S.B. 491
Senate Bill No. 491–Committee on Government Affairs
(On Behalf of the Public Works Board)
March 24, 2003
____________
Referred to Committee on Government Affairs
SUMMARY—Makes various changes regarding bidding on contracts for public works of this state. (BDR 28‑487)
FISCAL NOTE: Effect on Local Government: No.
Effect on the State: No.
~
EXPLANATION
– Matter in bolded italics is new; matter
between brackets [omitted material] is material to be omitted.
Green numbers along left margin indicate location on the printed bill (e.g., 5-15 indicates page 5, line 15).
AN ACT relating to public works; requiring certain subcontractors to become qualified to be subcontractors on contracts for public works; revising the criteria that the State Public Works Board is required to adopt for the qualification of bidders on contracts for public works; authorizing the Board and the governing body of a local government to issue subpoenas relating to hearings on denials of applications for qualification to bid on or be subcontractors on contracts for public works; specifying the burden of proof in such hearings; revising the provisions governing the awarding of design-build contracts; and providing other matters properly relating thereto.
THE PEOPLE OF THE STATE OF NEVADA, REPRESENTED IN
SENATE AND ASSEMBLY, DO ENACT AS FOLLOWS:
1-1 Section 1. NRS 338.1375 is hereby amended to read as
1-2 follows:
1-3 338.1375 1. The State Public Works Board shall not accept a
1-4 bid on a contract for a public work unless the person who submits
1-5 the bid [has] and each subcontractor who will provide labor or a
1-6 portion of the work or improvement to the contractor for which
2-1 the subcontractor will be paid an amount exceeding 5 percent of
2-2 the prime contractor’s total bid are qualified pursuant to NRS
2-3 338.1379 to bid on or be a subcontractor on that contract.
2-4 2. The State Public Works Board shall by regulation adopt
2-5 criteria for the qualification of bidders and subcontractors on
2-6 contracts for public works of this state. The criteria adopted by the
2-7 State Public Works Board pursuant to this section must be used by
2-8 the State Public Works Board to determine the qualification of
2-9 bidders and subcontractors on contracts for public works of this
2-10 state.
2-11 3. The criteria adopted by the State Public Works Board
2-12 pursuant to this section:
2-13 (a) Must be adopted in such a form that the determination of
2-14 whether an applicant is qualified to bid on or be a subcontractor on
2-15 a contract for a public work does not require or allow the exercise of
2-16 discretion by any one person.
2-17 (b) May include [only:] , but is not limited to:
2-18 (1) The financial ability of the applicant to perform a
2-19 contract[;] or subcontract, as applicable;
2-20 (2) The principal personnel of the applicant;
2-21 (3) Whether the applicant has breached any contracts or
2-22 subcontracts, as applicable, with a public agency or person in this
2-23 state or any other state;
2-24 (4) [Whether] If the applicant is a prime contractor,
2-25 whether the applicant has been disqualified from being awarded a
2-26 contract pursuant to NRS 338.017 or 338.1387; [and]
2-27 (5) The performance history of the applicant concerning any
2-28 other recent, similar contracts[, if any,] or subcontracts, as
2-29 applicable, completed by the applicant[.] ; and
2-30 (6) The truthfulness and completeness of the application.
2-31 Sec. 2. NRS 338.1379 is hereby amended to read as follows:
2-32 338.1379 1. Except as otherwise provided in NRS 338.1383,
2-33 a person who wishes to qualify as [a] :
2-34 (a) A bidder on a contract for a public work must submit an
2-35 application to the State Public Works Board or the governing body.
2-36 (b) A subcontractor on a contract for a public work of this
2-37 state must submit an application to the State Public Works Board.
2-38 2. Upon receipt of an application pursuant to subsection 1, the
2-39 State Public Works Board or the governing body shall:
2-40 (a) Investigate the applicant to determine whether he is qualified
2-41 to bid on or be a subcontractor, as applicable, on a contract; and
2-42 (b) After conducting the investigation, determine whether the
2-43 applicant is qualified to bid on or be a subcontractor, as applicable,
2-44 on such a contract. The determination must be made within [30] 45
2-45 days after receipt of the application.
