Assembly Bill No. 295–Assemblymen McClain, Claborn, Ohrenschall, Atkinson, Gibbons, Anderson, Andonov, Arberry, Beers, Carpenter, Christensen, Collins, Conklin, Giunchigliani, Grady, Griffin, Hettrick, Knecht, Koivisto, Manendo, Parks, Pierce, Sherer and Williams (by request)

 

March 13, 2003

____________

 

Referred to Committee on Government Affairs

 

SUMMARY—Revises provisions governing criteria for determining qualification of bidders on public works of local governments. (BDR 28‑747)

 

FISCAL NOTE:  Effect on Local Government: Yes.

                           Effect on the State: No.

 

~

 

EXPLANATION – Matter in bolded italics is new; matter between brackets [omitted material] is material to be omitted.

Green numbers along left margin indicate location on the printed bill (e.g., 5-15 indicates page 5, line 15).

 

AN ACT relating to public works; allowing the governing body of a local government, in certain circumstances, to deem a person to be qualified to bid on contracts for public works of the local government; establishing requirements relating to the advertisement of the acceptance of certain applications to qualify as a bidder on a contract for a public work; revising the provisions governing the criteria for determining the qualification of bidders on public works of local governments; expanding the circumstances in which a subcontractor who is named in a bid on a contract for a public work of a local government may be substituted; and providing other matters properly relating thereto.

 

THE PEOPLE OF THE STATE OF NEVADA, REPRESENTED IN

SENATE AND ASSEMBLY, DO ENACT AS FOLLOWS:

 

 

 


2-1  Section 1.  Chapter 338 of NRS is hereby amended by adding

2-2  thereto the provisions set forth as sections 2 and 3 of this act.

2-3  Sec. 2.  In lieu of adopting criteria pursuant to NRS 338.1377

2-4  and determining the qualification of bidders pursuant to NRS

2-5  338.1379, the governing body of a local government may deem a

2-6  person to be qualified to bid on:

2-7  1.  Contracts for public works of the local government if the

2-8  person has been determined by:

2-9  (a) The State Public Works Board pursuant to NRS 338.1379

2-10  to be qualified to bid on contracts for public works of the State

2-11  pursuant to the criteria set forth in NRS 338.1375; or

2-12      (b) The governing body of another local government pursuant

2-13  to NRS 338.1379 to be qualified to bid on contracts for public

2-14  works of that local government pursuant to the criteria set forth in

2-15  NRS 338.1377.

2-16      2.  A contract for a public work of the local government if:

2-17      (a) The person has been determined by the Department of

2-18  Transportation pursuant to NRS 408.333 to be qualified to bid on

2-19  the contract for the public work;

2-20      (b) The public work will be owned, operated or maintained by

2-21  the Department of Transportation after the public work is

2-22  constructed by the local government; and

2-23      (c) The Department of Transportation requested that bidders

2-24  on the contract for the public work be qualified to bid on the

2-25  contract pursuant to NRS 408.333.

2-26      Sec. 3.  1.  Before the governing body of a local government

2-27  accepts applications pursuant to NRS 338.1379, the governing

2-28  body must, in accordance with subsection 2, advertise in a

2-29  newspaper that is:

2-30      (a) Qualified pursuant to the provisions of chapter 238 of

2-31  NRS; and

2-32      (b) Published in a county in which the contracts for the

2-33  potential public works will be performed or, if no qualified

2-34  newspaper is published in that county, published in a qualified

2-35  newspaper that is published in the State of Nevada and which has

2-36  a general circulation in the county in which the contracts for the

2-37  potential public works will be performed.

2-38      2.  An advertisement required pursuant to subsection 1:

2-39      (a) Must be published at least once not less than 21 days

2-40  before applications are to be submitted to the governing body; and

2-41      (b) Must include:

2-42          (1) A description of the potential public works for which

2-43  applications to qualify as a bidder are being accepted;

2-44          (2) The time and place at which applications are to be

2-45  submitted to the governing body;


3-1       (3) The place at which applications may be obtained; and

3-2       (4) Any other information that the governing body deems

3-3  necessary.

3-4  Sec. 4.  NRS 338.010 is hereby amended to read as follows:

3-5  338.010  As used in this chapter:

3-6  1.  “Day labor” means all cases where public bodies, their

3-7  officers, agents or employees, hire, supervise and pay the wages

3-8  thereof directly to a workman or workmen employed by them on

3-9  public works by the day and not under a contract in writing.

3-10      2.  “Design-build contract” means a contract between a public

3-11  body and a design-build team in which the design-build team agrees

3-12  to design and construct a public work.

3-13      3.  “Design-build team” means an entity that consists of:

3-14      (a) At least one person who is licensed as a general engineering

3-15  contractor or a general building contractor pursuant to chapter 624

3-16  of NRS; and

3-17      (b) For a public work that consists of:

3-18          (1) A building and its site, at least one person who holds a

3-19  certificate of registration to practice architecture pursuant to chapter

3-20  623 of NRS.

3-21          (2) Anything other than a building and its site, at least one

3-22  person who holds a certificate of registration to practice architecture

3-23  pursuant to chapter 623 of NRS or is licensed as a professional

3-24  engineer pursuant to chapter 625 of NRS.

