action upon all of the notices of

29-3  lien [claims] in his own name[.] or in the name of the original lien

29-4  claimant.

29-5    4.  In the event that a claim for which a lien may be filed is assigned

29-6  before it is perfected, such an assignment [shall] must not discharge or

29-7  defeat the right to perfect [such] the lien, if [such] the claim is reassigned

29-8  to the lien claimant, and thereafter [such lien claim] the lien is timely

29-9  perfected.

29-10  Sec. 52.  NRS 108.2433 is hereby amended to read as follows:

29-11  108.2433  1.  Except as otherwise provided in subsection 2, a notice

29-12  of lien [of record upon real] upon the property provided for in NRS

29-13  108.221 to 108.246, inclusive, and sections 2 to 26, inclusive, of this act

29-14  may be discharged by an entry on the margin of the record thereof, signed

29-15  by the [lienor] lien claimant orhis personal representative or assignee in

29-16  the presence of the recorder or his deputy, acknowledging the satisfaction

29-17  of or value received for the notice of lien and the debt secured thereby. The

29-18  recorder or his deputy shall subscribe the entry as witness. The entry has

29-19  the same effect as a discharge or release of the notice of lien acknowledged

29-20  and recorded as provided by law. The recorder shall properly index each

29-21  marginal discharge.

29-22  2.  If the notice of lien has been recorded by a microfilm or other

29-23  photographic process, a marginal release may not be used and an

29-24  acknowledged discharge or release of the notice of lien must be recorded.

29-25  3.  If the recorder or his deputy is presented with a certificate executed

29-26  by the [lienor] lien claimant or his personal representative or assignee,

29-27  specifying that the notice of lien has been paid or otherwise satisfied or

29-28  discharged, the recorder or his deputy shall discharge the notice of lien

29-29  upon the record.

29-30  Sec. 53.  NRS 108.2437 is hereby amended to read as follows:

29-31  108.2437  1.  As soon as practicable, but not later than 10 days after a

29-32  notice of lien [of record upon real] upon the property pursuant to NRS

29-33  108.221 to 108.246, inclusive, and sections 2 to 26, inclusive, of this act is

29-34  fully satisfied or discharged, the [lienor] lien claimant shall cause to be

29-35  recorded a discharge or release of the notice of lien in substantially the

29-36  following form:

 

29-37  Discharge or Release of Notice of Lien

 

29-38  NOTICE IS HEREBY GIVEN THAT:

29-39     The undersigned did, on the ....... day of the month of ....... of the year

29-40  ......., record in Book ............, as Document No. ............, in the office of the

29-41  county recorder of ............. County, Nevada, its Notice of Lien, or has

29-42  otherwise given notice of his intention to hold [and claim] a lien upon the

29-43  following described property[,] or improvements, owned or purportedly

29-44  owned by ..............., [situated] located in the County of ............, State of

29-45  Nevada, to wit:

 

 


30-1  (Legal Description or Address of the Property[)] or Improvements)

 

30-2      NOW, THEREFORE, for valuable consideration the undersigned

30-3  does release, satisfy and discharge [the claim or] his notice of lien on the

30-4  property or improvements described above by reason of [such] this Notice

30-5  of Lien . [, or by reason of the work and labor on, or materials furnished

30-6  for, that property.]

 

30-7                                                                               ..............................................

30-8                    (Signature of [Lienor)] Lien Claimant)

 

30-9    2.  If the [lienor] lien claimant fails to comply with the provisions of

30-10  subsection 1, he is liable in a civil action to the owner of the [real]

30-11  property, his heirs or assigns for any actual damages caused by his failure

30-12  to comply with those provisions or $100, whichever is greater, and for a

30-13  reasonable attorney’s fee and the costs of bringing the action.

30-14  Sec. 54.  NRS 108.244 is hereby amended to read as follows:

30-15  108.244  A lien claimant or assignee of a lien claimant or claimants

30-16  may not file a complaint for foreclosure of his [mechanic’s] notice of lien

30-17  or the assigned [mechanic’s] notice of lien or [mechanics’ liens] notices of

30-18  lien until 30 days have expired immediately following the filing of his

30-19  [mechanic’s] notice of lien or following the filing of the assigned

30-20  [mechanic’s] notice of lien or the last of the assigned [mechanics’ liens.]