3-1 3. The State Public Works Board or the governing body shall
3-2 notify each applicant in writing of its determination. If an
3-3 application is denied, the notice must set forth the reasons for the
3-4 denial and inform the applicant of his right to a hearing pursuant to
3-5 NRS 338.1381.
3-6 4. The State Public Works Board or the governing body of a
3-7 local government may determine an applicant is qualified to bid[:]
3-8 or be a subcontractor, as applicable:
3-9 (a) On a specific project;
3-10 (b) On more than one project over a period of 12 months; or
3-11 (c) On more than one project over a period of 24 months.
3-12 5. The State Public Works Board shall not use any criteria
3-13 other than criteria adopted by regulation pursuant to NRS 338.1375
3-14 in determining whether to approve or deny an application.
3-15 6. The governing body of a local government shall not use any
3-16 criteria other than the criteria described in NRS 338.1377 in
3-17 determining whether to approve or deny an application.
3-18 7. Financial information and other data pertaining to the net
3-19 worth of an applicant which is gathered by or provided to the State
3-20 Public Works Board or a governing body to determine the financial
3-21 ability of an applicant to perform a contract or be a subcontractor
3-22 on a contract, as applicable, is confidential and not open to public
3-23 inspection.
3-24 Sec. 3. NRS 338.1381 is hereby amended to read as follows:
3-25 338.1381 1. If, within 10 days after receipt of the notice
3-26 denying his application, the applicant files a written request for a
3-27 hearing with the State Public Works Board or the governing body of
3-28 the local government, the Board or governing body shall set the
3-29 matter for a hearing within [10] 20 days after receipt of the request.
3-30 The hearing must be held not later than [20] 45 days after the receipt
3-31 of the request for a hearing[.] unless the parties, by written
3-32 stipulation, agree to extend the time.
3-33 2. The hearing must be held at a time and place prescribed by
3-34 the Board or governing body. At least 10 days before the date set for
3-35 the hearing, the Board or governing body shall serve the applicant
3-36 with written notice of the hearing. The notice may be served by
3-37 personal delivery to the applicant or by certified mail to the last
3-38 known business or residential address of the applicant.
3-39 3. The applicant has the burden at the hearing of proving by
3-40 substantial evidence that the applicant is entitled to be qualified to
3-41 bid on or be a subcontractor on, as applicable, a contract for a
3-42 public work.
3-43 4. In conducting a hearing pursuant to this subsection, the
3-44 Board or the governing body of a local government may:
3-45 (a) Administer oaths;
4-1 (b) Take testimony;
4-2 (c) Issue subpoenas to compel the attendance of witnesses to
4-3 testify before the Board or governing body;
4-4 (d) Require the production of related books, papers and
4-5 documents; and
4-6 (e) Issue commissions to take testimony.
4-7 5. If a witness refuses to attend or testify or produce books,
4-8 papers or documents as required by the subpoena issued pursuant
4-9 to subsection 4, the Board or governing body may petition the
4-10 district court to order the witness to appear or testify or produce
4-11 the requested books, papers or documents.
4-12 6. The Board or governing body shall issue a decision on the
4-13 matter within 5 days after the hearing and notify the applicant, in
4-14 writing, of its decision within [5] 15 days after it is issued. The
4-15 decision of the Board or governing body is a final decision for
4-16 purposes of judicial review.
4-17 Sec. 4. NRS 338.1385 is hereby amended to read as follows:
4-18 338.1385 1. Except as otherwise provided in subsection 7
4-19 and NRS 338.1906 and 338.1907, this state, or a local government
4-20 that awards a contract for the construction, alteration or repair of a
4-21 public work in accordance with paragraph (a) of subsection 1 of
4-22 NRS 338.1373, or a public officer, public employee or other person
4-23 responsible for awarding a contract for the construction, alteration
4-24 or repair of a public work who represents the State or the local
4-25 government, shall not:
4-26 (a) Commence such a project for which the estimated cost
4-27 exceeds $100,000 unless it advertises in a newspaper of general
4-28 circulation in this state for bids for the project; or
4-29 (b) Divide such a project into separate portions to avoid the
4-30 requirements of paragraph (a).