3-25      4.  “Design professional” means:

3-26      (a) A person who is licensed as a professional engineer pursuant

3-27  to chapter 625 of NRS;

3-28      (b) A person who is licensed as a professional land surveyor

3-29  pursuant to chapter 625 of NRS;

3-30      (c) A person who holds a certificate of registration to engage in

3-31  the practice of architecture pursuant to chapter 623 of NRS;

3-32      (d) A person who holds a certificate of registration to engage in

3-33  the practice of landscape architecture pursuant to chapter 623A of

3-34  NRS; or

3-35      (e) A business entity that engages in the practice of professional

3-36  engineering, land surveying, architecture or landscape architecture.

3-37      5.  “Eligible bidder” means a person who is:

3-38      (a) Found to be a responsible and responsive contractor by a

3-39  local government which requests bids for a public work in

3-40  accordance with paragraph (b) of subsection 1 of NRS 338.1373; or

3-41      (b) Determined by a public body which awarded a contract for a

3-42  public work pursuant to NRS 338.1375 to 338.139, inclusive, to be

3-43  qualified to bid on that contract pursuant to NRS 338.1379 or

3-44  section 2 of this act or was exempt from meeting such qualifications

3-45  pursuant to NRS 338.1383.


4-1  6.  “General contractor” means a person who is licensed to

4-2  conduct business in one, or both, of the following branches of the

4-3  contracting business:

4-4  (a) General engineering contracting, as described in subsection 2

4-5  of NRS 624.215.

4-6  (b) General building contracting, as described in subsection 3 of

4-7  NRS 624.215.

4-8  7.  “Local government” means every political subdivision or

4-9  other entity which has the right to levy or receive money from ad

4-10  valorem or other taxes or any mandatory assessments, and includes,

4-11  without limitation, counties, cities, towns, boards, school districts

4-12  and other districts organized pursuant to chapters 244A, 309, 318,

4-13  379, 474, 541, 543 and 555 of NRS, NRS 450.550 to 450.750,

4-14  inclusive, and any agency or department of a county or city which

4-15  prepares a budget separate from that of the parent political

4-16  subdivision.

4-17      8.  “Offense” means failing to:

4-18      (a) Pay the prevailing wage required pursuant to this chapter;

4-19      (b) Pay the contributions for unemployment compensation

4-20  required pursuant to chapter 612 of NRS;

4-21      (c) Provide and secure compensation for employees required

4-22  pursuant to chapters 616A to 617, inclusive, of NRS; or

4-23      (d) Comply with subsection 4 or 5 of NRS 338.070.

4-24      9.  “Prime contractor” means a person who:

4-25      (a) Contracts to construct an entire project;

4-26      (b) Coordinates all work performed on the entire project;

4-27      (c) Uses his own workforce to perform all or a part of the

4-28  construction, repair or reconstruction of the project; and

4-29      (d) Contracts for the services of any subcontractor or

4-30  independent contractor or is responsible for payment to any

4-31  contracted subcontractors or independent contractors.

4-32  The term includes, without limitation, a general contractor or a

4-33  specialty contractor who is authorized to bid on a project pursuant to

4-34  NRS 338.139 or 338.148.

4-35      10.  “Public body” means the State, county, city, town, school

4-36  district or any public agency of this state or its political subdivisions

4-37  sponsoring or financing a public work.

4-38      11.  “Public work” means any project for the new construction,

4-39  repair or reconstruction of:

4-40      (a) A project financed in whole or in part from public money

4-41  for:

4-42          (1) Public buildings;

4-43          (2) Jails and prisons;

4-44          (3) Public roads;

4-45          (4) Public highways;


5-1       (5) Public streets and alleys;

5-2       (6) Public utilities which are financed in whole or in part by

5-3  public money;

5-4       (7) Publicly owned water mains and sewers;

5-5       (8) Public parks and playgrounds;

5-6       (9) Public convention facilities which are financed at least in

5-7  part with public funds; and

5-8       (10) All other publicly owned works and property whose cost

5-9  as a whole exceeds $20,000. Each separate unit that is a part of a

5-10  project is included in the cost of the project to determine whether a

5-11  project meets that threshold.

5-12      (b) A building for the University and Community College

5-13  System of Nevada of which 25 percent or more of the costs of the

5-14  building as a whole are paid from money appropriated by this state

5-15  or from federal money.

5-16      12.  “Specialty contractor” means a person who is licensed to

5-17  conduct business as described in subsection 4 of NRS 624.215.

5-18      13.  “Stand-alone underground utility project” means an

5-19  underground utility project that is not integrated into a larger

5-20  project, including, without limitation:

5-21      (a) An underground sewer line or an underground pipeline for

5-22  the conveyance of water, including facilities appurtenant thereto;

5-23  and

5-24      (b) A project for the construction or installation of a storm drain,

5-25  including facilities appurtenant thereto,

5-26  that is not located at the site of a public work for the design and

5-27  construction of which a public body is authorized to contract with a

5-28  design-build team pursuant to subsection 2 of NRS 338.1711.

5-29      14.  “Wages” means:

5-30      (a) The basic hourly rate of pay; and

5-31      (b) The amount of pension, health and welfare, vacation and

5-32  holiday pay, the cost of apprenticeship training or other similar

5-33  programs or other bona fide fringe benefits which are a benefit to

5-34  the workman.

5-35      15.  “Workman” means a skilled mechanic, skilled workman,

5-36  semiskilled mechanic, semiskilled workman or unskilled workman.