30-21  notices of lien. This provision [shall] does not apply to nor prohibit the

30-22  filing of any statement of fact constituting a lien or statements of fact

30-23  constituting a lien in an already filed action for foreclosure of

30-24  [mechanic’s] a notice of lien and to comply with the provisions of NRS

30-25  108.239.

30-26  Sec. 55.  NRS 108.245 is hereby amended to read as follows:

30-27  108.245  1.  Except as otherwise provided in subsection 5, every

30-28  [person, firm, partner-ship, corporation or other legal entity,] lien claimant,

30-29  other than one who performs only labor, who claims the benefit of NRS

30-30  108.221 to 108.246, inclusive, and sections 2 to 26, inclusive, of this act

30-31  shall[, within 31 days after the first delivery of material or performance of

30-32  work or services under his contract,] deliver in person or by certified mail

30-33  to the owner [or reputed owner of the property or to the person whose

30-34  name appears as owner on the building permit, if any, for] of the

30-35  improvement a preliminary notice of right to lien in substantially the

30-36  following form:

 

30-37  Preliminary Notice of Right to Lien to Owner of Materials

30-38  Supplied or Work [or Services] Performed

 

30-39  To: ...........................

30-40  (Owner’s name and address)

 

 

 


31-1    The undersigned notifies you that he has supplied materials or

31-2  performed work [or services] as follows:

31-3  ............................................................................   

31-4  (General description of materials[, work or services

31-5  and anticipated total value)] supplied or work performed)

31-6  for improvement of real property identified as (property description or

31-7  street address) under contract with (general contractor or subcontractor).

31-8  This is not a notice that the undersigned has not been or does not expect to

31-9  be paid, but a notice required by law that the undersigned may, at a future

31-10  date, [claim] record a notice of lien as provided by law against the property

31-11  or any improvement if the undersigned is not paid.

 

31-12                                                                              .........................................

31-13                                           [(] (Lien Claimant)

 

31-14  A subcontractor [or materialman under a subcontract] who gives such a

31-15  notice must also deliver in person or send by certified mail a copy of the

31-16  notice to [the general] his prime contractor for information only. The

31-17  failure by a subcontractor to deliver [such] the notices to the [general]

31-18  prime contractor is a ground for disciplinary proceedings against the

31-19  subcontractor under chapter 624 of NRS[.] but does not invalidate the

31-20  notice to the owner.

31-21  2.  Such a notice does not constitute a lien or give actual or constructive

31-22  notice of a lien for any purpose.

31-23  3.  No lien for materials or equipment furnished or for work [or

31-24  services] performed, except labor, may be perfected or enforced pursuant

31-25  to NRS 108.221 to 108.246, inclusive, [unless the] and sections 2 to 26,

31-26  inclusive, of this act for work, materials or equipment furnished more

31-27  than 31 days before:

31-28  (a) The date on which a preliminary notice of right to lien has been

31-29  given[.] as provided in this section; or

31-30  (b) The owner obtains notice or knowledge of the work, materials or

31-31  equipment the lien claimant furnished for the work of improvement.

31-32  4.  The notice need not be verified, sworn to or acknowledged.

31-33  5.  A [general] prime contractor or other person who contracts directly

31-34  with an owner or sells materials directly to an owner is not required to give

31-35  notice pursuant to this section.

31-36  [6.  As used in this section, “owner” does not include any person, firm

31-37  or corporation whose only interest in the real property is under a mortgage,

31-38  deed of trust or other security arrangement.]

31-39  Sec. 56.  NRS 108.246 is hereby amended to read as follows:

31-40  108.246  1.  Each [general] prime contractor shall, before execution of

31-41  a contract for construction, inform the [record] owner with whom he

31-42  intends to contract of the provisions of NRS 108.245 in substantially the

31-43  following form:

 

31-44  To:...........................

31-45  (Owner’s name and address)


32-1    [Section 108.245 of Nevada Revised Statutes,] The provisions of NRS

32-2  108.245, a part of the mechanics’ and materialmen’s lien law of the State

32-3  of Nevada, [requires,] require, for your information and protection from

32-4  hidden liens, that each person or other legal entity [which] who supplies

32-5  materials to or performs work [or services] on a construction project, other

32-6  than one who performs only labor, shall deliver to the owner a notice of the

32-7  materials and equipment supplied or the work [or services] performed.