4-31 2. Except as otherwise provided in subsection 7, a public body
4-32 that maintains a list of properly licensed contractors who are
4-33 interested in receiving offers to bid on public works projects for
4-34 which the estimated cost is more than $25,000 but less than
4-35 $100,000 shall solicit bids from not more than three of the
4-36 contractors on the list for a contract of that value for the
4-37 construction, alteration or repair of a public work. The public body
4-38 shall select contractors from the list in such a manner as to afford
4-39 each contractor an equal opportunity to bid on a public works
4-40 project. A properly licensed contractor must submit a written
4-41 request annually to the public body to remain on the list. Offers for
4-42 bids which are made pursuant to this subsection must be sent by
4-43 certified mail.
4-44 3. Each advertisement for bids must include a provision that
4-45 sets forth:
5-1 (a) The requirement that [a] :
5-2 (1) A contractor must be qualified pursuant to NRS 338.1379
5-3 to bid on the contract or must be exempt from meeting such
5-4 qualifications pursuant to NRS 338.1383; and
5-5 (2) If the contract is for a public work of this state, each
5-6 subcontractor who will provide labor or a portion of the work or
5-7 improvement to the contractor for which the subcontractor will be
5-8 paid an amount exceeding 5 percent of the prime contractor’s total
5-9 bid must be qualified pursuant to NRS 338.1379 to be a
5-10 subcontractor on the contract; and
5-11 (b) The period during which an application to qualify as a bidder
5-12 or a subcontractor on the contract must be submitted.
5-13 4. Approved plans and specifications for the bids must be on
5-14 file at a place and time stated in the advertisement for the inspection
5-15 of all persons desiring to bid thereon and for other interested
5-16 persons. Contracts for the project must be awarded on the basis of
5-17 bids received.
5-18 5. Any bids received in response to an advertisement for bids
5-19 may be rejected if the person responsible for awarding the contract
5-20 determines that:
5-21 (a) The bidder is not a qualified bidder pursuant to NRS
5-22 338.1379, unless the bidder is exempt from meeting such
5-23 qualifications pursuant to NRS 338.1383;
5-24 (b) If the contract is for a public work of this state, a
5-25 subcontractor who will provide labor or a portion of the work or
5-26 improvement to the contractor for which the subcontractor will be
5-27 paid an amount exceeding 5 percent of the prime contractor’s total
5-28 bid is not a qualified subcontractor pursuant to NRS 338.1379;
5-29 (c) The bidder is not responsive;
5-30 [(c)] (d) The quality of the services, materials, equipment or
5-31 labor offered does not conform to the approved plan or
5-32 specifications; or
5-33 [(d)] (e) The public interest would be served by such a rejection.
5-34 6. Before the State or a local government may commence a
5-35 project subject to the provisions of this section, based upon a
5-36 determination that the public interest would be served by rejecting
5-37 any bids received in response to an advertisement for bids, it shall
5-38 prepare and make available for public inspection a written statement
5-39 containing:
5-40 (a) A list of all persons, including supervisors, whom the State
5-41 or the local government intends to assign to the project, together
5-42 with their classifications and an estimate of the direct and indirect
5-43 costs of their labor;
5-44 (b) A list of all equipment that the State or the local government
5-45 intends to use on the project, together with an estimate of the
6-1 number of hours each item of equipment will be used and the hourly
6-2 cost to use each item of equipment;
6-3 (c) An estimate of the cost of administrative support for the
6-4 persons assigned to the project;
6-5 (d) An estimate of the total cost of the project; and
6-6 (e) An estimate of the amount of money the State or the local
6-7 government expects to save by rejecting the bids and performing the
6-8 project itself.