5-37  The term does not include a design professional.

5-38      Sec. 5.  NRS 338.1373 is hereby amended to read as follows:

5-39      338.1373  1.  A local government shall award a contract for

5-40  the construction, alteration or repair of a public work pursuant to the

5-41  provisions of:

5-42      (a) NRS 338.1377 to 338.139, inclusive [;] , and sections 2 and

5-43  3 of this act; or

5-44      (b) NRS 338.143 to 338.148, inclusive.


6-1  2.  The provisions of NRS 338.1375 to 338.1383, inclusive, and

6-2  338.139 do not apply with respect to contracts for the construction,

6-3  reconstruction, improvement and maintenance of highways that are

6-4  awarded by the Department of Transportation pursuant to NRS

6-5  408.313 to 408.433, inclusive.

6-6  Sec. 6. NRS 338.1377 is hereby amended to read as follows:

6-7  338.1377  [1.] Except as otherwise provided in NRS 338.1383

6-8  [,] and section 2 of this act, the governing body of each local

6-9  government that sponsors or finances a public work shall adopt the

6-10  following criteria for [the qualification of bidders] determining

6-11  whether a person who has applied pursuant to NRS 338.1379 is

6-12  qualified to bid on contracts for public works of the local

6-13  government[. The governing body shall use the criteria to determine

6-14  the qualification of bidders on contracts for public works of the local

6-15  government.

6-16      2.  Before adopting criteria pursuant to this section, the

6-17  governing body of a local government shall hold at least one public

6-18  hearing to solicit and evaluate public opinion regarding the criteria

6-19  to be adopted. Notice of such a hearing must be provided by mail at

6-20  least 10 days before the hearing to:

6-21      (a) Construction trade associations in this state; and

6-22      (b) Labor unions representing trades in the building industry in

6-23  this state.

6-24      3.  The criteria adopted by a governing body pursuant to this

6-25  section to determine whether an applicant is qualified to bid on a

6-26  contract for a public work:

6-27      (a) Must be adopted in such a form that the determination of

6-28  whether an applicant is qualified to bid on a contract for a public

6-29  work does not require or allow the exercise of discretion by any one

6-30  person.

6-31      (b) May include only:

6-32          (1) The financial ability of the applicant to perform a

6-33  contract;

6-34          (2) The principal personnel of the applicant;

6-35          (3)] :

6-36      1.  Whether the applicant possesses a valid contractor’s

6-37  license of a class corresponding to the work to be required by the

6-38  local government;

6-39      2.  Whether the applicant has the ability to obtain the

6-40  necessary bonding for the work to be required by the local

6-41  government;

6-42      3.  Whether the applicant has successfully completed one or

6-43  more projects during the 5 years immediately preceding the date of

6-44  application of similar size, scope or type as the work to be required

6-45  by the local government;


7-1  4.  Whether the principal personnel employed by the applicant

7-2  have the necessary professional qualifications and experience for

7-3  the work to be required by the local government;

7-4  5.  Whether the applicant has breached any contracts with a

7-5  public agency or person in this state or any other state[; and

7-6       (4)] during the 5 years immediately preceding the date of

7-7  application;

7-8  6.  Whether the applicant has been disqualified from being

7-9  awarded a contract pursuant to NRS 338.017 or 338.1387[.] ;

7-10      7.  Whether the applicant has been convicted of a violation for

7-11  discrimination in employment during the 2 years immediately

7-12  preceding the date of application;

7-13      8.  Whether the applicant has the ability to obtain and

7-14  maintain insurance coverage for public liability and property

7-15  damage within limits sufficient to protect the applicant and all the

7-16  subcontractors of the applicant from claims for personal injury,

7-17  accidental death and damage to property that may arise in

7-18  connection with the work to be required by the local government;

7-19      9.  Whether the applicant has established a safety program

7-20  that complies with the requirements of chapter 618 of NRS;

7-21      10.  Whether the applicant has been disciplined or fined by

7-22  the State Contractors’ Board or another state or federal agency for

7-23  conduct that relates to the ability of the applicant to perform the

7-24  work to be required by the local government;

7-25      11.  Whether, during the 5 years immediately preceding the

7-26  date of application, the applicant has filed as a debtor under the

7-27  provisions of the United States Bankruptcy Code;

7-28      12.  Whether the application of the applicant is truthful and

7-29  complete; and

7-30      13.  Whether, during the 5 years immediately preceding the

7-31  date of application, the applicant has, as a result of causes within

7-32  the control of the applicant or a subcontractor or supplier of the

7-33  applicant, failed to perform any contract:

7-34      (a) In the manner specified by the contract and any change

7-35  orders initiated or approved by the person or governmental entity

7-36  that awarded the contract or its authorized representative;

7-37      (b) Within the time specified by the contract unless extended

7-38  by the person or governmental entity that awarded the contract or

7-39  its authorized representative; or

7-40      (c) For the amount of money specified in the contract or as

7-41  modified by any change orders initiated or approved by the person

7-42  or governmental entity that awarded the contract or its authorized

7-43  representative.

7-44  Evidence of the failures described in this subsection may include,

7-45  without limitation, the assessment of liquidated damages against


8-1  the applicant, the forfeiture of any bonds posted by the applicant,

8-2  an arbitration award granted against the applicant or a decision

8-3  by a court of law against the applicant.

