A.B. 519
Assembly Bill No. 519–Committee on Transportation
(On Behalf of the Department of Transportation)
March 24, 2003
____________
Referred to Committee on Transportation
SUMMARY—Revises provisions relating to awarding of design-build contracts by Department of Transportation. (BDR 35‑542)
FISCAL NOTE: Effect on Local Government: No.
Effect on the State: No.
~
EXPLANATION
– Matter in bolded italics is new; matter
between brackets [omitted material] is material to be omitted.
Green numbers along left margin indicate location on the printed bill (e.g., 5-15 indicates page 5, line 15).
AN ACT relating to the Department of Transportation; authorizing the Department, in carrying out the process for awarding design-build contracts, to request revised final proposals under certain circumstances; establishing procedures for requesting and evaluating revised final proposals; and providing other matters properly relating thereto.
THE PEOPLE OF THE STATE OF NEVADA, REPRESENTED IN
SENATE AND ASSEMBLY, DO ENACT AS FOLLOWS:
1-1 Section 1. Chapter 408 of NRS is hereby amended by adding
1-2 thereto a new section to read as follows:
1-3 1. If the Department determines that no final proposal
1-4 received pursuant to NRS 408.3886 is cost-effective and
1-5 responsive and the Department further determines that requesting
1-6 revised final proposals pursuant to this section will likely result in
1-7 the submission of a satisfactory proposal, the Department shall
1-8 prepare and provide to each finalist a request for revised final
1-9 proposals for the project.
1-10 2. In conjunction with preparing a request for revised final
1-11 proposals pursuant to this section, the Department may:
1-12 (a) Alter the scope of the project; and
2-1 (b) Revise the estimates of the costs of designing and
2-2 constructing the project.
2-3 3. A request for revised final proposals prepared pursuant to
2-4 this section must:
2-5 (a) Set forth the date by which revised final proposals must be
2-6 submitted to the Department;
2-7 (b) If the Department has altered the scope of the project, set
2-8 forth an updated description of the project;
2-9 (c) If the Department has revised the estimates of the costs of
2-10 designing and constructing the project, set forth updated estimates
2-11 for those costs; and
2-12 (d) Set forth the factors that the Department will use to select a
2-13 design-build team to design and construct the project, including
2-14 the relative weight to be assigned to each factor. The factors and
2-15 relative weights required to be set forth pursuant to this paragraph
2-16 need not be the same as those which were set forth in the request
2-17 for final proposals pursuant to NRS 408.3886.
2-18 4. Except as otherwise provided in this subsection, in
2-19 assigning the relative weight to each factor for selecting a design-
2-20 build team pursuant to subsection 3, the Department shall assign,
2-21 without limitation, a relative weight of 5 percent to the possession
2-22 of a certificate of eligibility to receive a preference in bidding on
2-23 public works and a relative weight of at least 30 percent for the
2-24 proposed cost of design and construction of the project. If any
2-25 federal statute or regulation precludes the granting of federal
2-26 assistance or reduces the amount of that assistance for a
2-27 particular project because of the provisions of this subsection
2-28 relating to preference in bidding on public works, those provisions
2-29 of this subsection do not apply insofar as their application would
2-30 preclude or reduce federal assistance for that project.
2-31 5. A revised final proposal submitted by a design-build team
2-32 pursuant to this section must be prepared thoroughly, be
2-33 responsive to the criteria that the Department will use to select a
2-34 design-build team to design and construct the project described in
2-35 subsection 3 and comply with the provisions of NRS 338.141.
2-36 6. After receiving the revised final proposals for the project,
2-37 the Department shall:
2-38 (a) Select the most cost-effective and responsive revised final
2-39 proposal, using the criteria set forth pursuant to subsections 3 and
2-40 4; or
2-41 (b) Reject all the revised final proposals.
2-42 7. If the Department selects a revised final proposal pursuant
2-43 to paragraph (a) of subsection 6, the Department shall hold a
2-44 public meeting to:
2-45 (a) Review and ratify the selection.
3-1 (b) Award the design-build contract to the design-build team
3-2 whose proposal is selected.
3-3 (c) Partially reimburse the unsuccessful finalists who
3-4 submitted revised final proposals if partial reimbursement was
3-5 provided for in the request for preliminary proposals pursuant to
3-6 paragraph (f) of subsection 3 of NRS 408.3883. The amount of
3-7 reimbursement must not exceed, for each unsuccessful finalist
3-8 who submitted a revised final proposal, 3 percent of the total
3-9 amount to be paid to the design-build team as set forth in the
3-10 design-build contract.
3-11 (d) Make available to the public a summary setting forth the
3-12 factors used by the Department to select the successful design-
3-13 build team and the ranking of the design-build teams who
3-14 submitted revised final proposals. The Department shall not
3-15 release to a third party, or otherwise make public, financial or
3-16 proprietary information submitted by a design-build team.