6-9 7. This section does not apply to:
6-10 (a) Any utility subject to the provisions of chapter 318 or 710 of
6-11 NRS;
6-12 (b) Any work of construction, reconstruction, improvement and
6-13 maintenance of highways subject to NRS 408.323 or 408.327;
6-14 (c) Normal maintenance of the property of a school district;
6-15 (d) The Las Vegas Valley Water District created pursuant to
6-16 chapter 167, Statutes of Nevada 1947, the Moapa Valley Water
6-17 District created pursuant to chapter 477, Statutes of Nevada 1983 or
6-18 the Virgin Valley Water District created pursuant to chapter 100,
6-19 Statutes of Nevada 1993; or
6-20 (e) The design and construction of a public work for which a
6-21 public body contracts with a design-build team pursuant to NRS
6-22 338.1711 to 338.1727.
6-23 Sec. 5. NRS 338.1385 is hereby amended to read as follows:
6-24 338.1385 1. Except as otherwise provided in subsection 8,
6-25 this state, or a local government that awards a contract for the
6-26 construction, alteration or repair of a public work in accordance with
6-27 paragraph (a) of subsection 1 of NRS 338.1373, or a public officer,
6-28 public employee or other person responsible for awarding a contract
6-29 for the construction, alteration or repair of a public work who
6-30 represents the State or the local government, shall not:
6-31 (a) Commence such a project for which the estimated cost
6-32 exceeds $100,000 unless it advertises in a newspaper of general
6-33 circulation in this state for bids for the project; or
6-34 (b) Divide such a project into separate portions to avoid the
6-35 requirements of paragraph (a).
6-36 2. Except as otherwise provided in subsection 8, a public body
6-37 that maintains a list of properly licensed contractors who are
6-38 interested in receiving offers to bid on public works projects for
6-39 which the estimated cost is more than $25,000 but less than
6-40 $100,000 shall solicit bids from not more than three of the
6-41 contractors on the list for a contract of that value for the
6-42 construction, alteration or repair of a public work. The public body
6-43 shall select contractors from the list in such a manner as to afford
6-44 each contractor an equal opportunity to bid on a public works
6-45 project. A properly licensed contractor must submit a written
7-1 request annually to the public body to remain on the list. Offers for
7-2 bids which are made pursuant to this subsection must be sent by
7-3 certified mail.
7-4 3. Each advertisement for bids must include a provision that
7-5 sets forth:
7-6 (a) The requirement that [a]
7-7 (1) A contractor must be qualified pursuant to NRS 338.1379
7-8 to bid on the contract or must be exempt from meeting such
7-9 qualifications pursuant to NRS 338.1383; and
7-10 (2) If the contract is for a public work of this state, each
7-11 subcontractor who will provide labor or a portion of the work or
7-12 improvement to the contractor for which the subcontractor will be
7-13 paid an amount exceeding 5 percent of the prime contractor’s total
7-14 bid must be qualified pursuant to NRS 338.1379 to be a
7-15 subcontractor on the contract; and
7-16 (b) The period during which an application to qualify as a bidder
7-17 or subcontractor on the contract must be submitted.
7-18 4. Approved plans and specifications for the bids must be on
7-19 file at a place and time stated in the advertisement for the inspection
7-20 of all persons desiring to bid thereon and for other interested
7-21 persons. Contracts for the project must be awarded on the basis of
7-22 bids received.
7-23 5. Any bids received in response to an advertisement for bids
7-24 may be rejected if the person responsible for awarding the contract
7-25 determines that:
7-26 (a) The bidder is not a qualified bidder pursuant to NRS
7-27 338.1379, unless the bidder is exempt from meeting such
7-28 qualifications pursuant to NRS 338.1383;
7-29 (b) If the contract is for a public work of this state, a
7-30 subcontractor who will provide labor or a portion of the work or
7-31 improvement to the contractor for which the subcontractor will be
7-32 paid an amount exceeding 5 percent of the prime contractor’s total
7-33 bid is not a qualified subcontractor pursuant to NRS 338.1379;
7-34 (c) The bidder is not responsive;
7-35 [(c)] (d) The quality of the services, materials, equipment or
7-36 labor offered does not conform to the approved plan or
7-37 specifications; or
7-38 [(d)] (e) The public interest would be served by such a rejection.