8-4  Sec. 7.  NRS 338.1379 is hereby amended to read as follows:

8-5  338.1379  1.  Except as otherwise provided in NRS 338.1383

8-6  [,] and section 2 of this act, a person who wishes to qualify as a

8-7  bidder on a contract for a public work must submit an application to

8-8  the State Public Works Board or the governing body.

8-9  2.  Upon receipt of an application pursuant to subsection 1, the

8-10  State Public Works Board or the governing body shall:

8-11      (a) Investigate the applicant to determine whether he is qualified

8-12  to bid on a contract; and

8-13      (b) After conducting the investigation, determine whether the

8-14  applicant is qualified to bid on a contract. The determination must

8-15  be made within 30 days after receipt of the application.

8-16      3.  The State Public Works Board or the governing body shall

8-17  notify each applicant in writing of its determination. If an

8-18  application is denied, the notice must set forth the reasons for the

8-19  denial and inform the applicant of his right to a hearing pursuant to

8-20  NRS 338.1381.

8-21      4.  The State Public Works Board or the governing body of a

8-22  local government may determine an applicant is qualified to bid:

8-23      (a) On a specific project;

8-24      (b) On more than one project over a period of 12 months; or

8-25      (c) On more than one project over a period of 24 months.

8-26      5.  The State Public Works Board shall not use any criteria

8-27  other than criteria adopted by regulation pursuant to NRS 338.1375

8-28  in determining whether to approve or deny an application.

8-29      6.  The governing body of a local government shall not use any

8-30  criteria other than the criteria described in NRS 338.1377 in

8-31  determining whether to approve or deny an application.

8-32      7.  Financial information and other data pertaining to the net

8-33  worth of an applicant which is gathered by or provided to the State

8-34  Public Works Board or a governing body to determine the financial

8-35  ability of an applicant to perform a contract is confidential and not

8-36  open to public inspection.

8-37      Sec. 8.  NRS 338.1383 is hereby amended to read as follows:

8-38      338.1383  [If] Except as otherwise provided in section 2 of this

8-39  act, if a local government does not adopt criteria for the

8-40  qualification of bidders on a public work pursuant to NRS 338.1377,

8-41  the governing body may only accept a bid on a contract for a public

8-42  work from a person who holds:

8-43      1.  An unlimited contractor’s license issued by the State

8-44  Contractors’ Board in the branch of general engineering contracting

8-45  or general building contracting, or in both branches, and:


9-1  (a) At the time he submits his bid, he provides a bid bond equal

9-2  to 10 percent of the amount of the bid; and

9-3  (b) At the time the contract is awarded, he provides a

9-4  performance bond, a labor and material bond and a guaranty bond,

9-5  each equal to 100 percent of the amount of the contract; or

9-6  2.  A contractor’s license issued by the State Contractors’ Board

9-7  that is designated in any classification if he:

9-8  (a) Has, in the 5 years immediately preceding the submission of

9-9  the bid, been found to be a responsible contractor in the

9-10  classification in which his contractor’s license is designated;

9-11      (b) Provides a bid bond, a performance bond, a guaranty bond,

9-12  and a labor and material bond in such amounts as the governing

9-13  body may require; and

9-14      (c) Employs a person determined by the State Contractors’

9-15  Board to be qualified to supervise each classification of construction

9-16  upon which the person submitting the bid is bidding.

9-17      Sec. 9.  NRS 338.1385 is hereby amended to read as follows:

9-18      338.1385  1.  Except as otherwise provided in subsection 7

9-19  and NRS 338.1906 and 338.1907, this state, or a local government

9-20  that awards a contract for the construction, alteration or repair of a

9-21  public work in accordance with paragraph (a) of subsection 1 of

9-22  NRS 338.1373, or a public officer, public employee or other person

9-23  responsible for awarding a contract for the construction, alteration

9-24  or repair of a public work who represents the State or the local

9-25  government, shall not:

9-26      (a) Commence such a project for which the estimated cost

9-27  exceeds $100,000 unless it advertises in a newspaper of general

9-28  circulation in this state for bids for the project; or

9-29      (b) Divide such a project into separate portions to avoid the

9-30  requirements of paragraph (a).

9-31      2.  Except as otherwise provided in subsection 7, a public body

9-32  that maintains a list of properly licensed contractors who are

9-33  interested in receiving offers to bid on public works projects for

9-34  which the estimated cost is more than $25,000 but less than

9-35  $100,000 shall solicit bids from not more than three of the

9-36  contractors on the list for a contract of that value for the

9-37  construction, alteration or repair of a public work. The public body

9-38  shall select contractors from the list in such a manner as to afford

9-39  each contractor an equal opportunity to bid on a public works

9-40  project. A properly licensed contractor must submit a written

9-41  request annually to the public body to remain on the list. Offers for

9-42  bids which are made pursuant to this subsection must be sent by

9-43  certified mail.

9-44      3.  Each advertisement for bids must include a provision that

9-45  sets forth:


10-1      (a) The requirement that a contractor must be qualified pursuant

10-2  to NRS 338.1379 or section 2 of this act to bid on the contract or

10-3  must be exempt from meeting such qualifications pursuant to NRS

10-4  338.1383; and

10-5      (b) The period during which an application to qualify as a bidder

10-6  on the contract must be submitted.