32-8  You may receive [such] these notices in connection with the construction

32-9  project which you propose to undertake.

32-10  2.  Each [general] prime contractor shall deliver a copy of the

32-11  information required by subsection 1 to each subcontractor who

32-12  participates in the construction project.

32-13  3.  The failure of a [general] prime contractor so to inform owners and

32-14  subcontractors with whom he contracts is a ground for disciplinary

32-15  proceedings under chapter 624 of NRS . [.

32-16  4.  Each subcontractor who participates in the construction project shall

32-17  deliver a copy of each notice required by NRS 108.226 to the general

32-18  contractor. The failure of the subcontractor to deliver such notice to the

32-19  general contractor is a ground for disciplinary proceedings under chapter

32-20  624 of NRS.]

32-21  Sec. 57.  NRS 624.3016 is hereby amended to read as follows:

32-22  624.3016  The following acts or omissions, among others, constitute

32-23  cause for disciplinary action under NRS 624.300:

32-24  1.  Any fraudulent or deceitful act committed in the capacity of a

32-25  contractor.

32-26  2.  A conviction of a violation of NRS 624.730 or a felony or a crime

32-27  involving moral turpitude.

32-28  3.  Knowingly making a false statement in or relating to the recording

32-29  of a notice of lien pursuant to the provisions of NRS 108.226.

32-30  4.  Failure to give a notice required by NRS 108.227, 108.245 or

32-31  108.246.

32-32  5.  Failure to comply with NRS 597.713, 597.716 or 597.719 or any

32-33  regulations of the board governing contracts for the construction of

32-34  residential pools and spas.

32-35  6.  Failure to comply with NRS 624.600.

32-36  7.  Misrepresentation or the omission of a material fact, or the

32-37  commission of any other fraudulent or deceitful act, to obtain a license.

32-38  8.  Failure to pay an assessment required pursuant to NRS 624.470.

32-39  Sec. 58.  NRS 108.223, 108.2231and 108.224 are hereby repealed.

32-40  Sec. 59. Sections 25 and 26 of this act apply only to agreements

32-41  entered into after October 1, 2001.

 


 

 

33-1  TEXT OF REPEALED SECTIONS

 

 

33-2    108.223  Lien on lot or tract of land for improvements made at

33-3   request of owner. Any person who, at the request of the owner of any

33-4   lot or tract of land, or his agent, grades, fills in, installs a system for

33-5   irrigation, seeds, plants, lays sod, landscapes or otherwise improves the lot

33-6   or tract of land, or the street in front of or adjoining it, has a lien upon it

33-7   for the work done and materials furnished.

33-8    108.2231  Lien on real property, building, structure or

33-9   improvement thereon for services rendered at request of owner.

33-10  1.  Any person who, at the request of the owner of any real property,

33-11   building, structure or improvement thereon, or his agent, performs services

33-12   as an engineer, land surveyor or geologist in relation to that real property,

33-13   building, structure or improvement thereon, has a lien upon it for the work

33-14   done and materials furnished.

33-15  2.  The amount of the lien is:

33-16  (a) If the parties entered into a contract, the unpaid balance of the price

33-17   agreed upon; or

33-18  (b) In the absence of a contract, an amount equal to the fair market

33-19   value of the labor performed or material furnished, including a reasonable

33-20   allowance for overhead and profit.

33-21  108.224  Land subject to lien. The land occupied by any building or

33-22   other superstructure, railroad, tramway, toll road, canal, water ditch,

33-23   flume, aqueduct or reservoir, bridge or fence, together with a convenient

33-24   space about the same, or so much as may be required for the convenient

33-25   use and occupation thereof, to be determined by the court on rendering

33-26   judgment, is also subject to the lien, if at the commencement of the work,

33-27   or of the furnishing of the materials for the same, the land belonged to the

33-28   person who caused the building, improvement or structure to be

33-29   constructed, altered or repaired; but if such person owned less than a fee

33-30   simple estate in such land, then only his interest therein is subject to such

33-31   lien.

 

33-32  H