7-39 6. Before the State or a local government may commence a
7-40 project subject to the provisions of this section, based upon a
7-41 determination that the public interest would be served by rejecting
7-42 any bids received in response to an advertisement for bids, it shall
7-43 prepare and make available for public inspection a written statement
7-44 containing:
8-1 (a) A list of all persons, including supervisors, whom the State
8-2 or the local government intends to assign to the project, together
8-3 with their classifications and an estimate of the direct and indirect
8-4 costs of their labor;
8-5 (b) A list of all equipment that the State or the local government
8-6 intends to use on the project, together with an estimate of the
8-7 number of hours each item of equipment will be used and the hourly
8-8 cost to use each item of equipment;
8-9 (c) An estimate of the cost of administrative support for the
8-10 persons assigned to the project;
8-11 (d) An estimate of the total cost of the project; and
8-12 (e) An estimate of the amount of money the State or the local
8-13 government expects to save by rejecting the bids and performing the
8-14 project itself.
8-15 7. In preparing the estimated cost of a project pursuant to
8-16 subsection 6, the State or a local government must include the fair
8-17 market value of, or, if known, the actual cost of, all materials,
8-18 supplies, labor and equipment to be used for the project.
8-19 8. This section does not apply to:
8-20 (a) Any utility subject to the provisions of chapter 318 or 710 of
8-21 NRS;
8-22 (b) Any work of construction, reconstruction, improvement and
8-23 maintenance of highways subject to NRS 408.323 or 408.327;
8-24 (c) Normal maintenance of the property of a school district; or
8-25 (d) The Las Vegas Valley Water District created pursuant to
8-26 chapter 167, Statutes of Nevada 1947, the Moapa Valley Water
8-27 District created pursuant to chapter 477, Statutes of Nevada 1983 or
8-28 the Virgin Valley Water District created pursuant to chapter 100,
8-29 Statutes of Nevada 1993; or
8-30 (e) The design and construction of a public work for which a
8-31 public body contracts with a design-build team pursuant to NRS
8-32 338.1711 to 338.1727, inclusive.
8-33 Sec. 6. NRS 338.1387 is hereby amended to read as follows:
8-34 338.1387 1. A public body awarding a contract for a public
8-35 work shall not award the contract to a person who, at the time of the
8-36 bid, is not properly licensed under the provisions of chapter 624 of
8-37 NRS or if the contract would exceed the limit of his license. A
8-38 subcontractor named by the contractor who will provide labor or a
8-39 portion of the work or improvement to the contractor for which
8-40 the subcontractor will be paid an amount not exceeding 5 percent
8-41 of the prime contractor’s total bid and who is not properly licensed
8-42 for that portion of the work shall be deemed unacceptable. If [the]
8-43 such a subcontractor is deemed unacceptable, the contractor shall
8-44 provide an acceptable subcontractor before the award of the
8-45 contract.
9-1 2. If, after awarding the contract, the public body discovers
9-2 that the person to whom the contract was awarded is not licensed, or
9-3 that the contract would exceed his license, the public body shall
9-4 reject the bid and may accept the next lowest bid for that public
9-5 work from a responsive bidder who was determined by the public
9-6 body to be a qualified bidder pursuant to NRS 338.1379 or was
9-7 exempt from meeting such qualifications pursuant to NRS 338.1373
9-8 or 338.1383 without requiring that new bids be submitted.
9-9 Sec. 7. NRS 338.141 is hereby amended to read as follows:
9-10 338.141 1. Except as otherwise provided in subsection 2[,]
9-11 and NRS 338.1727, each bid submitted to any officer, department,
9-12 board or commission for the construction of any public work or
9-13 improvement must include:
9-14 (a) The name of each subcontractor who is qualified pursuant
9-15 to NRS 338.1379 to be a subcontractor on a contract for a public
9-16 work and who will provide labor or a portion of the work or
9-17 improvement to the contractor for which he will be paid an amount
9-18 exceeding 5 percent of the prime contractor’s total bid. Within 2
9-19 hours after the completion of the opening of the bids, the contractors
9-20 who submitted the three lowest bids must submit a list containing
9-21 the name of each subcontractor who will provide labor or a portion
9-22 of the work or improvement to the contractor for which he will be
9-23 paid an amount exceeding 1 percent of the prime contractor’s total
9-24 bid or $50,000, whichever is greater, and the number of the license
9-25 issued to the subcontractor pursuant to chapter 624 of NRS. If a
9-26 contractor fails to submit such a list within the required time, his bid
9-27 shall be deemed not responsive.