10-7      4.  Approved plans and specifications for the bids must be on

10-8  file at a place and time stated in the advertisement for the inspection

10-9  of all persons desiring to bid thereon and for other interested

10-10  persons. Contracts for the project must be awarded on the basis of

10-11  bids received.

10-12     5.  Any bids received in response to an advertisement for bids

10-13  may be rejected if the person responsible for awarding the contract

10-14  determines that:

10-15     (a) The bidder is not a qualified bidder pursuant to NRS

10-16  338.1379 [,] or section 2 of this act, unless the bidder is exempt

10-17  from meeting such qualifications pursuant to NRS 338.1383;

10-18     (b) The bidder is not responsive;

10-19     (c) The quality of the services, materials, equipment or labor

10-20  offered does not conform to the approved plan or specifications; or

10-21     (d) The public interest would be served by such a rejection.

10-22     6.  Before the State or a local government may commence a

10-23  project subject to the provisions of this section, based upon a

10-24  determination that the public interest would be served by rejecting

10-25  any bids received in response to an advertisement for bids, it shall

10-26  prepare and make available for public inspection a written statement

10-27  containing:

10-28     (a) A list of all persons, including supervisors, whom the State

10-29  or the local government intends to assign to the project, together

10-30  with their classifications and an estimate of the direct and indirect

10-31  costs of their labor;

10-32     (b) A list of all equipment that the State or the local government

10-33  intends to use on the project, together with an estimate of the

10-34  number of hours each item of equipment will be used and the hourly

10-35  cost to use each item of equipment;

10-36     (c) An estimate of the cost of administrative support for the

10-37  persons assigned to the project;

10-38     (d) An estimate of the total cost of the project; and

10-39     (e) An estimate of the amount of money the State or the local

10-40  government expects to save by rejecting the bids and performing the

10-41  project itself.

10-42     7.  This section does not apply to:

10-43     (a) Any utility subject to the provisions of chapter 318 or 710 of

10-44  NRS;


11-1      (b) Any work of construction, reconstruction, improvement and

11-2  maintenance of highways subject to NRS 408.323 or 408.327;

11-3      (c) Normal maintenance of the property of a school district;

11-4      (d) The Las Vegas Valley Water District created pursuant to

11-5  chapter 167, Statutes of Nevada 1947, the Moapa Valley Water

11-6  District created pursuant to chapter 477, Statutes of Nevada 1983 or

11-7  the Virgin Valley Water District created pursuant to chapter 100,

11-8  Statutes of Nevada 1993; or

11-9      (e) The design and construction of a public work for which a

11-10  public body contracts with a design-build team pursuant to NRS

11-11  338.1711 to 338.1727.

11-12     Sec. 10.  NRS 338.1385 is hereby amended to read as follows:

11-13     338.1385  1.  Except as otherwise provided in subsection 8,

11-14  this state, or a local government that awards a contract for the

11-15  construction, alteration or repair of a public work in accordance with

11-16  paragraph (a) of subsection 1 of NRS 338.1373, or a public officer,

11-17  public employee or other person responsible for awarding a contract

11-18  for the construction, alteration or repair of a public work who

11-19  represents the State or the local government, shall not:

11-20     (a) Commence such a project for which the estimated cost

11-21  exceeds $100,000 unless it advertises in a newspaper of general

11-22  circulation in this state for bids for the project; or

11-23     (b) Divide such a project into separate portions to avoid the

11-24  requirements of paragraph (a).

11-25     2.  Except as otherwise provided in subsection 8, a public body

11-26  that maintains a list of properly licensed contractors who are

11-27  interested in receiving offers to bid on public works projects for

11-28  which the estimated cost is more than $25,000 but less than

11-29  $100,000 shall solicit bids from not more than three of the

11-30  contractors on the list for a contract of that value for the

11-31  construction, alteration or repair of a public work. The public body

11-32  shall select contractors from the list in such a manner as to afford

11-33  each contractor an equal opportunity to bid on a public works

11-34  project. A properly licensed contractor must submit a written

11-35  request annually to the public body to remain on the list. Offers for

11-36  bids which are made pursuant to this subsection must be sent by

11-37  certified mail.

11-38     3.  Each advertisement for bids must include a provision that

11-39  sets forth:

11-40     (a) The requirement that a contractor must be qualified pursuant

11-41  to NRS 338.1379 or section 2 of this act to bid on the contract or

11-42  must be exempt from meeting such qualifications pursuant to NRS

11-43  338.1383; and

11-44     (b) The period during which an application to qualify as a bidder

11-45  on the contract must be submitted.


12-1      4.  Approved plans and specifications for the bids must be on

12-2  file at a place and time stated in the advertisement for the inspection

12-3  of all persons desiring to bid thereon and for other interested

12-4  persons. Contracts for the project must be awarded on the basis of

12-5  bids received.

12-6      5.  Any bids received in response to an advertisement for bids

12-7  may be rejected if the person responsible for awarding the contract

12-8  determines that:

12-9      (a) The bidder is not a qualified bidder pursuant to NRS

12-10  338.1379 [,] or section 2 of this act, unless the bidder is exempt

12-11  from meeting such qualifications pursuant to NRS 338.1383;

12-12     (b) The bidder is not responsive;

12-13     (c) The quality of the services, materials, equipment or labor

12-14  offered does not conform to the approved plan or specifications; or

12-15     (d) The public interest would be served by such a rejection.