3-17 8. A contract awarded pursuant to this section must specify:
3-18 (a) An amount that is the maximum amount that the
3-19 Department will pay for the performance of all the work required
3-20 by the contract, excluding any amount related to costs that may be
3-21 incurred as a result of unexpected conditions or occurrences as
3-22 authorized by the contract;
3-23 (b) An amount that is the maximum amount that the
3-24 Department will pay for the performance of the professional
3-25 services required by the contract; and
3-26 (c) A date by which performance of the work required by the
3-27 contract must be completed.
3-28 9. A design-build team to whom a contract is awarded
3-29 pursuant to this section shall:
3-30 (a) Assume overall responsibility for ensuring that the design
3-31 and construction of the project is completed in a satisfactory
3-32 manner; and
3-33 (b) Use the workforce of the prime contractor on the design-
3-34 build team to construct at least 15 percent of the project.
3-35 Sec. 2. NRS 408.215 is hereby amended to read as follows:
3-36 408.215 1. The Director has charge of all the records of the
3-37 Department, keeping records of all proceedings pertaining to the
3-38 Department and keeping on file information, plans, specifications,
3-39 estimates, statistics and records prepared by the Department, except
3-40 those financial statements described in NRS 408.333 and the
3-41 financial or proprietary information described in paragraph (d) of
3-42 subsection 5 of NRS 408.3886[,] and paragraph (d) of subsection
3-43 7 of section 1 of this act, which must not become matters of public
3-44 record.
4-1 2. The Director may photograph, microphotograph or film or
4-2 dispose of the records of the Department referred to in subsection 1
4-3 as provided in NRS 239.051, 239.080 and 239.085.
4-4 3. The Director shall maintain an index or record of deeds or
4-5 other references of title or interests in and to all lands or interests in
4-6 land owned or acquired by the Department.
4-7 4. The Director shall adopt such regulations as may be
4-8 necessary to carry out and enforce the provisions of this chapter.
4-9 Sec. 3. NRS 408.3875 is hereby amended to read as follows:
4-10 408.3875 As used in NRS 408.3875 to 408.3887, inclusive,
4-11 and section 1 of this act, unless the context otherwise requires, the
4-12 words and terms defined in NRS 408.3876 to 408.3879, inclusive,
4-13 have the meanings ascribed to them in those sections.
4-14 Sec. 4. NRS 408.3882 is hereby amended to read as follows:
4-15 408.3882 If the Department desires to contract with a design-
4-16 build team pursuant to NRS 408.388 and 408.3881, the Department
4-17 must select the design-build team in accordance with NRS 408.3883
4-18 to 408.3886, inclusive[.] , and section 1 of this act.
4-19 Sec. 5. NRS 408.3883 is hereby amended to read as follows:
4-20 408.3883 1. The Department shall advertise for preliminary
4-21 proposals for the design and construction of a project by a design-
4-22 build team in a newspaper of general circulation in this state.
4-23 2. A request for preliminary proposals published pursuant to
4-24 subsection 1 must include, without limitation:
4-25 (a) A description of the proposed project;
4-26 (b) Separate estimates of the costs of designing and constructing
4-27 the project;
4-28 (c) The dates on which it is anticipated that the separate phases
4-29 of the design and construction of the project will begin and end;
4-30 (d) The date by which preliminary proposals must be submitted
4-31 to the Department, which must not be less than 30 days after the
4-32 date that the request for preliminary proposals is first published in a
4-33 newspaper pursuant to subsection 1; and
4-34 (e) A statement setting forth the place and time in which a
4-35 design-build team desiring to submit a proposal for the project may
4-36 obtain the information necessary to submit a proposal, including,
4-37 without limitation, the information set forth in subsection 3.