9-28 (b) A description of the portion of the work or improvement
9-29 which each subcontractor named in the bid will complete.
9-30 2. The contractor shall list in his bid pursuant to subsection 1
9-31 the name of a subcontractor for each portion of the project that will
9-32 be completed by a subcontractor.
9-33 3. A contractor whose bid is accepted shall not substitute any
9-34 person for a subcontractor who is named in the bid, unless:
9-35 (a) The awarding authority objects to the subcontractor, requests
9-36 in writing a change in the subcontractor and pays any increase in
9-37 costs resulting from the change; or
9-38 (b) The substitution is approved by the awarding authority or an
9-39 authorized representative of the awarding authority. The substitution
9-40 must be approved if the awarding authority or authorized
9-41 representative of the awarding authority determines that:
9-42 (1) The named subcontractor, after having a reasonable
9-43 opportunity, fails or refuses to execute a written contract with the
9-44 contractor which was offered to the subcontractor with the same
10-1 general terms that all other subcontractors on the project were
10-2 offered;
10-3 (2) The named subcontractor files for bankruptcy or becomes
10-4 insolvent; or
10-5 (3) The named subcontractor fails or refuses to perform his
10-6 subcontract within a reasonable time or is unable to furnish a
10-7 performance bond and payment bond pursuant to NRS 339.025.
10-8 4. As used in this section, “general terms” means the terms and
10-9 conditions of a contract that set the basic requirements for a project
10-10 and apply without regard to the particular trade or specialty of a
10-11 subcontractor, but does not include any provision that controls or
10-12 relates to the specific portion of the project that will be completed
10-13 by a subcontractor, including, without limitation, the materials to be
10-14 used by the subcontractor or other details of the work to be
10-15 performed by the subcontractor.
10-16 Sec. 8. NRS 338.1721 is hereby amended to read as follows:
10-17 338.1721 To qualify to participate in a project for the design
10-18 and construction of a public work, a design-build team must:
10-19 1. Obtain a performance bond and payment bond as required
10-20 pursuant to NRS 339.025;
10-21 2. Obtain insurance covering general liability and liability for
10-22 errors and omissions;
10-23 3. Not have been found liable for breach of contract with
10-24 respect to a previous project, other than a breach for legitimate
10-25 cause;
10-26 4. Not have been disqualified from being awarded a contract
10-27 pursuant to NRS 338.017, 338.1387, 338.145 or 408.333; [and]
10-28 5. Ensure that the members of the design-build team possess
10-29 the licenses and certificates required to carry out the functions of
10-30 their respective professions within this state[.] ; and
10-31 6. Ensure that the prime contractor is qualified to bid on a
10-32 public work pursuant to NRS 338.1379 or is exempt from meeting
10-33 such qualifications pursuant to NRS 338.1383.
10-34 Sec. 9. NRS 338.1723 is hereby amended to read as follows:
10-35 338.1723 1. A public body shall advertise for preliminary
10-36 proposals for the design and construction of a public work by a
10-37 design-build team in a newspaper of general circulation in this state.