12-16     6.  Before the State or a local government may commence a

12-17  project subject to the provisions of this section, based upon a

12-18  determination that the public interest would be served by rejecting

12-19  any bids received in response to an advertisement for bids, it shall

12-20  prepare and make available for public inspection a written statement

12-21  containing:

12-22     (a) A list of all persons, including supervisors, whom the State

12-23  or the local government intends to assign to the project, together

12-24  with their classifications and an estimate of the direct and indirect

12-25  costs of their labor;

12-26     (b) A list of all equipment that the State or the local government

12-27  intends to use on the project, together with an estimate of the

12-28  number of hours each item of equipment will be used and the hourly

12-29  cost to use each item of equipment;

12-30     (c) An estimate of the cost of administrative support for the

12-31  persons assigned to the project;

12-32     (d) An estimate of the total cost of the project; and

12-33     (e) An estimate of the amount of money the State or the local

12-34  government expects to save by rejecting the bids and performing the

12-35  project itself.

12-36     7.  In preparing the estimated cost of a project pursuant to

12-37  subsection 6, the State or a local government must include the fair

12-38  market value of, or, if known, the actual cost of, all materials,

12-39  supplies, labor and equipment to be used for the project.

12-40     8.  This section does not apply to:

12-41     (a) Any utility subject to the provisions of chapter 318 or 710 of

12-42  NRS;

12-43     (b) Any work of construction, reconstruction, improvement and

12-44  maintenance of highways subject to NRS 408.323 or 408.327;

12-45     (c) Normal maintenance of the property of a school district; or


13-1      (d) The Las Vegas Valley Water District created pursuant to

13-2  chapter 167, Statutes of Nevada 1947, the Moapa Valley Water

13-3  District created pursuant to chapter 477, Statutes of Nevada 1983 or

13-4  the Virgin Valley Water District created pursuant to chapter 100,

13-5  Statutes of Nevada 1993; or

13-6      (e) The design and construction of a public work for which a

13-7  public body contracts with a design-build team pursuant to NRS

13-8  338.1711 to 338.1727, inclusive.

13-9      Sec. 11.  NRS 338.1387 is hereby amended to read as follows:

13-10     338.1387  1.  A public body awarding a contract for a public

13-11  work shall not award the contract to a person who, at the time of the

13-12  bid, is not properly licensed under the provisions of chapter 624 of

13-13  NRS or if the contract would exceed the limit of his license. A

13-14  subcontractor named by the contractor who is not properly licensed

13-15  for that portion of the work shall be deemed unacceptable. If the

13-16  subcontractor is deemed unacceptable, the contractor shall provide

13-17  an acceptable subcontractor before the award of the contract.

13-18     2.  If, after awarding the contract, the public body discovers that

13-19  the person to whom the contract was awarded is not licensed, or that

13-20  the contract would exceed his license, the public body shall

13-21  reject the bid and may accept the next lowest bid for that public

13-22  work from a responsive bidder who was determined by the public

13-23  body to be a qualified bidder pursuant to NRS 338.1379 or section 2

13-24  of this act or was exempt from meeting such qualifications pursuant

13-25  to NRS 338.1373 or 338.1383 without requiring that new bids be

13-26  submitted.

13-27     Sec. 12.  NRS 338.1389 is hereby amended to read as follows:

13-28     338.1389  1.  Except as otherwise provided in NRS 338.1385

13-29  and 338.1711 to 338.1727, inclusive, a public body shall award a

13-30  contract for a public work to the contractor who submits the best

13-31  bid.

13-32     2.  Except as otherwise provided in subsection 10 or limited by

13-33  subsection 11, for the purposes of this section, a contractor who:

13-34     (a) Has been determined by the public body to be a qualified

13-35  bidder pursuant to NRS 338.1379 or section 2 of this act or is

13-36  exempt from meeting such requirements pursuant to NRS 338.1373

13-37  or 338.1383; and

13-38     (b) At the time he submits his bid, provides to the public body a

13-39  copy of a certificate of eligibility to receive a preference in bidding

13-40  on public works issued to him by the State Contractors’ Board

13-41  pursuant to subsection 3 or 4,

13-42  shall be deemed to have submitted a better bid than a competing

13-43  contractor who has not provided a copy of such a valid certificate of

13-44  eligibility if the amount of his bid is not more than 5 percent higher

13-45  than the amount bid by the competing contractor.


14-1      3.  The State Contractors’ Board shall issue a certificate of

14-2  eligibility to receive a preference in bidding on public works to a

14-3  general contractor who is licensed pursuant to the provisions of

14-4  chapter 624 of NRS and submits to the Board an affidavit from a

14-5  certified public accountant setting forth that the general contractor

14-6  has, while licensed as a general contractor in this state:

14-7      (a) Paid directly, on his own behalf:

14-8          (1) The sales and use taxes imposed pursuant to chapters

14-9  372, 374 and 377 of NRS on materials used for construction in this

14-10  state, including, without limitation, construction that is undertaken

14-11  or carried out on land within the boundaries of this state that is

14-12  managed by the Federal Government or is on an Indian reservation

14-13  or Indian colony, of not less than $5,000 for each consecutive 12-

14-14  month period for 60 months immediately preceding the submission

14-15  of the affidavit from the certified public accountant;

14-16         (2) The governmental services tax imposed pursuant to

14-17  chapter 371 of NRS on the vehicles used in the operation of his

14-18  business in this state of not less than $5,000 for each consecutive

14-19  12-month period for 60 months immediately preceding the

14-20  submission of the affidavit from the certified public accountant; or

14-21         (3) Any combination of such sales and use taxes and

14-22  governmental services tax; or

14-23     (b) Acquired, by purchase, inheritance, gift or transfer through a

14-24  stock option plan, all the assets and liabilities of a viable, operating

14-25  construction firm that possesses a:

14-26         (1) License as a general contractor pursuant to the provisions

14-27  of chapter 624 of NRS; and

14-28         (2) Certificate of eligibility to receive a preference in bidding

14-29  on public works.