4-38 3. The Department shall maintain at the time and place set
4-39 forth in the request for preliminary proposals the following
4-40 information for inspection by a design-build team desiring to submit
4-41 a proposal for the project:
4-42 (a) The extent to which designs must be completed for [both
4-43 preliminary and] preliminary, final and, if applicable, revised final
4-44 proposals and any other requirements for the design and
5-1 construction of the project that the Department determines to be
5-2 necessary;
5-3 (b) A list of the requirements set forth in NRS 408.3884;
5-4 (c) A list of the factors that the Department will use to evaluate
5-5 design-build teams who submit a proposal for the project, including,
5-6 without limitation:
5-7 (1) The relative weight to be assigned to each factor pursuant
5-8 to NRS 408.3886; and
5-9 (2) A disclosure of whether the factors that are not related to
5-10 cost are, when considered as a group, more or less important in the
5-11 process of evaluation than the factor of cost;
5-12 (d) Notice that a design-build team desiring to submit a proposal
5-13 for the project must include with its proposal the information used
5-14 by the Department to determine finalists among the design-build
5-15 teams submitting proposals pursuant to subsection 2 of NRS
5-16 408.3885 and a description of that information;
5-17 (e) A statement that a design-build team whose prime contractor
5-18 holds a certificate of eligibility to receive a preference in bidding on
5-19 public works issued pursuant to NRS 338.1389 or 338.147 should
5-20 submit a copy of the certificate of eligibility with its proposal; and
5-21 (f) A statement as to whether a bidding design-build team that is
5-22 selected as a finalist pursuant to NRS 408.3885 but is not awarded
5-23 the design-build contract pursuant to NRS 408.3886 or section 1 of
5-24 this act will be partially reimbursed for the cost of preparing a final
5-25 proposal or revised final proposal and, if so, an estimate of the
5-26 amount of the partial reimbursement.
5-27 Sec. 6. NRS 408.3886 is hereby amended to read as follows:
5-28 408.3886 1. After selecting the finalists pursuant to NRS
5-29 408.3885, the Department shall provide to each finalist a request for
5-30 final proposals for the project. The request for final proposals must:
5-31 (a) Set forth the factors that the Department will use to select a
5-32 design-build team to design and construct the project, including the
5-33 relative weight to be assigned to each factor; and
5-34 (b) Set forth the date by which final proposals must be
5-35 submitted to the Department.
5-36 2. Except as otherwise provided in this subsection, in assigning
5-37 the relative weight to each factor for selecting a design-build team
5-38 pursuant to subsection 1, the Department shall assign, without
5-39 limitation, a relative weight of 5 percent to the possession of a
5-40 certificate of eligibility to receive a preference in bidding on public
5-41 works and a relative weight of at least 30 percent for the proposed
5-42 cost of design and construction of the project. If any federal statute
5-43 or regulation precludes the granting of federal assistance or reduces
5-44 the amount of that assistance for a particular project because of the
5-45 provisions of this subsection relating to preference in bidding on
6-1 public works, those provisions of this subsection do not apply
6-2 insofar as their application would preclude or reduce federal
6-3 assistance for that project.
6-4 3. A final proposal submitted by a design-build team pursuant
6-5 to this section must be prepared thoroughly, be responsive to the
6-6 criteria that the Department will use to select a design-build team to
6-7 design and construct the project described in subsection 1 and
6-8 comply with the provisions of NRS 338.141.
6-9 4. After receiving the final proposals for the project, the
6-10 Department shall:
6-11 (a) Select the most cost-effective and responsive final proposal,
6-12 using the criteria set forth pursuant to subsections 1 and 2; [or]
6-13 (b) Reject all the final proposals[.] ; or
6-14 (c) Request revised final proposals pursuant to section 1 of this
6-15 act.
6-16 5. If the Department selects a final proposal pursuant to
6-17 paragraph (a) of subsection 4, the Department shall hold a public
6-18 meeting to:
6-19 (a) Review and ratify the selection.
6-20 (b) Award the design-build contract to the design-build team
6-21 whose proposal is selected.
6-22 (c) Partially reimburse the unsuccessful finalists if partial
6-23 reimbursement was provided for in the request for preliminary
6-24 proposals pursuant to paragraph (f) of subsection 3 of NRS
6-25 408.3883. The amount of reimbursement must not exceed, for each
6-26 unsuccessful finalist, [three] 3 percent of the total amount to be paid
6-27 to the design-build team as set forth in the design-build contract.
6-28 (d) Make available to the public a summary setting forth the
6-29 factors used by the Department to select the successful design-build
6-30 team and the ranking of the design-build teams who submitted final
6-31 proposals. The Department shall not release to a third party, or
6-32 otherwise make public, financial or proprietary information
6-33 submitted by a design-build team.
6-34 6. A contract awarded pursuant to this section must specify:
6-35 (a) An amount that is the maximum amount that the Department
6-36 will pay for the performance of all the work required by the
6-37 contract, excluding any amount related to costs that may be incurred
6-38 as a result of unexpected conditions or occurrences as authorized by
6-39 the contract;
6-40 (b) An amount that is the maximum amount that the Department
6-41 will pay for the performance of the professional services required by
6-42 the contract; and
6-43 (c) A date by which performance of the work required by the
6-44 contract must be completed.
7-1 7. A design-build team to whom a contract is awarded pursuant
7-2 to this section shall:
7-3 (a) Assume overall responsibility for ensuring that the design
7-4 and construction of the project is completed in a satisfactory
7-5 manner; and
7-6 (b) Use the workforce of the prime contractor on the design-
7-7 build team to construct at least 15 percent of the project.
7-8 H