10-38 2. A request for preliminary proposals published pursuant to
10-39 subsection 1 must include, without limitation:
10-40 (a) A description of the public work to be designed and
10-41 constructed;
10-42 (b) Separate estimates of the costs of designing and constructing
10-43 the public work;
11-1 (c) The dates on which it is anticipated that the separate phases
11-2 of the design and construction of the public work will begin and
11-3 end;
11-4 (d) The date by which preliminary proposals must be submitted
11-5 to the public body, which must not be less than 30 days after the
11-6 date that the request for preliminary proposals is first published in a
11-7 newspaper pursuant to subsection 1; [and]
11-8 (e) A statement setting forth the place and time in which a
11-9 design-build team desiring to submit a proposal for the public work
11-10 may obtain the information necessary to submit a proposal,
11-11 including, without limitation, the information set forth in subsection
11-12 3[.] ; and
11-13 (f) A statement setting forth that the prime contractor must be
11-14 qualified to bid on a public work pursuant to NRS 338.1379 or be
11-15 exempt from meeting such qualifications pursuant to NRS
11-16 338.1383 before submitting a preliminary proposal.
11-17 3. A public body shall maintain at the time and place set forth
11-18 in the request for preliminary proposals the following information
11-19 for inspection by a design-build team desiring to submit a proposal
11-20 for the public work:
11-21 (a) The extent to which designs must be completed for both
11-22 preliminary and final proposals and any other requirements for the
11-23 design and construction of the public work that the public body
11-24 determines to be necessary;
11-25 (b) A list of the requirements set forth in NRS 338.1721;
11-26 (c) A list of the factors that the public body will use to evaluate
11-27 design-build teams who submit a proposal for the public work,
11-28 including, without limitation:
11-29 (1) The relative weight to be assigned to each factor pursuant
11-30 to NRS 338.1727; and
11-31 (2) A disclosure of whether the factors that are not related to
11-32 cost are, when considered as a group, more or less important in the
11-33 process of evaluation than the factor of cost;
11-34 (d) Notice that a design-build team desiring to submit a proposal
11-35 for the public work must include with its proposal the information
11-36 used by the public body to determine finalists among the design-
11-37 build teams submitting proposals pursuant to subsection 2 of NRS
11-38 338.1725 and a description of that information;
11-39 (e) A statement that a design-build team whose prime contractor
11-40 holds a certificate of eligibility to receive a preference in bidding on
11-41 public works issued pursuant to NRS 338.1389 or 338.147 should
11-42 submit a copy of the certificate of eligibility with its proposal; and
11-43 (f) A statement as to whether a design-build team that is selected
11-44 as a finalist pursuant to NRS 338.1725 but is not awarded the
11-45 design-build contract pursuant to NRS 338.1727 will be partially
12-1 reimbursed for the cost of preparing a final proposal and, if so, an
12-2 estimate of the amount of the partial reimbursement.
12-3 Sec. 10. NRS 338.1727 is hereby amended to read as follows:
12-4 338.1727 1. After selecting the finalists pursuant to NRS
12-5 338.1725, the public body shall provide to each finalist a request for
12-6 final proposals for the public work. The request for final proposals
12-7 must:
12-8 (a) Set forth the factors that the public body will use to select a
12-9 design-build team to design and construct the public work, including
12-10 the relative weight to be assigned to each factor; and
12-11 (b) Set forth the date by which final proposals must be
12-12 submitted to the public body.
12-13 2. If one or more of the finalists selected pursuant to NRS
12-14 338.1725 is disqualified or withdraws, the public body may select a
12-15 design-build team from the remaining finalists if at least two
12-16 finalists remain.
12-17 3. Except as otherwise provided in this subsection, in assigning
12-18 the relative weight to each factor for selecting a design-build team
12-19 pursuant to subsection 1, the public body shall assign, without
12-20 limitation, a relative weight of 5 percent to the possession of a
12-21 certificate of eligibility to receive a preference in bidding on public
12-22 works and a relative weight of at least 30 percent to the proposed
12-23 cost of design and construction of the public work. If any federal
12-24 statute or regulation precludes the granting of federal assistance or
12-25 reduces the amount of that assistance for a particular public work
12-26 because of the provisions of this subsection relating to preference in
12-27 bidding on public works, those provisions of this subsection do not
12-28 apply insofar as their application would preclude or reduce federal
12-29 assistance for that public work.