14-30     4.  The State Contractors’ Board shall issue a certificate of

14-31  eligibility to receive a preference in bidding on public works to a

14-32  specialty contractor who is licensed pursuant to the provisions of

14-33  chapter 624 of NRS and submits to the Board an affidavit from a

14-34  certified public accountant setting forth that the specialty contractor

14-35  has, while licensed as a specialty contractor in this state:

14-36     (a) Paid directly, on his own behalf:

14-37         (1) The sales and use taxes pursuant to chapters 372, 374 and

14-38  377 of NRS on materials used for construction in this state,

14-39  including, without limitation, construction that is undertaken or

14-40  carried out on land within the boundaries of this state that is

14-41  managed by the Federal Government or is on an Indian reservation

14-42  or Indian colony, of not less than $5,000 for each consecutive 12-

14-43  month period for 60 months immediately preceding the submission

14-44  of the affidavit from the certified public accountant;


15-1          (2) The governmental services tax imposed pursuant to

15-2  chapter 371 of NRS on the vehicles used in the operation of his

15-3  business in this state of not less than $5,000 for each consecutive

15-4  12-month period for 60 months immediately preceding the

15-5  submission of the affidavit from the certified public accountant; or

15-6          (3) Any combination of such sales and use taxes and

15-7  governmental services tax; or

15-8      (b) Acquired, by purchase, inheritance, gift or transfer through a

15-9  stock option plan, all the assets and liabilities of a viable, operating

15-10  construction firm that possesses a:

15-11         (1) License as a specialty contractor pursuant to the

15-12  provisions of chapter 624 of NRS; and

15-13         (2) Certificate of eligibility to receive a preference in bidding

15-14  on public works.

15-15     5.  For the purposes of complying with the requirements set

15-16  forth in paragraph (a) of subsection 3 and paragraph (a) of

15-17  subsection 4, a contractor shall be deemed to have paid:

15-18     (a) Sales and use taxes and governmental services taxes that

15-19  were paid in this state by an affiliate or parent company of the

15-20  contractor, if the affiliate or parent company is also a general

15-21  contractor or specialty contractor, as applicable; and

15-22     (b) Sales and use taxes that were paid in this state by a joint

15-23  venture in which the contractor is a participant, in proportion to the

15-24  amount of interest the contractor has in the joint venture.

15-25     6.  A contractor who has received a certificate of eligibility to

15-26  receive a preference in bidding on public works from the State

15-27  Contractors’ Board pursuant to subsection 3 or 4 shall, at the time

15-28  for the annual renewal of his contractor’s license pursuant to NRS

15-29  624.283, submit to the Board an affidavit from a certified public

15-30  accountant setting forth that the contractor has, during the

15-31  immediately preceding 12 months, paid the taxes required pursuant

15-32  to paragraph (a) of subsection 3 or paragraph (a) of subsection 4, as

15-33  applicable, to maintain his eligibility to hold such a certificate.

15-34     7.  A contractor who fails to submit an affidavit to the Board

15-35  pursuant to subsection 6 ceases to be eligible to receive a preference

15-36  in bidding on public works unless he reapplies for and receives a

15-37  certificate of eligibility pursuant to subsection 3 or 4, as applicable.

15-38     8.  If a contractor holds more than one contractor’s license, he

15-39  must submit a separate application for each license pursuant to

15-40  which he wishes to qualify for a preference in bidding. Upon

15-41  issuance, the certificate of eligibility to receive a preference in

15-42  bidding on public works becomes part of the contractor’s license for

15-43  which the contractor submitted the application.

15-44     9.  If a contractor who applies to the State Contractors’ Board

15-45  for a certificate of eligibility to receive a preference in bidding on


16-1  public works submits false information to the Board regarding the

16-2  required payment of taxes, the contractor is not eligible to receive a

16-3  preference in bidding on public works for a period of 5 years after

16-4  the date on which the Board becomes aware of the submission of the

16-5  false information.

16-6      10.  If any federal statute or regulation precludes the granting of

16-7  federal assistance or reduces the amount of that assistance for a

16-8  particular public work because of the provisions of subsection 2,

16-9  those provisions do not apply insofar as their application would

16-10  preclude or reduce federal assistance for that work. The provisions

16-11  of subsection 2 do not apply to any contract for a public work which

16-12  is expected to cost less than $250,000.

16-13     11.  If a bid is submitted by two or more contractors as a joint

16-14  venture or by one of them as a joint venturer, the provisions of

16-15  subsection 2 apply only if both or all of the joint venturers

16-16  separately meet the requirements of that subsection.