12-30 [3.] 4. A final proposal submitted by a design-build team
12-31 pursuant to this section must be prepared thoroughly[,] and be
12-32 responsive to the criteria that the public body will use to select a
12-33 design-build team to design and construct the public work described
12-34 in subsection 1 . [and comply with the provisions] A final proposal
12-35 is exempt from the requirements of NRS 338.141.
12-36 [4.] 5. After receiving the final proposals for the public work,
12-37 the public body shall:
12-38 (a) Select the most cost-effective and responsive final proposal,
12-39 using the criteria set forth pursuant to subsections 1 and [2;] 3; or
12-40 (b) Reject all the final proposals.
12-41 [5.] 6. If a public body selects a final proposal pursuant to
12-42 paragraph (a) of subsection [4,] 5, the public body shall, at its next
12-43 regularly scheduled meeting:
12-44 (a) Review and ratify the selection.
13-1 (b) Award the design-build contract to the design-build team
13-2 whose proposal is selected.
13-3 (c) Partially reimburse the unsuccessful finalists if partial
13-4 reimbursement was provided for in the request for preliminary
13-5 proposals pursuant to paragraph (f) of subsection 3 of NRS
13-6 338.1723. The amount of reimbursement must not exceed, for each
13-7 unsuccessful finalist, 3 percent of the total amount to be paid to the
13-8 design-build team as set forth in the design-build contract.
13-9 (d) Make available to the public a summary setting forth the
13-10 factors used by the public body to select the successful design-build
13-11 team and the ranking of the design-build teams who submitted final
13-12 proposals. The public body shall not release to a third party, or
13-13 otherwise make public, financial or proprietary information
13-14 submitted by a design-build team.
13-15 [6.] 7. A contract awarded pursuant to this section:
13-16 (a) Must specify:
13-17 (1) An amount that is the maximum amount that the public
13-18 body will pay for the performance of all the work required by the
13-19 contract, excluding any amount related to costs that may be incurred
13-20 as a result of unexpected conditions or occurrences as authorized by
13-21 the contract;
13-22 (2) An amount that is the maximum amount that the public
13-23 body will pay for the performance of the professional services
13-24 required by the contract; and
13-25 (3) A date by which performance of the work required by the
13-26 contract must be completed.
13-27 (b) May set forth the terms by which the design-build team
13-28 agrees to name the public body, at the cost of the public body, as an
13-29 additional insured in an insurance policy held by the design-build
13-30 team.
13-31 (c) Except as otherwise provided in paragraph (d), must not
13-32 require the design professional to defend, indemnify or hold
13-33 harmless the public body or the employees, officers or agents of that
13-34 public body from any liability, damage, loss, claim, action or
13-35 proceeding caused by the negligence, errors, omissions, recklessness
13-36 or intentional misconduct of the employees, officers and agents of
13-37 the public body.
13-38 (d) May require the design-build team to defend, indemnify and
13-39 hold harmless the public body, and the employees, officers and
13-40 agents of the public body from any liabilities, damages, losses,
13-41 claims, actions or proceedings, including, without limitation,
13-42 reasonable attorneys’ fees, that are caused by the negligence, errors,
13-43 omissions, recklessness or intentional misconduct of the design-
13-44 build team or the employees or agents of the design-build team in
13-45 the performance of the contract.
14-1 [7.] 8. Any provision of a contract that is in violation of
14-2 paragraph (c) of subsection [6] 7 is declared to be contrary to the
14-3 public policy of this state and is void.
14-4 [8.] 9. A design-build team to whom a contract is awarded
14-5 pursuant to this section shall:
14-6 (a) Assume overall responsibility for ensuring that the design
14-7 and construction of the public work is completed in a satisfactory
14-8 manner; and
14-9 (b) Use the workforce of the prime contractor on the design-
14-10 build team to construct at least 15 percent of the public work.
14-11 Sec. 11. 1. This section and sections 1 to 4, inclusive, and 6
14-12 to 10, inclusive, of this act become effective upon passage and
14-13 approval.
14-14 2. Section 4 of this act expires by limitation on April 30, 2013.
14-15 3. Section 5 of this act becomes effective on May 1, 2013.
14-16 H