16-17     12.  The State Contractors’ Board shall adopt regulations and

16-18  may assess reasonable fees relating to the certification of contractors

16-19  for a preference in bidding on public works.

16-20     13.  A person or entity who believes that a contractor

16-21  wrongfully holds a certificate of eligibility to receive a preference in

16-22  bidding on public works may challenge the validity of the certificate

16-23  by filing a written objection with the public body to which the

16-24  contractor has submitted a bid or proposal on a contract for the

16-25  construction of a public work. A written objection authorized

16-26  pursuant to this subsection must:

16-27     (a) Set forth proof or substantiating evidence to support the

16-28  belief of the person or entity that the contractor wrongfully holds a

16-29  certificate of eligibility to receive a preference in bidding on public

16-30  works; and

16-31     (b) Be filed with the public body at or after the time at which the

16-32  contractor submitted the bid or proposal to the public body and

16-33  before the time at which the public body awards the contract for

16-34  which the bid or proposal was submitted.

16-35     14.  If a public body receives a written objection pursuant to

16-36  subsection 13, the public body shall determine whether the objection

16-37  is accompanied by the proof or substantiating evidence required

16-38  pursuant to paragraph (a) of that subsection. If the public body

16-39  determines that the objection is not accompanied by the required

16-40  proof or substantiating evidence, the public body shall dismiss the

16-41  objection and may proceed immediately to award the contract. If

16-42  the public body determines that the objection is accompanied by the

16-43  required proof or substantiating evidence, the public body shall

16-44  determine whether the contractor qualifies for the certificate


17-1  pursuant to the provisions of this section and may proceed to award

17-2  the contract accordingly.

17-3      Sec. 13.  NRS 338.141 is hereby amended to read as follows:

17-4      338.141  1.  Except as otherwise provided in subsection 2,

17-5  each bid submitted to any officer, department, board or commission

17-6  for the construction of any public work or improvement must

17-7  include:

17-8      (a) The name of each subcontractor who will provide labor or a

17-9  portion of the work or improvement to the contractor for which he

17-10  will be paid an amount exceeding 5 percent of the prime

17-11  contractor’s total bid. Within 2 hours after the completion of the

17-12  opening of the bids, the contractors who submitted the three lowest

17-13  bids must submit a list containing the name of each subcontractor

17-14  who will provide labor or a portion of the work or improvement to

17-15  the contractor for which he will be paid an amount exceeding 1

17-16  percent of the prime contractor’s total bid or $50,000, whichever is

17-17  greater, and the number of the license issued to the subcontractor

17-18  pursuant to chapter 624 of NRS. If a contractor fails to submit such

17-19  a list within the required time, his bid shall be deemed not

17-20  responsive.

17-21     (b) A description of the portion of the work or improvement

17-22  which each subcontractor named in the bid will complete.

17-23     2.  The contractor shall list in his bid pursuant to subsection 1

17-24  the name of a subcontractor for each portion of the project that will

17-25  be completed by a subcontractor.

17-26     3.  A contractor whose bid is accepted shall not substitute any

17-27  person for a subcontractor who is named in the bid, unless:

17-28     (a) The awarding authority objects to the subcontractor, requests

17-29  in writing a change in the subcontractor and pays any increase in

17-30  costs resulting from the change; [or]

17-31     (b) The substitution is approved by the awarding authority or an

17-32  authorized representative of the awarding authority. The substitution

17-33  must be approved if the awarding authority or authorized

17-34  representative of the awarding authority determines that:

17-35         (1) The named subcontractor, after having a reasonable

17-36  opportunity, fails or refuses to execute a written contract with the

17-37  contractor which was offered to the subcontractor with the same

17-38  general terms that all other subcontractors on the project were

17-39  offered;

17-40         (2) The named subcontractor files for bankruptcy or becomes

17-41  insolvent; or

17-42         (3) The named subcontractor fails or refuses to perform his

17-43  subcontract within a reasonable time or is unable to furnish a

17-44  performance bond and payment bond pursuant to NRS 339.025 [.];

17-45  or


18-1      (c) If the awarding body is the governing body of a local

18-2  government, the awarding authority or an authorized

18-3  representative of the awarding body, in awarding a contract for a

18-4  public work pursuant to NRS 338.1375 to 338.139, inclusive, and

18-5  sections 2 and 3 of this act:

18-6          (1) Applies such criteria set forth in NRS 338.1377 as are

18-7  appropriate for subcontractors and determines that the

18-8  subcontractor does not meet that criteria; and

18-9          (2) Requests in writing a substitution of the subcontractor.

18-10     4.  As used in this section, “general terms” means the terms and

18-11  conditions of a contract that set the basic requirements for a project

18-12  and apply without regard to the particular trade or specialty of a

18-13  subcontractor, but does not include any provision that controls or

18-14  relates to the specific portion of the project that will be completed

18-15  by a subcontractor, including, without limitation, the materials to be

18-16  used by the subcontractor or other details of the work to be

18-17  performed by the subcontractor.

18-18     Sec. 14.  1.  This section and sections 1 to 9, inclusive, 11, 12

18-19  and 13 of this act become effective on October 1, 2003.

18-20     2.  Section 9 of this act expires by limitation on April 30, 2013.

18-21     3.  Section 10 of this act becomes effective on May 1, 2013.

 

18-22  H